Mayville-Portland School District No. 10 v. C. L. Linfoot Co.

261 N.W.2d 907, 1978 N.D. LEXIS 203
CourtNorth Dakota Supreme Court
DecidedJanuary 19, 1978
DocketCiv. 9386
StatusPublished
Cited by9 cases

This text of 261 N.W.2d 907 (Mayville-Portland School District No. 10 v. C. L. Linfoot Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mayville-Portland School District No. 10 v. C. L. Linfoot Co., 261 N.W.2d 907, 1978 N.D. LEXIS 203 (N.D. 1978).

Opinions

ERICKSTAD, Chief Justice.

This is an appeal by C. L. Linfoot Company, a North Dakota corporation, defendant and appellant, (hereinafter Linfoot) from a judgment of the Traill County District Court which found in favor of the Mayville-Portland School District No. 10, plaintiff and appellee, (hereinafter School District) and against Linfoot.

The basic facts in this case are not in dispute. On May 28, 1974, Linfoot and the School District entered into a written contract wherein Linfoot agreed to furnish all materials and perform the plumbing work shown on the drawings and specifications for a new school, including the installation of an underground fiberglass water storage tank with appurtenant pipes and fixtures. (The dispute in this case involves the installation of the fiberglass storage tank.) The written contract consisted of several documents together with plans, drawings and specifications. The plans, drawings and specifications were furnished by the architect and the engineer and not by Linfoot. The contract also required Linfoot to follow the specifications of Owens/Corning, the manufacturer of the fiberglass tank, in the installation of the tank.

The fiberglass tank was supplied by and installed by Linfoot in the ground at the school site in the latter part of November, and the early part of December, 1974. It was understood by the parties at the time the tank was backfilled in December that the tank site would have to be partially re-excavated the following spring to complete work on the tank installation. This additional work consisted basically of installing a manway extension on the tank and a change order for some other work. When the tank site was uncovered by Lin-foot on June 3, 1975, it was discovered that the tank was severely damaged and unfit for its intended use.

The fiberglass tank, as of June 3, 1975, had not been finally accepted by the architect, and pursuant to Section 2.2.12 of the General Conditions of the Contract for Construction, the architect rejected the tank. Demand was then made by the School District upon Linfoot to replace the tank. Lin-foot refused to replace the tank unless it was compensated for doing so. The School District rejected this proposal and hired another contractor who installed an identical tank in an adjacent area. The School District then brought suit against Linfoot to recover the expense incurred by the School District in securing and installing the new tank.

This suit was based upon three grounds: breach of contract, breach of express warranty, and negligence. A trial was held before a judge of the First Judicial District, sitting without a jury on January 20 and 21, 1977.

After the trial, the court entered its findings of fact, conclusions of law, and order for judgment, and judgment was accordingly entered on March 23, 1977. In its findings of fact, the trial court found that Lin-foot breached its contract, breached its express warranty, and was negligent. The court found that the School District was entitled to damages in the sum of $16,-450.75, subject to Linfoot’s right to set-off against the judgment in the amount of $9,298. This resulted in a net judgment for the School District of $7,152.75. It is from [909]*909this judgment that Linfoot appeals to this court.

Linfoot, in its appeal, disputes the findings of the trial court that it breached the contract, that it breached an express warranty, and that its negligence was the proximate cause of the damage to the tank. Linfoot further contends that the court erred as a matter of law in determining that a contractor could be liable under any circumstances, when the contractor specifically followed the plans and specifications prepared by the owner’s (School District’s) architect.

We will deal with Linfoot’s last contention first. It is undisputed by the parties that the School District employed the architect, who in turn employed the engineer. The plans and specifications for the installation of the tank were furnished to Linfoot by the architect and engineer. Linfoot, as the contractor, was required to follow the plans and specifications furnished by the School District’s architect and engineer.

There is a dispute over whether or not those specifications were followed to the letter by Linfoot. The dispute arises as to whether or not Linfoot properly backfilled the site when it covered the tank in December of 1975.

The School District contends that Linfoot failed to follow the Owens/Corning installation instructions in installing the tank. These instructions were incorporated into the contract by Section 4.4.4(b) of the Supplementary Conditions (Article 15) of the contract. Item six of these instructions, reads:

“Caution: Bricks or blocks used to support piping must be removed prior to filling to grade. Do not use rock, shale or debris for fill.”

The School District contends that Linfoot failed to follow those instructions in that large wooden pallets were placed around the manway to the tank prior to backfilling. Mr. Opp, who supervised the field job for Linfoot, testified that these wooden pallets were so used.

Linfoot asserts that these pallets were not used to support piping, but were placed over the top of the pipes. Furthermore, it contends that there is no showing that these pallets being placed there had any connection with the damage to the tank.

For the purpose of this opinion, we will assume that Linfoot followed the specifications, and we will therefore not determine if the placing of these wooden pallets around the manway before backfilling was contrary to the specifications. The trial court made no such finding and we do not believe that such finding is necessary to support the judgment in this case.

Assuming Linfoot followed the plans and .specifications to the letter, is it excused from liability in this case?

Linfoot points to the case of United States v. Spearin, 248 U.S. 132, 39 S.Ct. 59, 63 L.Ed. 166 (1918), where the United States Supreme Court said:

“But if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.” 248 U.S. 136, 39 S.Ct. 61, 63 L.Ed. 169.

Linfoot also cites the annotation found in 6 A.L.R.3d at 1394 to support its position. In that annotation, the general rule is stated to be as follows:

“ . . . the rule has become well settled in practically every American jurisdiction in which the matter has been involved, that a construction contractor who has followed plans or specifications furnished by the contractee, his architect, or engineer, and which have proved to be defective or insufficient, will not be responsible to the contractee for loss or damage which results, at least after the work is completed, solely from the defective or insufficient plans or specifications, in the absence of any negligence on the contractor’s part, or any express warranty by him as to their being sufficient or free from defects.” 6 A.L.R.3d 1394 at 1397.

We do not understand the rule stated in 6 A.L.R.3d or in United States v. Spearin, supra to automatically relieve the contrac[910]*910tor of liability if he follows the specifications given to him by the contractee, his architect, or engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Entzel v. Moritz Sport and Marine
2014 ND 12 (North Dakota Supreme Court, 2014)
City of Bismarck v. Mariner Construction, Inc.
2006 ND 108 (North Dakota Supreme Court, 2006)
Bechtold Paving, Inc. v. City of Kenmare
446 N.W.2d 19 (North Dakota Supreme Court, 1989)
Fidelity & Deposit Co. v. City of Sheboygan Falls
713 F.2d 1261 (Seventh Circuit, 1983)
Carlson Homes, Inc. v. Messmer
307 N.W.2d 564 (North Dakota Supreme Court, 1981)
Mayville-Portland School District No. 10 v. C. L. Linfoot Co.
261 N.W.2d 907 (North Dakota Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
261 N.W.2d 907, 1978 N.D. LEXIS 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mayville-portland-school-district-no-10-v-c-l-linfoot-co-nd-1978.