Appeal of Parsons Construction Company

146 N.W.2d 211, 146 N.W.2d 221, 180 Neb. 839, 1966 Neb. LEXIS 617
CourtNebraska Supreme Court
DecidedNovember 11, 1966
Docket36277
StatusPublished
Cited by7 cases

This text of 146 N.W.2d 211 (Appeal of Parsons Construction Company) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Appeal of Parsons Construction Company, 146 N.W.2d 211, 146 N.W.2d 221, 180 Neb. 839, 1966 Neb. LEXIS 617 (Neb. 1966).

Opinion

Spencer, J;

This is an appeal from the disallowance of a claim for $43,574.48 to cover increased costs occasioned by the breach of certain conditions of a construction contract by the State of Nebraska. The claim was disapproved by the State Engineer and disallowed by the Auditor of Public Accounts and the Secretary of State of the State of Nebraska.

The contract out of which the claim arose involved the building of two viaducts, which will hereinafter be referred to as the south and north bridges. It was one of several contracts included in a highway construction project on the Union-Omaha road (U. S. Highway No. 73-75) near Plattsmouth, Nebraska, in Cass County. One of the other successful bidders was Booth and Olson, Inc., a heavy highway contractor. Its contract covered grading, paving, and culvert work, and included the installation of the embankment fills for the bridges. It was necessary that certain culvert work and the embankment fills be completed before the plaintiff could begin work on its contract. The plans for the project used by the plaintiff as a basis for its bid had written above the profile for the bridge embankment the following: “Embankment to' be constructed by the grading contractor before the bridge work begins.”

All of the contracts on the project included an agreement that no work would be started prior to April 7, 1958. Subsequent to the acceptance of its bid, plaintiff notified the State that it desired a beginning date, of April 7, 1958, on the south bridge, and of April 25, 1958, on the north bridge. These dates were approved by the State. Booth and Olson, Inc., who was to do the necessary grading and fill work before the plaintiff could be *841 gin on its contract, also had a starting date of April 7, 1958. This fact was known to the plaintiff when it submitted its schedule of work, but it contends that the State, having approved its starting date, was obligated to coordinate the work and require the grading contractor to build the necessary embankments immediately.

On March 28, 1958, plaintiff notified Booth and Olson, Inc., that it would like to start on the south bridge not later than May 7, 1958, and on the north bridge not later than May 21, 1958. On April 2, 1958, plaintiff wrote the construction engineer for the State as follows:

“Re: Projects
FG-475 (2-3) Plattsmouth
IN-01-09 (21) Millard
“Dear Mr. Graham:
“Following your suggestion we contacted Booth and Olson, Inc., in regard to -this grading and the abutment fill on our projects near Plattsmouth and mailed you a copy of our letter. We are enclosing a copy of their reply. “While we want to cooperate in every way possible with your office toward expediting the schedules on this project, it is our opinion that your office will have to take the responsibility of determining when the abutment fills will be in place so we can start our work. We have no power or authority over the contractors who are to place these fills and feel that we would be out of order to attempt to set their schedules.
“We have come to the conclusion that our construction schedules on the above projects will have to be revised and we will make our revised (revision) as soon as your department notifies us when we can expect the abutment fills to be in place. We are hoping that we can tentatively set the starting time now on FG-475 (2-3) about May 7, 1958, and IN-01-09(21) about June 7, 1958.
“Yours truly,
PARSONS. CONSTRUCTION COMPANY
Earl G. Hawkins
President.”

*842 The Millard project referred to- in the above letter is not included in this action. Project FG-475 (2-3) covers the two bridge projects involved herein.

There is a dispute as to when the sites were actually available and ready fo-r the plaintiff. Plaintiff’s testimony is that the job- site was not available until August 4, 1958, and that it began work on August 11, 1958, on the south bridge, and on August 26, 1958, on the north bridge. The State’s evidence is to the effect that the embankments for the south bridge were- entirely completed by June 18, 1958. On June 9, 1958, the State notified the plaintiff that the south bridge site was available to them June 16, 1958.

The evidence for the State indicates that the last fill on the north bridge was not completed until July 22, 1958, but that there was ample work the plaintiff could have done previous to that date. In this respect, the State’s evidence indicates that the work o-n the north bridge could have been started as soon as the south abutment on that project was built, which was June 4, 1958. The north bridge was the larger project, and there was sufficient area between the two embankments to permit work on the completed embankment and some of the area adjacent to it.

After the embankments were in, it was necessary for the State to- stake the project before the plaintiff could begin its operation. There is a dispute as to when this was done. The specifications, which were a part of the plans used by the plaintiff in the submission of its bid, contain the following pro-visions on staking: “2. The department shall not be responsible for delays due to lack of grade or line stakes unless the contractor in moving on the work shall have given one week’s notice and, thereafter, unless the contractor shall have given the engineer 48 hours’ notice that such stakes, would be needed.” There is a dispute as to whether or not notice was ever given by the plaintiff to the State that the stakes were needed. It is the State’s contention that the stakes were *843 set without notice as soon as possible after the project was ready for stakes.

The State further contends that the plaintiff did not start work previous to- August 11, 1958, because of a carpenter’s strike from June 9, 1958, to early in August 1958, which prevented it from doing so. On June 20, 1958, 4 days after plaintiff had been advised the south bridge site would be ready, plaintiff sent the State the following letter:

“Attention: Mr. L. O. Graham
Construction Engineer
Re: Project No. FG-475(2) and F-FG-475(3) near Plattsmouth, Nebraska Carpenter Strike
“Dear Mr. Graham:
“We are unable to start the above referenced project because our firm as a member of the Associated General Contractors Employer’s Association of Omaha has been a victim of strike by the Omaha Carpenter’s District Council A. F. of L., C. I. O. and we are unable to start this job due to' this action.
“As per the general conditions in the specifications governing our work, we hereby request an extension to the construction period of our contract equal to one and one-half the period of the actual construction time lost plus a period of re-organization of equipment and job' personnel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Able Electric Co. v. Vacanti & Randazzo Construction Co.
324 N.W.2d 667 (Nebraska Supreme Court, 1982)
W. Wright, Inc. v. Korshoj Corp.
250 N.W.2d 894 (Nebraska Supreme Court, 1977)
Farmer's Union Co-Op Co. of Mead v. Flamme Bros.
245 N.W.2d 464 (Nebraska Supreme Court, 1976)
HD Fager Oil Co., Inc. v. VAINCE
224 N.W.2d 372 (Nebraska Supreme Court, 1974)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
Knight Bros., Inc. v. State
199 N.W.2d 720 (Nebraska Supreme Court, 1972)
Weiner v. Hroch
196 N.W.2d 907 (Nebraska Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W.2d 211, 146 N.W.2d 221, 180 Neb. 839, 1966 Neb. LEXIS 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/appeal-of-parsons-construction-company-neb-1966.