Eric A. Carlstrom Construction Co. v. Independent School District No. 77

256 N.W.2d 479, 1977 Minn. LEXIS 1491
CourtSupreme Court of Minnesota
DecidedJuly 1, 1977
Docket46539 and 46550
StatusPublished
Cited by21 cases

This text of 256 N.W.2d 479 (Eric A. Carlstrom Construction Co. v. Independent School District No. 77) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eric A. Carlstrom Construction Co. v. Independent School District No. 77, 256 N.W.2d 479, 1977 Minn. LEXIS 1491 (Mich. 1977).

Opinion

MacLAUGHLIN, Justice.

Plaintiff, Eric A. Carlstrom Construction Company (Carlstrom), and defendant, Independent School District No. 77 (School District), appeal from, the district court’s confirmation of arbitration awards arising from contracts for the construction of Man-kato East High School. For the reasons stated herein, we affirm.

In April 1971, the School District entered into four separate- prime contracts in connection with the construction of a new high school: (1) with the general contractor, Carlstrom; (2) with an electrical contractor, Hoffman Electric Company of Minneapolis (Hoffman); (3) with a plumbing and heating contractor, Midwest Mechanical Services, Inc. (Midwest); and (4) with a contrac *481 tor for the performance of ventilation services, Tessier Sheet Metal Works, Inc. (Tessier). The School District chose to enter into a separate agreement with each of the prime contractors rather than into a single contract with the general contractor who, in turn, would have let subcontracts for the other services.

The general terms and conditions of each of the four standard American Institute of Architects contracts were identical. Section 7.10.1 of each contract provided that “[a]ll claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, * * * shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.” This section further provided that “[t]he award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

On December 12, 1973, after construction of the new high school had been completed, Hoffman demanded arbitration proceedings against the School District pursuant to the arbitration provision of its contract with the School District. Hoffman charged that Carlstrom had failed to enclose certain parts of the building and that as a result, Hoffman had not been able to complete its work according to schedule. Hoffman sought compensation from the School District because of the extra cost of completion caused by Carlstrom’s delay. The theory of Hoffman’s claim was that the School District had the responsibility to assure that there was no delay on Carlstrom’s part which would cause loss to Hoffman.

Shortly thereafter, Midwest and Tessier filed demands for arbitration of their claims for compensation from the School District, again based on extra costs caused by Carl-strom’s delay. The School District then asserted a claim for indemnification against Carlstrom pursuant to section 4.18.1 of the contract, which stated in part:

“The Contractor shall indemnify and hold harmless the Owner * * * from and against all claims, damages, losses and expenses including attorneys’ fees arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense * * is caused in whole or in part by any negligent act or omission of the Contrae- ‡ ⅜ ⅜

Carlstrom brought this action for declaratory judgment and sought to enjoin the arbitration proceedings, claiming that the issues were not arbitrable. After a hearing, the district court retained jurisdiction but ordered, that the parties proceed with arbitration as provided by the- contracts. The separate arbitration proceedings were consolidated as a matter of. convenience and a joint hearing was held before a Commercial Arbitration Tribunal (Tribunal). The Tribunal, which was composed' of three arbitrators, all of whom were attorneys, heard testimony- from all of the parties and made the following written award:

“INDEPENDENT SCHOOL DISTRICT # 77, hereinafter referred to as SCHOOL, shall pay to HOFFMAN ELECTRIC COMPANY OF MINNEAPOLIS, hereinafter referred to as HOFFMAN, the sum of SEVENTY EIGHT THOUSAND DOLLARS ($78,000.00).
“SCHOOL shall pay to MIDWEST MECHANICAL SERVICES, INC. the sum of ELEVEN THOUSAND DOLLARS ($11,000.00).
“SCHOOL shall pay to. TESSIER SHEET METAL WORKS, INC. the sum of TWENTY-SIX THOUSAND DOLLARS ($26,000.00).
“ERIC A CARLSTROM CONSTRUCTION CO. shall pay to SCHOOL the sum of SEVENTY THREE THOUSAND FIVE HUNDRED THIRTEEN DOLLARS AND TWENTY-EIGHT CENTS ($73,513.28). ■
“The administrative fees and expenses of the American Arbitration Association shall be borne equally among the five parties and paid as directed by the Association.
*482 “The compensation for the Arbitrators shall be borne equally among the five parties and paid as directed by the Association.”
“This AWARD is in full settlement of all claims submitted to this arbitration.”

