Pfliger v. Peavey Co.

310 N.W.2d 742, 1981 N.D. LEXIS 330
CourtNorth Dakota Supreme Court
DecidedOctober 6, 1981
DocketCiv. 9960
StatusPublished
Cited by20 cases

This text of 310 N.W.2d 742 (Pfliger v. Peavey Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pfliger v. Peavey Co., 310 N.W.2d 742, 1981 N.D. LEXIS 330 (N.D. 1981).

Opinion

PAULSON, Justice.

Peavey Company [“Peavey”] appeals from a judgment entered against it by the District Court of Burleigh County sitting without a jury on February 5, 1981, which judgment found Peavey liable for the negligent construction of a farm building on the principle of an ostensible agency and awarded Richard Pfliger [“Pfliger”] the sum of $6,057 after setting off Peavey’s counterclaim. We modify the judgment of the district court and affirm it as modified.

In the early summer of 1978, Arnold Krein, a Peavey sales representative, contacted Pfliger at his farm after learning that Pfliger was interested in purchasing a steel farm building. They had a conversation about steel buildings and Krein showed Pfliger a brochure for a Circle Steel building. Pfliger asked for a bid for such a building as he needed one to present to the Agriculture Stabilization & Conservation Service in order to obtain financing.

Pfliger had secured bids from others and he told Krein that he wanted the same arrangement as he had asked from the others: he wanted the building completed. Krein said that he could prepare such a bid. 1

*744 To prepare his bid Krein contacted a contractor, Miller Construction Co. [“Miller”], for estimated labor costs. Krein also contacted a concrete supplier for an estimated cost of the concrete. These contacts were made without any direction or endorsement by Pfliger.

On July 11, 1978, Pfliger ordered the building materials from Peavey and signed a customer order for the purchase. The order involved the materials for the physical structure of the proposed building, but not for concrete or labor costs. 2 On July 28, 1978, the day before the construction of the building began, Mr. James Miller, of Miller Construction, met Pfliger at the Pfliger farm. Pfliger signed a “proposal” presented by Miller for the erection of the building. This proposal provided that Miller Construction was to furnish labor for pouring and forming the concrete and for erecting the structure. Miller told Pfliger that before he begins construction on any job he asks for half of his money down, and, at that time, Pfliger paid Miller $1,889.40, one-half of the labor costs.

The next day the concrete was delivered and poured. Pfliger paid Atlas, Inc., the concrete supplier, $3,542.72. This amount differs from the original bid prepared by Krein because Pfliger specified an additional two inches of concrete. The floor was originally planned to have four inches of concrete but Pfliger ordered the additional two inches at the suggestion of Miller so that the floor could support parked equipment. Pfliger paid for the concrete immediately to obtain a 5 percent discount about which he was told by the Atlas, Inc., truck driver.

In addition to the $1,889.40 paid to Miller and $3,542.72 paid to Atlas, Inc., Pfliger wrote a check to Peavey on December 7, 1978, for $12,000. The memorandum on the check indicates that it was for “building and account”. Pfliger had maintained an open account with Peavey for a number of years.

Peavey trucks were used only for delivery of building materials, but neither trucks nor other Peavey equipment was used in the construction of the building.

Pfliger did not supervise the construction of the building. When problems arose during the course of construction, Pfliger would contact Krein, who, in turn, wbuld contact Miller. Problems arose from side walls which were improperly bolted together, resulting in gaps through which daylight could be seen; the roof was improperly installed and leaked; and there were prob *745 lems with doors not fitting or operating properly. The building was not suitable for Pfliger to use for grain storage. Peavey admitted that the building was negligently constructed.

On April 25, 1978, Mr. Al Motl of Peavey came to the Pfliger farm with Arnold Krein to examine the building and its problems.

At trial Pfliger testified that the building was worth no more than a pole barn because it was unsuitable for grain storage. He valued the building at $5,000.

In determining damages, the trial judge in his memorandum opinion found Pfliger had paid the sum of $12,000 to Peavey; $1,889.40 to Miller; and $241.14 for repairs to one of the building’s doors, making a total sum of $14,130.54; and it was further found that the concrete slab had no defects and was useable for all purposes. The trial judge further found that Pfliger received value in the sum of $5,000.

