Alley Construction Co., Inc. v. State

219 N.W.2d 922, 300 Minn. 346, 1974 Minn. LEXIS 1345
CourtSupreme Court of Minnesota
DecidedJuly 5, 1974
Docket44298
StatusPublished
Cited by17 cases

This text of 219 N.W.2d 922 (Alley Construction Co., Inc. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alley Construction Co., Inc. v. State, 219 N.W.2d 922, 300 Minn. 346, 1974 Minn. LEXIS 1345 (Mich. 1974).

Opinion

Todd, Justice.

The state appeals from the judgment entered for plaintiff, Alley Construction Co., Inc., and from the order denying its motion for a new trial in an action arising out of the construction of a highway. The state challenges the sufficiency of the evidence permitting recovery on a breach of warranty theory and the allowance of prejudgment interest. We affirm as to the issue of liability and reverse as to the allowance of prejudgment interest.

This litigation concerns the award of a construction contract for 9.3 miles of highway between Kellogg and Wabasha in southeastern Minnesota. The trial was lengthy and complex, but the issues on appeal are quite narrow. Our discussion of facts will *348 be limited to those pertinent to the disposition of the issues before us.

In 1965, the state commenced the planning and design of the project. On March 7,1969, bids were requested by advertisement to be returned by March 28, 1969. Plaintiff was the low bidder and was awarded the contract. The plans prepared by the state upon which plaintiff bid consisted of 322 sheets and specifications including hundreds of pages of additional material. Section 1401 of the Standard Specifications for Highway Construction states in part:

“The intent of the Contract is to provide for construction and completion of the Project in every detail as described in the Plans and Specifications.”

The 9.3 miles of highway were divided into balance areas. These geographical areas of varying lengths were intended to provide within each an approximate balance between cuts and fills to minimize the hauling of earth materials. Under the terms of the contract, the state was allowed a deviation of 20 percent from any quantity estimates in the plans and specifications. As construction proceeded and was completed, both parties agree that none of the balance areas were actually in balance. At trial, the state contended that the percentage of common excavation overrun was 20.8 percent and the rock overrun was 23.7 percent. The state further contended that this arose because a large part of the rock formation was found to be unstable and under the terms of the contract could be redesigned. The state contended that the contractor was paid for these overruns under a specific clause in the agreement designed for this eventuality and pointed out that there was a substantial payment over and above the contract price.

The contractor submitted evidence that not one of the balance areas on the job actually was in balance. Thus, it was necessary to haul materials out of balance throughout the entire length of the project. In support of its contention, plaintiff submitted an *349 exhibit detailing the various balance areas which disclosed overruns in some balance areas as high as 744 percent. Since plaintiff is the prevailing party, we are compelled to view the evidence in the light most favorable to its position. Stapleman v. St. Joseph the Worker, 295 Minn. 406, 205 N. W. 2d 677 (1973). We find there was adequate evidence for which the jury could accept plaintiff’s position on this matter.

1. The case was submitted to the jury upon the theories of breach of warranty and breach of contract. On appeal, the state contends that it was improper to submit the issue of breach of warranty since there is no evidence that plaintiff relied upon the contract and specifications in submitting its bid. In support, the state submits that plaintiff failed to call as a witness Mr. Lloyd Parker, a former employee who participated substantially in the preparation of plaintiff’s bid. The state suggests that it was necessary that Mr. Parker appear and testify that he relied upon the plans and specifications and be subject to cross-examination. It is uncontested that Mr. Parker was available as a witness to either party and that he was not subpoenaed or called by the state.

We are unimpressed by this contention. As indicated previously, the plans and specifications for this project were massive. Plaintiff had 3 weeks in which to make its computations and submit its bids. To require such self-serving testimony of plaintiff’s employee seems unnecessary. Further, the specifications required that the contractor bid solely on the plans and specifications. We hold that under the facts and circumstances of this case an inference of reliance properly arises.

We concur in the statement of the trial court made in its memorandum accompanying its order denying a new trial:

“In the proposal here the State furnished certain quantity data, haul station data, and balance area information to prospective bidders. While some of this information was estimated, certainly those estimates must be reasonably accurate in order to provide the contractors some basis for their bidding. Since this is so, the very fact of bidding raises an inference that the con *350 tractor relied on the information contained in the plans, specifications, and proposal since the time was too short to do otherwise. Any other conclusion would obviate any necessity for supplying information of any kind at the time of inviting bids. Thus, no direct evidence is in any way necessary to establish the reliance of the ultimately successful bidder on the contract.”

The trial court cited Raymond International of Delaware, Inc. 70-1 CCH, Bd. Cont. App. Dec. par. 8341 (1970), in support of its statement that there exists an implied warranty that plans, specifications, and drawings are adequate for the work. Plaintiff also cites McCree & Company v. State, 253 Minn. 295, 91 N. W. 2d 713 (1958), and United States v. Spearin, 248 U. S. 132, 39 S. Ct. 59, 63 L. ed. 166 (1918). While the issue of inference of reliance was not directly involved in these cases, they do support our holding that such an inference properly arises under the facts and circumstances of this case. We find the state’s attempt to distinguish these cases on factual bases to be unconvincing.

In McCree & Company v. State, supra, our court had occasion to comment on this issue, and we quote with approval the following language (253 Minn. 313, 91 N. W. 2d 725):

“The evidence in the case at bar, viewed as a whole, demonstrates that the owner’s actions in furnishing detailed plans and specifications controlled not only the particular result to be accomplished but also the particular construction methods to be followed and used and supports an implied warranty in keeping with the intention and expectation of the parties that the plans, specifications, and soil conditions were such as would permit successful conclusion of the work. The state was the party in control who dictated the entire contract and retained control from start to finish. The evidence reasonably indicates that the plaintiff had neither the time nor the information prior to becoming a bidder nor the right of control in planning or executing the work which under the contract and the plans and specifications rested with the state. We think it may reasonably be said that in the in *351 stant case the party who had the superior knowledge and the complete control was the state.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Matthew v. Unum Life Insurance Co. of America
639 F.3d 857 (Eighth Circuit, 2011)
Fireman's Fund Insurance v. Canon U.S.A., Inc.
394 F.3d 1054 (Eighth Circuit, 2005)
Fireman's Fund Insurance Company v. Canon
394 F.3d 1054 (Eighth Circuit, 2005)
D.H. Blattner & Sons, Inc. v. Firemen's Insurance Co.
535 N.W.2d 671 (Court of Appeals of Minnesota, 1995)
Hendricks v. Callahan
972 F.2d 190 (Eighth Circuit, 1992)
Zontelli & Sons, Inc. v. City of Nashwauk
373 N.W.2d 744 (Supreme Court of Minnesota, 1985)
Cashman v. Allied Products Corp.
761 F.2d 1250 (Eighth Circuit, 1985)
Polaris Industries v. Plastics, Inc.
299 N.W.2d 414 (Supreme Court of Minnesota, 1980)
Eric A. Carlstrom Construction Co. v. Independent School District No. 77
256 N.W.2d 479 (Supreme Court of Minnesota, 1977)
Keegan v. Fischer Construction Co., Inc.
223 N.W.2d 141 (Supreme Court of Minnesota, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
219 N.W.2d 922, 300 Minn. 346, 1974 Minn. LEXIS 1345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alley-construction-co-inc-v-state-minn-1974.