Subsequently, Hoffman, Midwest, and Tessier moved the district court for an order confirming the Tribunal’s awards pursuant to Minn.St. 572.18, and for judgment in accordance therewith. Carlstrom and the School District moved the district court to vacate, modify, or amend the awards, claiming error in the Tribunal’s decision. The district court referred the matter to the Tribunal for further consideration, specifically asking why the Tribunal had awarded the School District only partial indemnification from Carlstrom for those amounts which had been awarded to Hoffman, Midwest, and Tessier from the School District.

The Tribunal provided the information requested, explaining its basis for determining that the School District was not entitled to full indemnification from Carlstrom:

“1) The last phrase of the language quoted in the contract reads: ‘Any costs caused by defective or ill timed work shall be borne by the party responsible therefore.’ The School District was a party to all four contracts and was responsible for part of its own damages and part of the delay and damages caused to the other general contractors. This was because it failed properly to enforce the terms of its contract and the rights accorded to it by the custom and usage of the trade to coordinate the work of the four general contractors in order to mitigate the damages of any of the parties and to avoid foreseeable delays. The School District is one of the parties responsible for its own damages and is not entitled to full indemnity under the terms of the contract.
“2) Despite the fact that the School District claimed it had no control over the time scheduling of the four general contractors, there is ample evidence that it did indeed have the right and the obligation to coordinate the performance of the four contractors when their respective performances came in conflict with one another. There are certain terms in the respective contracts of the parties which might indicate otherwise, but there are other areas of the contracts which confirm this conclusion of the arbitrators. Expert witnesses testified that well established custom and usage of the trade allow an owner to coordinate his contractors under circumstances such as were present in this instance.
“3) The School District did in fact, through its agent, the architect, make some efforts to coordinate the contractors in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Rochester v. Kottschade
896 N.W.2d 541 (Supreme Court of Minnesota, 2017)
Correll v. Distinctive Dental Services, P.A.
607 N.W.2d 440 (Supreme Court of Minnesota, 2000)
Menahga Education Ass'n v. Menahga Independent School District No. 821
568 N.W.2d 863 (Court of Appeals of Minnesota, 1997)
City of Minneapolis v. Police Officers' Federation of Minneapolis
566 N.W.2d 83 (Court of Appeals of Minnesota, 1997)
Independent School District No. 279 v. Winkelman Building Corp.
530 N.W.2d 583 (Court of Appeals of Minnesota, 1995)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Brown v. Allstate Insurance Co.
466 N.W.2d 54 (Court of Appeals of Minnesota, 1991)
Littfin Lumber Co. v. Fasching
436 N.W.2d 791 (Court of Appeals of Minnesota, 1989)
Schmidt v. Midwest Family Mutual Insurance Co.
426 N.W.2d 870 (Supreme Court of Minnesota, 1988)
Franke v. Farm Bureau Mutual Insurance Co.
421 N.W.2d 406 (Court of Appeals of Minnesota, 1988)
Johnson v. American Family Mutual Insurance Co.
413 N.W.2d 172 (Court of Appeals of Minnesota, 1987)
Weigand v. Allstate Ins. Companies
706 P.2d 16 (Hawaii Supreme Court, 1985)
Afscme Dist. Coun. 96 v. Ind. Sch. Dist. 381
351 N.W.2d 33 (Court of Appeals of Minnesota, 1984)
Broadway Maintenance Corp. v. Rutgers
447 A.2d 906 (Supreme Court of New Jersey, 1982)
Barber-Greene Co. v. Zeco Co.
17 B.R. 248 (D. Minnesota, 1982)
Children's Hospital, Inc. v. Minnesota Nurses Ass'n
265 N.W.2d 649 (Supreme Court of Minnesota, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
256 N.W.2d 479, 1977 Minn. LEXIS 1491, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eric-a-carlstrom-construction-co-v-independent-school-district-no-77-minn-1977.