The trial judge concluded that Peavey Company was the principal and James Miller, doing business as Miller Construction, was the agent of Peavey Company. The trial judge further concluded that the slant wall steel building was negligently constructed and was not suitable for the use intended by Pfliger and that Pfliger had sustained damages in the amount of $9,130.54, subject to Peavey’s counterclaim of $4,066.18, resulting in a judgment for Pfliger in the sum of $5,064.36, with interest from the first day of November, 1978, and costs.

The issues presented on appeal for our determination are:

1. Whether the trial court’s finding that an ostensible agency relationship existed between Peavey Company as principal and Miller Construction as agent was clearly erroneous.
2. Whether the damages as calculated by the trial court are clearly erroneous.

The first issue is whether or not the finding of the trial court that Miller was the agent of Peavey on the basis of an ostensible agency is clearly erroneous.

The question of the existence of a principal-agency relationship is one of fact. Midland Forge, Inc. v. Letts Industries, Inc., 395 F.Supp. 506 (D.C.Iowa 1975); Northern Nevada Mobile Home Brokers v. Penrod, 610 P.2d 724 (Nev.1980). Our review of the findings of fact is subject to the limitations of Rule 52(a) of the North Dakota Rules of Civil Procedure, which provides, in part, that:

“Findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge of the credibility of the witnesses.”

An agency relationship must be found by clear and convincing evidence, and the burden of proof when an agency is denied is upon the one who asserts that an agency exists. Farmers Union Oil Co. of Dickinson v. Wood, 301 N.W.2d 129 (N.D.1980). An agency is ostensible “when the principal intentionally or by want of ordinary care causes a third person to believe another to be his agent, who really is not employed by him”. § 3-01-03, N.D.C.C. “Ostensible authority is such as the principal intentionally or by want of ordinary care causes or allows a third person to believe the agent to possess.” § 3-02-02, N.D.C.C. There must have been some conduct on the part of the principal reasonably resulting in the belief in the mind of the third party, that an agency existed together with a reliance thereon. Bernard v. Madsen,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Ziegler
2025 ND 78 (North Dakota Supreme Court, 2025)
Grengs v. Grengs
2023 ND 239 (North Dakota Supreme Court, 2023)
Estate of Froemke
2023 ND 154 (North Dakota Supreme Court, 2023)
Valley Honey Co., LLC v. Graves
2003 ND 125 (North Dakota Supreme Court, 2003)
North Shore, Inc. v. Wakefield
530 N.W.2d 297 (North Dakota Supreme Court, 1995)
Swain v. Harvest States Cooperatives
469 N.W.2d 571 (North Dakota Supreme Court, 1991)
Bechtold Paving, Inc. v. City of Kenmare
446 N.W.2d 19 (North Dakota Supreme Court, 1989)
Hopkins v. McBane
427 N.W.2d 85 (North Dakota Supreme Court, 1988)
Belgarde v. Rosenau
388 N.W.2d 129 (North Dakota Supreme Court, 1986)
Knoff v. American Crystal Sugar Co.
380 N.W.2d 313 (North Dakota Supreme Court, 1986)
Farmers State Bank of Leeds v. Thompson
372 N.W.2d 862 (North Dakota Supreme Court, 1985)
Meyer v. Hansen
373 N.W.2d 392 (North Dakota Supreme Court, 1985)
Radspinner v. Charlesworth
369 N.W.2d 109 (North Dakota Supreme Court, 1985)
Anderson v. Anderson
368 N.W.2d 566 (North Dakota Supreme Court, 1985)
Martin v. Weckerly
364 N.W.2d 93 (North Dakota Supreme Court, 1985)
Johnson v. Production Credit Ass'n of Fargo
345 N.W.2d 371 (North Dakota Supreme Court, 1984)
Asleson v. West Branch Land Co.
311 N.W.2d 533 (North Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
310 N.W.2d 742, 1981 N.D. LEXIS 330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pfliger-v-peavey-co-nd-1981.