Bechtold Paving, Inc. v. City of Kenmare

446 N.W.2d 19, 1989 N.D. LEXIS 165, 1989 WL 99225
CourtNorth Dakota Supreme Court
DecidedAugust 28, 1989
DocketCiv. 890012
StatusPublished
Cited by2 cases

This text of 446 N.W.2d 19 (Bechtold Paving, Inc. v. City of Kenmare) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bechtold Paving, Inc. v. City of Kenmare, 446 N.W.2d 19, 1989 N.D. LEXIS 165, 1989 WL 99225 (N.D. 1989).

Opinion

VANDE WALLE, Justice.

Wold Engineering, P.C., and the City of Kenmare appealed from a judgment awarding Bechtold Paving, Inc., the balance due on a contract to seal streets in Kenmare *20 and ordering Wold to pay to have the streets redone. We affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

Kenmare retained Wold to provide engineering services and supervision for street sealing in Kenmare. Wold prepared plans and specifications for the project, which entailed sealing the streets with asphalt and aggregate. Bechtold was awarded the bid to provide contractor’s services for the project. Before the streets were sealed, Wold authorized Bechtold to change materials to a larger size aggregate and to an asphalt emulsion thinned with water rather than a rapid-cure asphalt thinned with gasoline as required in the original contract specifications.

During the sealing, dust from the unwashed aggregate was observed, and Ken-mare complained to Bechtold and Wold. However, Wold ordered the project to continue and ultimately approved and accepted Bechtold’s work. After the project was completed, there were longitudinal streaks and ridges of aggregate throughout the streets. Kenmare was not satisfied with the project and refused to pay Bechtold the balance due on the contract.

Bechtold sued Kenmare, alleging that $15,030.03 was due on the contract. Ken-mare counterclaimed against Bechtold, alleging that Bechtold caused $2,348 in damage to a water main. Kenmare further alleged that the sealing project was not done in a workmanlike manner and sought $131,991.70 in damages to have the streets redone. Kenmare also sued Wold for $131,991.70 in damages to have the streets redone, alleging that Wold had altered the contract specifications and had allowed the use of improper materials.

After some discovery and a continuance, Kenmare moved to amend its third-party complaint to allege that Wold negligently supervised the resurfacing and to increase the claim for damages to $400,000. Wold objected, but the trial court allowed the amendment.

After a bench trial, the court found in favor of Bechtold on its claim for the balance due on the contract and in favor of Kenmare on its claim for the damaged water main. The court offset the damages for the water main against the balance due on the contract. The court also found in favor of Kenmare on its claim against Wold and an amended judgment 1 was entered which provided:

“That the City of Kenmare shall cause the streets included in the original resealing project to be resealed by reletting bids for the project and may employ an engineer to prepare specifications, let bids, and superintend the work in progress to accomplish in a workmanlike manner what the City of Kenmare initially proposed to receive from a successful bidder utilizing the materials initially specified, and which it should have received by proper supervision and enforcement of the contract by the contractor, Wold Engineering, P.C.; and that Wold Engineering, P.C. shall pay for the project awarded and completed, making payments to the engineer and contractor when progress payments are required by the construction contract.”

Wold argues that the trial court’s finding of fact that the problems with the project “were caused by improper material and improper application” was clearly erroneous. Wold asserts that the testimony by' Kenmare’s expert that the changes in the contract specifications were not improper and the uncontradicted testimony that the asphalt and aggregate were applied properly establishes that the trial court’s finding of fact was clearly erroneous.

*21 Our review of a trial court’s determination on factual matters is governed by the "clearly erroneous” standard of Rule 52(a), N.D.R.Civ.P. A finding of fact is clearly erroneous when, although there is some evidence to support it, the reviewing court on the entire evidence is left with a definite and firm conviction that a mistake has been made. In re Estate of Elmer, 210 N.W.2d 815 (N.D.1973). We give due regard to the trial court’s opportunity to assess the credibility of the witnesses, and a choice between two permissible views of the evidence is not clearly erroneous. Three Affiliated Tribes v. Wold Eng., 419 N.W.2d 920 (N.D.1988).

The evidence adduced at trial established that the completed project had longitudinal streaks with rutted street surfaces, which resulted in accumulations of water. The streets also had bare spots with no seal coating and areas with loose aggregate. There was evidence that the aggregate was dirty and did not properly adhere to the asphalt. An engineer hired by Kenmare, Calvin Marjamaa, inspected the streets and reported that the problems with the streets were caused by: (1) applying the liquid bitumen unevenly; (2) allowing traffic on the fresh bitumen before seal-coating with aggregate; and (3) using improper seal-coat aggregate. The evidence supports the trial court’s finding of fact that the problems with the project were caused by improper material and improper application, and we are not left with a definite and firm conviction that the trial court made a mistake in that finding. We therefore conclude that that finding is not clearly erroneous.

Wold also argues that the trial court improperly allowed Kenmare to amend its complaint on the eve of trial to allege that Wold improperly supervised the project and to increase the claim for damages from $131,991.70 to more than $400,-000.

Rule 15(a), N.D.R.Civ.P., permits amendments to pleadings and provides that such amendments “shall be freely given when justice so requires.” It is well established that a decision on a motion to amend pleadings depends on the facts and circumstances of the particular case and is within the sound discretion of the trial court. E.g., First Trust Co. v. Scheels Hardware, 429 N.W.2d 5 (N.D.1988); Greenwood v. American Family Insurance Co., 398 N.W.2d 108 (N.D.1986). We will not reverse a trial court’s decision on a motion to amend pleadings in the absence of an abuse of discretion. E.g., Geo-Mobile, Inc. v. Dean Bender Chevrolet, 386 N.W.2d 918 (N.D.1986); Bender v. Time Insurance Co., 286 N.W.2d 489 (N.D.1979).

Kenmare moved to amend its complaint on December 26, 1986, before Wold and Bechtold had served answers to interrogatories. The trial court heard and decided Kenmare’s motion on January 6, 1987, the first day of trial. Wold did not ask for a continuance after the trial court granted Kenmare’s motion. This case was heard in three segments: on January 6-7, 1987; on January 20-21, 1987; and on August 27, 1987, when the trial court conducted an on-site inspection of the streets.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Honey Co., LLC v. Graves
2003 ND 125 (North Dakota Supreme Court, 2003)
Matter of Estate of Jorstad
447 N.W.2d 283 (North Dakota Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
446 N.W.2d 19, 1989 N.D. LEXIS 165, 1989 WL 99225, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bechtold-paving-inc-v-city-of-kenmare-nd-1989.