Puget Sound National Bank v. C. B. Lauch Const. Co.

245 P.2d 800, 73 Idaho 68, 1952 Ida. LEXIS 210
CourtIdaho Supreme Court
DecidedJune 18, 1952
Docket7805
StatusPublished
Cited by21 cases

This text of 245 P.2d 800 (Puget Sound National Bank v. C. B. Lauch Const. Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Puget Sound National Bank v. C. B. Lauch Const. Co., 245 P.2d 800, 73 Idaho 68, 1952 Ida. LEXIS 210 (Idaho 1952).

Opinion

*71 KEETON, Justice.

C. B. Lauch Construction Company, defendant and appellant, entered into a contract dated the 20th of October, 1947, with the Boise Hills Village Incorporated, to construct certain houses and make improvements pursuant to drawings, plans and specifications made a part of the contract. Thereafter, by three several written instruments, part of the contract work so undertaken by appellant was sublet to Saxon Painting Company, hereinafter referred to as Saxon.

By one of these subcontracts, appellant “ * * * for the full, complete and faithful performance of this subcontract, agrees to pay to the subcontractor, in accordance herewith, the sum of ($53,500).” For said sum Saxon agreed “To furnish all supervision, labor and materials, and perform all work as described in Paragraph 3 hereof, for the construction of Boise Hills Village project.”

Paragraph 3 referred to reads:

“That the labor and materials to be furnished, and the work to be performed by the subcontractor are as follows: All painting as called for or indicated on plans and specifications or addendum. If further changes are made in the painting specifications from the date of this contract, additional or deductive changes will be made at a fair and equitable rate.”

The specifications referred to in this paragraph in the contract between the appellant and the Boise Hills Village Incorporated reads:

“Exterior wood work shall have 2 coats paint, factory mixed. Material shall be prepared, ready-mixed paint, and shall consist of a separate primer and separate finish coat, which shall be used together as a two-coat system. All containers shall have labels as required by and satisfactory to the Federal Housing Administration. Thinner and coverage shall conform to specifications on manufacturer’s label. It is understood that acceptance of all 2-coat work is withheld by the Federal Housing Administration until completion, and all surface with unsatisfactory coverage shall be redone.” (Emphasis supplied)

The subcontract also contained a provision reading:

The subcontractor (Saxon):

“To be bound by the terms of said Main Contract with the Owner (including every part of and all the general and special conditions, drawings, specifications and addenda), in any way applicable to this subcontract, and also by the Provisions Printed On The Reverse Side Hereof, which are hereby referred to and made a part of this subcontract.”

*72 The subcontractor further assumed, so far as the subcontract work was concerned “all the obligations and responsibilities which the contractor assumed toward the owner by the main contract * *

Other parts of the work undertaken by the appellant were also sublet to Saxon. The amounts earned under these other contracts are not in dispute.

In addition to the general provisions defining the work to be done, and the material to be furnished, the subcontract contained the following provisions:

Saxon “to commence and at all times to carry out, perform and complete this subcontract to the full and complete satisfaction of the contractor, and of the architect or owner. It is specifically understood and agreed that in the event the contractor shall at any time be of the opinion that the subcontractor is not proceeding with diligence and in such a manner as to satisfactorily complete said work within the required time, then and in that event the contractor shall have the right, after reasonable notice, to take over said work and to complete the same at the cost and expense of the subcontractor, without prejudice to the contractor’s other rights or remedies for any loss or damage sustained.”

Pursuant to the subcontract Saxon commenced the painting operation in January, 1948, completing work thereunder in December of the same year. Saxon made assignments of all sums due or to become due under the contract to the plaintiff bank, respondent here.

In June, 1949, six months after Saxon had completed the painting job, objection to the work was made by the owner, or those acting for it. This objection was not made on the grounds that the paint used did not conform to specifications, or the application of the same to the wood was not properly done, or that any of the wood had been left unpainted. The objection was entirely on other grounds.

In furnishing the paint, Saxon was limited to a certain brand of factory mixed paint. He had nothing to do with the selection of colors, this being a privilege of the owner, to be selected from certain basic or multiple colors which appeared in the specifications, and when so selected, it was the contractual duty of Saxon to apply the same to the wood of the building.

During the progress of the work, Saxon performed certain extra work and'claimed an additional sum earned, amounting to $21,464.19. This extra work claim was disputed by appellant and after some negotiations, a settlement was made and the extra work adjusted in the sum of $13,-670.68. For the work done under the subcontracts, and the extra work performed and agreed to by settlement, Saxon claimed to have earned an aggregate of $81,826.68. There were cash and other *73 credits of $61,868.03, leaving, according to Saxon, a balance of $19,958.65.

In a letter dated March 16, 1949, three months subsequent to the time Saxon claimed to have performed his contract and left the job, addressed to an officer of respondent, signed by the appellant, a complete tabulation of the amounts earned, including sums by reason of the contract now in dispute, and the credits given was furnished the respondent. The balance shown amounted to the sum of $19,958.65.

Payment not having been made, plaintiff brought this action as assignee of Saxon to recover the amount claimed due.

The answer, among other things, alleged that the painting work was unsatisfactory, and that the Federal Housing Administration, in July, 1949, after an inspection of the Boise Hills Village project, had made a list of claimed deficiencies in performance by the appellant, and one of the claimed deficiencies listed was the unsatisfactory condition of the exterior paint applied by Saxon; that to conform the exterior paint to the specifications made a part of all contracts, and to secure final approval required an additional coat of paint on all exterior surfaces; • and that after notice to Saxon and his refusal to apply a third coat of paint, appellant repainted the exterior of the Boise Hills Village project, and made the same acceptable to the owners at an expense of $8,810.45. The answer asked to have this sum offset against the sum claimed by respondent.

On issues thus joined, the matter was tried before a jury and a verdict rendered for $19,958.65, for which amount judgment was entered. Defendant appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ervin Construction Co. v. Van Orden
874 P.2d 506 (Idaho Supreme Court, 1993)
Leazer v. Kiefer
821 P.2d 957 (Idaho Supreme Court, 1991)
Garrett Freightlines, Inc. v. Bannock Paving Co.
735 P.2d 1033 (Idaho Supreme Court, 1987)
Gilbert v. City of Caldwell
732 P.2d 355 (Idaho Court of Appeals, 1987)
Green v. Bannock Paving Co.
720 P.2d 186 (Idaho Supreme Court, 1986)
Yellowstone Pipe Line Co. v. Grant Const. Co., Inc.
520 P.2d 249 (Idaho Supreme Court, 1974)
Bell v. Joint School District No. 241
499 P.2d 323 (Idaho Supreme Court, 1972)
Black v. Peter Kiewit Sons' Co.
497 P.2d 1056 (Idaho Supreme Court, 1972)
Home Furniture, Inc. v. Brunzell Construction Co.
440 P.2d 398 (Nevada Supreme Court, 1968)
Gates v. Pickett & Nelson Construction Co.
432 P.2d 780 (Idaho Supreme Court, 1967)
Commercial Insurance Co. v. Hartwell Excavating Co.
407 P.2d 312 (Idaho Supreme Court, 1965)
Branom v. Smith Frozen Foods of Idaho, Inc.
365 P.2d 958 (Idaho Supreme Court, 1961)
Goodwin v. Village of Firth
319 P.2d 970 (Idaho Supreme Court, 1957)
Black v. Theo Hamm Brewing Co.
305 P.2d 1085 (Idaho Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
245 P.2d 800, 73 Idaho 68, 1952 Ida. LEXIS 210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/puget-sound-national-bank-v-c-b-lauch-const-co-idaho-1952.