Home Furniture, Inc. v. Brunzell Construction Co.

440 P.2d 398, 84 Nev. 309, 1968 Nev. LEXIS 356
CourtNevada Supreme Court
DecidedMay 3, 1968
Docket5404
StatusPublished
Cited by8 cases

This text of 440 P.2d 398 (Home Furniture, Inc. v. Brunzell Construction Co.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Home Furniture, Inc. v. Brunzell Construction Co., 440 P.2d 398, 84 Nev. 309, 1968 Nev. LEXIS 356 (Neb. 1968).

Opinion

*310 OPINION

By the Court,

Mowbray, J.:

Home Furniture, Inc. appeals from a $10,000 judgment awarded Brunzell Construction Company, Inc. for the remaining balance due on the construction of the Home Furniture building in Reno.

*311 On November 17, 1959, the parties entered into a written contract in the total sum of $845,623.79 for the construction of a 6-story furniture building. The contract provided for progress payments with the provision that 10 percent of the contract price could be withheld until 35 days after filing of the notice of completion, which was filed by appellant on March 17, 1961. Appellant made all payments on the contract except $10,000, which appellant withheld, asserting that respondent had not constructed the building in accordance with appellant’s plans and specifications and that appellant had been damaged as a result of respondent’s faulty performance in the sum of $40,000. The case was pretried, and it was stipulated at the pretrial conference that $10,000 was due respondent pursuant to the construction contract and that appellant would have the burden of proving failure of performance by respondent and the damages that resulted. The faulty performance complained of is narrowed to the specified tolerance level 1 of the slab finish of the concrete, prestressed sixth floor, or roof, which, it was found, several months after the building had been occupied, puddled, or retained “bird baths” after the summer showers. The learned trial judge, in his written decision, found this condition was not due to respondent’s failure of performance of the contract and ordered judgment entered for respondent accordingly. We agree, and affirm the judgment.

The construction contract of October 15, 1959, consisting of 124 single-spaced typewritten pages, is most complete in its detailed specifications as to the materials to be used and the manner in which the prestressed concrete slab floors were to be poured and jacked into position. The plans and specifications were drawn and prepared by the appellant’s architect, Ralph Berger, A.I.A., of San Francisco.

An architect employed by the owner is the agent of such owner in supervising construction work and in the interpretation of plans and specifications relating thereto. Erskine v. Johnson, 36 N.W. 510 (Neb. 1888); 3 AraJur., Architects § 5, at 1000. Indeed, Mr. Leo Myer Ginsburg, President of appellant, testified at the trial, on direct examination by Mr. Hagen:

*312 “Q. Did you hire the architect to prepare the plans for the construction?
“A. Yes.
“Q. Did he prepare drawings for the construction of the building?
“A. Yes.”

And on cross-examination by Mr. McAuliffe, Mr. Ginsburg testified:

“Q. As I understood your direct examination, Mr. Ginsburg, you hired Mr. Berger to design this building; is that correct?
“A. Yes.
“Q. Did you specify to Mr. Berger what you wanted in the way of a building?
“A. Yes.”

The contract set forth the general scope of the work to be performed 2 and provided that the owner’s architect would, at ■all times, have access to the work and that the contractor would provide proper facilities for inspection. 3 The contractor *313 was required to keep on the job site a competent superintendent approved by the architect. 4 The architect had the duty of general supervision of the entire project. 5

The question presented is: Did the contractor follow the plans and specifications furnished by the owner’s architect, or did he vary from them and not perform in accordance with the contract? The law is well settled in practically every American jurisdiction that, where a contractor has followed the plans and specifications furnished by the owner and his architect, he will not be responsible to the owner, at least after the work is completed, for any loss or damage which results solely from the defects or insufficient plans or specifications, in the absence of any negligence on the part of the contractor or any express warranty by him as to their being sufficient or free from defects. This rule was well stated in Friederick v. Redwood County, 190 N.W. 801, 802 (Minn. 1922):

“Where a contractor makes an absolute and unqualified contract to construct a building or perform a given undertaking, it is the general, and perhaps universal, rule that he assumes the risks attending the performance of the contract, and must repair and make any injury or defect which occurs or develops before the completed work has been delivered to *314 the other party. But where he makes a contract to perform a given undertaking in accordance with prescribed plans and specifications, this rule does not apply. Under such a contract he is not permitted to vary from the prescribed plans and specifications even if he deems them improper and insufficient; and therefore cannot be held to guarantee that work performed as required by them will be free from defects, or withstand the action of the elements, or accomplish the purpose intended. Where the contract specifies what he is to do and the manner and method of doing it, and he does the work specified in the manner specified, his engagement is fulfilled and he remains liable only for defects resulting from improper workmanship or other fault on his part, unless there be a provision in the contract imposing some other or further obligation.” See Annot, 6 A.L.R.3d 1396 (1966); Fuchs v. Parsons Constr. Co., 111 N.W.2d 727 (Neb. 1961); Havard v. Bd. of Supervisors, 70 So.2d 875 (Miss. 1954); Puget Sound Nat'l Bank v. C. B. Lauch Constr. Co., 245 P.2d 800 (Idaho 1952); Woods v. Amulco Prods., 235 P.2d 273 (Okla. 1951); Annot., 88 A.L.R. 797 (1934).

The record before the trial court supports the trial judge’s decision. Appellant failed to show any deviation by the contractor from the architect’s plans and specifications. On the contrary, Mr. Berger, the architect, testified that the prestressed concrete slab floor in question was poured in accordance with the specifications of the contract.

By Mr. McAuliffe:

“Q. As far as you know, all the concrete that was poured into this particular slab met the specifications?
“A. Yes.
“Q. And it passed all the tests?
“A. We never had any controversy or anything over that.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leviton Manufacturing Co. v. Fireman's Fund Insurance
226 F. App'x 671 (Ninth Circuit, 2007)
Williams v. Cottonwood Cove Development Co.
619 P.2d 1219 (Nevada Supreme Court, 1980)
Mayville-Portland School District No. 10 v. C. L. Linfoot Co.
261 N.W.2d 907 (North Dakota Supreme Court, 1978)
Mohasco Industries, Inc. v. Anderson Halverson Corp.
520 P.2d 234 (Nevada Supreme Court, 1974)
Hopkins Construction Co. v. Reliance Insurance Co.
475 P.2d 223 (Alaska Supreme Court, 1970)
Kubby v. Crescent Steel
466 P.2d 753 (Arizona Supreme Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
440 P.2d 398, 84 Nev. 309, 1968 Nev. LEXIS 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/home-furniture-inc-v-brunzell-construction-co-nev-1968.