Independent School District No. 279 v. Winkelman Building Corp.

530 N.W.2d 583, 1995 Minn. App. LEXIS 585, 1995 WL 251790
CourtCourt of Appeals of Minnesota
DecidedMay 2, 1995
DocketC4-94-1694
StatusPublished
Cited by1 cases

This text of 530 N.W.2d 583 (Independent School District No. 279 v. Winkelman Building Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent School District No. 279 v. Winkelman Building Corp., 530 N.W.2d 583, 1995 Minn. App. LEXIS 585, 1995 WL 251790 (Mich. Ct. App. 1995).

Opinion

OPINION

HUSPENI, Judge.

Appellant, a general contractor, filed a demand for arbitration claiming that respondent, a school district, owed it $25,000 remaining on a construction contract. The arbitrator awarded respondent $20,000 and appellant $5,000, respectively, from the escrow account and found that respondent had waived any other affirmative setoff or counterclaim against appellant. Upon respondent’s motion, the district court concluded *585 that the arbitrator had exceeded his authority and vacated the portion of the arbitrator’s decision holding that respondent had waived its right to assert further setoff or counterclaims. Because we conclude that the arbitrator did not exceed his authority, we reverse.

FACTS

This dispute arises out of a 1990 contract between appellant Winkelman Building Corporation and respondent Independent School District Number 279 for the construction of Weaver Lake Elementary School. The agreement provided in relevant part:

4.5.1. Controversies and Claims Subject to Arbitration. Any controversy or claim arising out of or related to the Contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association * * *.
* * * * * *
4.5.2 Rules and Notices for Arbitration. Claims between the Owner and Contractor not resolved under paragraph 4.4 shall, if subject to arbitration under Subparagraph 4.5.1, be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect, unless the parties mutually agree otherwise.

Subparagraph 4.5.2 was amended to include:

Prearbitration discovery shall be conducted in accordance with Rules 26 through 87 of the Federal Rules of Civil Procedure.

In September 1992, while construction was still underway, respondent first noticed cracks in the mortar of the budding. Consequently, architects for the project inspected the building and found significant masonry distress. Respondent then retained American Engineering Testing (AET) to inspect the mortar. In a November 1992 report, AET stated that the extent of the masonry distress could not be fully ascertained at that time due to the nature of the deterioration. Therefore, the parties agreed to have AET conduct tests on the building beginning in July 1993.

On July 6,1993, before AET had issued its report, appellant filed a demand for arbitration, stating in part:

Nature of Dispute: Claimant was the general contractor for the construction of the Weaver Lake School. Although the project was completed and occupied on or before September 1991, there remains owing to Claimant the principal sum of approximately $25,000 plus interest, costs, disbursements and attorneys fees.
Claim or Relief Sought: (amount, if any) Approximately $25,000 plus interest, costs, disbursements and attorneys fees.

On July 13,1993, the American Arbitration Association sent respondent notice that if respondent chose to do so, respondent must file an answer by July 23,1993. Respondent did not file an answer or counterclaim.

On July 23, 1993, the day respondent’s answer in the arbitration proceeding was due, AET issued a report indicating that the cause of the masonry problem was appellant’s failure to comply with the masonry specifications. Respondent received this report on or about July 27,1993. The building continued to deteriorate and further tests were performed to determine the cost of restoration. In March 1994, the MacPher-son-Towne Company issued a report estimating that the cost of restoration would be $175,000.

In December 1993, the arbitrator awarded respondent $20,000 and appellant $5,000, respectively, from the escrow account, and found that respondent “has waived any other affirmative setoff or counterclaim against [appellant].” Respondent did not challenge the $20,000 awarded to it, nor the $5,000 awarded to appellant, but did seek to vacate the portion of the arbitrator’s award that determined respondent had waived its right to assert further setoff or counterclaims. The district court granted respondent’s motion, finding that the arbitrator exceeded the scope of his authority because the parties intended to arbitrate only whether the $25,-000 should remain in escrow and did not intend to arbitrate the issue of damages. The district court also found that neither the Construction Industry Arbitration Rules, nor *586 the parties’ agreement, nor the Federal Rules of Civil Procedure mandated that respondent file a counterclaim. 1

ISSUES

1. Did the district court err by finding that the arbitrator exceeded the scope of his authority?

2. Was there a compulsory counterclaim?

ANALYSIS

Arbitration is a proceeding favored in law. Ehlert v. Western Nat’l Mut. Ins. Co., 296 Minn. 195, 199, 207 N.W.2d 334, 336 (1973). The primary intent of arbitration is to encourage voluntary resolution of disputes in a forum created and controlled by the parties in their written agreement, and to discourage litigation. Eric A. Carlstrom Constr. Co. v. Independent Sch. Dist. No. 77, 256 N.W.2d 479, 483 (Minn.1977).

Upon application of a party, a district court shall vacate an arbitration award when the arbitrator exceeded his or her power. Minn.Stat. § 572.19, subd. 1(3) (1992). The scope of the arbitrator’s power is determined by the intent of the parties. Johnson v. American Family Mut. Ins. Co., 426 N.W.2d 419, 420 (Minn.1988). “The issue of arbitrability is to be determined by ascertaining the intention of the parties through examination of the language of the arbitration agreement.” Michael-Curry Co. v. Knutson Shareholders Liquidating Trust, 449 N.W.2d 139, 141 (Minn.1989). This court’s review of a district court’s interpretation of an arbitration agreement is de novo. Id.

“Once arbitrability is established, the standard of review narrows sharply.” Morrison v. Northern States Power Co., 491 N.W.2d 675, 678 (Minn.App.1992), pet. for rev. denied (Minn. Jan. 15, 1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seagate Technology, LLC v. Western Digital Corp.
834 N.W.2d 555 (Court of Appeals of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
530 N.W.2d 583, 1995 Minn. App. LEXIS 585, 1995 WL 251790, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-school-district-no-279-v-winkelman-building-corp-minnctapp-1995.