Otto B. Ashbach & Sons, Inc. v. State

78 N.W.2d 446, 247 Minn. 573, 1956 Minn. LEXIS 607
CourtSupreme Court of Minnesota
DecidedJuly 6, 1956
Docket36,664
StatusPublished
Cited by2 cases

This text of 78 N.W.2d 446 (Otto B. Ashbach & Sons, Inc. v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otto B. Ashbach & Sons, Inc. v. State, 78 N.W.2d 446, 247 Minn. 573, 1956 Minn. LEXIS 607 (Mich. 1956).

Opinion

Dell, Chief Justice.

Action by Otto B. Ashbach & Sons, Inc., against the State of Minnesota to recover for a volume of excavation claimed due under a contract for highway construction work. The contract dated January 19, 1948, called for construction work by plaintiff on state trunk Highway No. 35, commencing 4.5 miles east of Soudan and extending to 3.5 miles southwest of Ely. The work to be performed consisted of (1) grading, excavating, and embanking; and (2) the placing of a twelve-inch gravel base and subbase on the section of highway included in the contract.

It was agreed that the contract had been satisfactorily completed by plaintiff, the controversy here centering around the meaning of the contract as it related to “rock cuts” and whether plaintiff had been paid in full therefor. Section 11.02 of the contract provided that for “rock cuts” plaintiff would be paid at the rate of $2.88 per cubic yard and further specified that:

“In rock cuts, the excavation will be measured as the volume within the grading section staked by the Engineer; plus the volume included between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally; plus the volume above a surface 18 inches below the staked grade of the roadbed, extended to the shoulder slopes. No overbreak beyond these limits will be measured.”

Plaintiff contended that under this provision the state in its measurements of rock-cut excavations had failed to include some 11,000 cubic yards thereof for which plaintiff claimed payment at the rate of $2.88 per cubic yard. The trial court was called upon to construe the contract and under its construction determined that *575 plaintiff had not been paid for 2,73á cubic yards of such rock-cut excavations and accordingly that the defendant was indebted to plaintiff therefor in the sum of $7,873.92, plus interest, costs, and disbursements.

Included in the trial court’s findings were the following:

“8. That under Section 2105.2B, M. H. D. Specs., excavation is classified as Class ‘A’, ‘B’, or ‘C’.

“That section 2105.2B1, defines Class ‘A’ excavation as consisting of ‘all materials of an earthy nature, however compact they may be, such as earth, loam, clay, indurated clay, hardpan, silt, sand, and loose or cemented gravel; and boulders or detached rocks each having an average diameter of two (2) feet or less.’

“That Section 2105.2B2 defines Class ‘B’ as excavation consisting of ‘all ledge rock, and all boulders and detached rock, each having an average diameter of more than two (2) feet.’

“That Section 2105.2B3, M. H. D. Specs., defines Class ‘C’ excavation as consisting of ‘all materials listed under Class “A” and “B”, and any other material which may be encountered regardless of its nature.’

“9. That Special Provisions 11.01, at page 13 of the Proposal, provides that ‘All excavation, except Special Swamp Excavation, between the stations tabulated below will be classified as Class “B” excavation. [Here follows a list of the stations referred to.]’

“10. That materials actually excavated by plaintiff within those stations listed above which were classified as Class ‘B’ excavation under the contract consisted of materials meeting the definition of Class ‘B’ excavation, as well as materials defined as Class ‘A’ excavation, under M. H. D. Specs.

“11. Section 11.02 of the Special Provisions provides that, ‘In rock cuts, the excavation will be measured as the volume within the grading section staked by the Engineer; plus the volume included between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally; plus the volume above a surface 18 inches below the staked grade of the roadbed, extended to the shoulder slopes. No overbreak beyond these limits will be measured.’

*576 “That Section 11.02 applies to Class 'A’, 'B’, or 'O’ excavation whenever a rock cut is actually made.

“12. That 'grading section staked by the Engineer’ as used in Section 11.02 of the Special Provisions is the cross section of the roadway to which excavation would be made if the markings on the stakes were followed exactly. That 'staked grade of the roadbed’ as used in Section 11.02 of the Special Provisions is the top of the finished grade of the roadbed as required by the contract. That 'overbreak’ as used in Special Provisions 11.02 is defined under Section 2105.2L5, M. H. D. Specs., as 'that material in rock cuts which is removed outside of the authorized slope lines.’

*****

“14 That under Section 11.02 of the Special Provisions plaintiff in rock cuts, in addition to the volume of excavation within the grading section staked by the engineer, is to be paid for a volume of excavation between the staked backslopes of the roadway and a parallel slope 18 inches beyond that point measured horizontally; and in the roadbed a volume of excavation between the grade to which excavation was required to be made (subgrade or limits of grading section staked by the engineer) and a surface 18 inches below the finished grade of the roadbed extended to the shoulder slopes. That this additional volume allowed under Section 11.02 in backslopes and roadbeds is computed by using as a multiple the severed surface area of the rock at the limits of the staked grading section. That plaintiff in rock cuts is entitled to this additional volume of excavation whether the material is actually excavated or not.

“15. That except in rock cuts plaintiff has been paid in full for all excavation within the grading section staked by the engineer regardless of classification of materials excavated. That in rock cuts plaintiff has been paid for the total volume of excavation within the grading section staked by the engineer, plus an additional volume of excavation not necessarily excavated, as follows:

*577 “(1) At the backslopes — a volume of excavation between the staked backslopes and slopes distant 18 inches outside thereof, measured horizontally.

“(2) In the roadbed — a volume of excavation between the grade to which excavation was required to be made (subgrade) and a surface 18 inches below the staked grade of the roadbed (finished grade) extended to the shoulder slopes.

“(3) In a sub-excavation (excavation below the sub-grade) the volume of excavation performed within the excavation limits.”

After such findings the trial court requested that the parties submit figures as to the number of cubic yards of rock-cut excavations not paid for by defendant. They were unable to agree as to such figures, and thereupon the trial court requested that additional evidence be presented on this issue. Based on such additional evidence, the trial court then made an additional finding as follows:

“That, except in rock cuts, plaintiff has been paid in full. That in rock cuts plaintiff has not been paid for a volume amounting to 2734 cubic yards of material from rock cuts. That said material, under Section 11.02 of the Special Provisions, should be paid for at the rate of $2.88 per cubic yard.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lienhard v. State
431 N.W.2d 861 (Supreme Court of Minnesota, 1988)
Alley Construction Co., Inc. v. State
219 N.W.2d 922 (Supreme Court of Minnesota, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
78 N.W.2d 446, 247 Minn. 573, 1956 Minn. LEXIS 607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otto-b-ashbach-sons-inc-v-state-minn-1956.