In Re Appeal of Roberts Construction Company

111 N.W.2d 767, 172 Neb. 819, 1961 Neb. LEXIS 129
CourtNebraska Supreme Court
DecidedDecember 1, 1961
Docket35012
StatusPublished
Cited by13 cases

This text of 111 N.W.2d 767 (In Re Appeal of Roberts Construction Company) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Appeal of Roberts Construction Company, 111 N.W.2d 767, 172 Neb. 819, 1961 Neb. LEXIS 129 (Neb. 1961).

Opinion

Boslaugh, J.

This is an appeal from the disallowance of a claim by the Auditor of Public Accounts and the Secretary of State of the State of Nebraska. The claim arose out of a highway construction contract.

The contract in question was for the improvement of U. S. Highway No. 77 for a distance of 7 miles south from Beatrice, Nebraska. The contract was awarded to Roberts Construction Company by the Department of Roads and Irrigation on June 15, 1954. The work to be done by Roberts included grading and concrete paving of U. S. Highway No. 77 and surfacing of a county road which was to be used as a detour.

After the work had been completed, Roberts filed a claim with the State for damages for breach of contract. The claim included other items that are not important to the litigation at this time. The claim was disapproved by the State Engineer and disallowed by the Auditor of Public Accounts and the Secretary of State. Roberts then perfected an appeal to the district court for Lancaster County. After a lengthy hearing the district court allowed the claim in the amount of $16,594.45. The State has appealed from this judgment.

Roberts’ theory of the case is that the State failed to make the construction site available to the contractor until long after the beginning date specified in the contract; that as a result of this delay the costs of the contractor were substantially increased over the amounts that were and could have been reasonably anticipated at the time the parties entered into the contract; that the failure of the State to make the construction site available at the starting date provided in the contract was a breach of express and implied covenants in that regard; and that Roberts is entitled to recover as damages the amount of its increased costs resulting from the delay.

*821 The State’s theory of the case is that it did not agree to make the construction site available to Roberts on the beginning date specified in the contract; that the State is not responsible for any delay that may have occurred and that such delay was due to other causes including the acts or omissions of the contractor; that the provision in the contract for an extension of time is the exclusive remedy of Roberts for any delay resulting from causes beyond its control; and that the evidence does not show with certainty what damages Roberts may have sustained or the causes thereof.

The district court found that the State had represented to Roberts and other bidders that by June 21, 1954, subgrade preparation on the detour would be completed and a windrow of rock placed along the length of the detour so that the contractor could begin work on that date; that utility lines would be out of the way of grading operations; that the State failed to carry out these representations and agreements at the time specified; that, without notice to Roberts or other bidders, the State granted Gage County the right to take 90 working days from May 20, 1954, to perform subgrade preparation and placement of rock upon the detour; that grading and paving along the south 5 miles of the project could not be commenced, in any substantial volume, until the work on the permanent detour had been completed; that the State failed to cause the subgrade work on the detour to be performed properly so that the surfacing placed thereon by Roberts failed and further delayed the opening of the detour; that as a result of the delay in making the construction site available, Roberts’ plan for construction of the work was disrupted, an orderly and efficient construction operation was prevented, the work was extended into a period” of unseasonable weather, and Roberts was subjected to excessive and unexpected costs, especially labor costs; that the State could have avoided the damage by requiring Gage County to have performed its work on or *822 before June 21, 1954, or by not awarding the contract; that Roberts was partly at fault in failing to thoroughly inspect the construction site, in failing to timely procure material meeting the contract specifications which would have permitted mitigation of the damage, and in other unspecified respects; and that Roberts was entitled to recover $16,594.45.

The assignments of error which require consideration are those relating to the sufficiency of the evidence to sustain the judgment against the State.

This was an action at law for damages for breach of contract. By agreement of counsel a jury was waived. Under such circumstances the findings of the trial court are equivalent to the verdict of a jury and will not be disturbed unless clearly wrong. Thus, in reviewing the evidence it must be considered in the light most favorable to the plaintiff, every controverted fact must be resolved in the plaintiff’s favor, and the plaintiff must have the benefit of every inference that can reasonably be deduced therefrom. Capital Bridge Co. v. County of Saunders, 164 Neb. 304, 83 N. W. 2d 18. See, also, In re Appeal Roadmix Constr. Corp., 143 Neb. 425, 9 N. W. 2d 741.

The contract provided that Roberts would complete its work under the contract within 140 working days beginning June 21, 1954, or any prior date upon which construction operations were begun. The contract also provided for “reshaping” of the detour “after the completion of the grading operations by Gage County” and the spreading of a windrow of crushed rock “previously placed by Gage County.” The contract further provided that telephone poles within the limits of the proposed construction “will be moved by their owners * * * in advance of grading operations. The contractor shall perform all work beyond the pole lines * * * after the pole lines have been moved.”

On June 21, 1954, Roberts could not begin work on the north 2 miles of the project because the telephone *823 poles were in the way; Roberts could not begin work on the south 5 miles of the project because the detour was not available; and Roberts could not begin work on the detour because Gage County had not completed its work.

The evidence shows without dispute that at about the time the State was advertising for bids on the contract in question, it entered into a supplemental agreement allowing Gage County 90 working days in which to complete its work upon a part of the detour; that the grading work on the detour to be done by the county was not completed until sometime after July 17, 1954; that the delivery of the rock to be supplied by Gage County on the detour was not completed until August 26, 1954; that the telephone poles along the north 2 miles of the project were not moved until about August 9, 1954; and that much of the surfacing on the detour failed and required reconstructing and patching.

There is conflict in the evidence as to what caused the delay in this case but the evidence is sufficient to sustain the finding of the trial court that the State was responsible for a substantial amount of the delay that Roberts encountered in the performance of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reichert v. Rubloff Hammond, L.L.C.
645 N.W.2d 519 (Nebraska Supreme Court, 2002)
Nebraska Public Power District v. Austin Power, Inc.
773 F.2d 960 (Eighth Circuit, 1985)
Meisinger Earth Moving, Inc. v. State
324 N.W.2d 387 (Nebraska Supreme Court, 1982)
Omaha Paper Stock Co. v. California Union Insurance
262 N.W.2d 175 (Nebraska Supreme Court, 1978)
W. Wright, Inc. v. Korshoj Corp.
250 N.W.2d 894 (Nebraska Supreme Court, 1977)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
Craig Ex Rel. Craig v. Gage County
208 N.W.2d 82 (Nebraska Supreme Court, 1973)
Movie Films, Inc. v. First Security Bank of Utah, NA
447 P.2d 38 (Utah Supreme Court, 1968)
Appeal of Parsons Construction Company
146 N.W.2d 211 (Nebraska Supreme Court, 1966)
Lincoln Welding Supply Co. v. Western Contracting Corp.
128 N.W.2d 621 (Nebraska Supreme Court, 1964)
Caster v. Moeller
125 N.W.2d 89 (Nebraska Supreme Court, 1963)
In Re Fisher's Estate
113 N.W.2d 625 (Nebraska Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
111 N.W.2d 767, 172 Neb. 819, 1961 Neb. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-appeal-of-roberts-construction-company-neb-1961.