Able Electric Co. v. Vacanti & Randazzo Construction Co.

324 N.W.2d 667, 212 Neb. 619, 1982 Neb. LEXIS 1263
Nebraska Supreme Court·Decided October 1, 1982·No. 44402·Published·Cited by 4 cases

Opinion

Krivosha, C.J.

This appeal arises out of a suit filed by the appellee, Able Electric Co., an electrical subcontractor, against the appellant, Vacanti & Randazzo Construction Company, a general contractor. Following trial, a judgment in favor of Able and against Vacanti in the amount of $15,156.40 was returned by a jury. Vacanti has appealed to this court, essentially maintaining that the trial court committed error by reason of certain of the instructions given by the court to the jury. We have examined the record and conclude that the claims of appellant are without merit and that the judgment should be affirmed.

Vacanti, as general contractor, entered into a contract for the construction of a building in Council Bluffs, Iowa. The general contract between the owner and Vacanti contained a clause requiring the project to be completed within 450 days from the issuance of a notice to proceed. Thereafter, Vacanti entered into a subcontract with Able. Able was to perform the electrical work for the project. Able agreed to perform all the work for a price “not to *621 exceed” $120,000. The subcontract entered into between Vacanti and Able provided in part that Able would ‘‘complete all work under the job schedule time period set up by the General Contractor and Owner.” Able also agreed to ‘‘assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the aforesaid documents toward the Owner, in so far as they are applicable to this particular sub-contract.”

The project manual which included the job specifications and was made available to all the contractors and subcontractors in determining their bids further provided in part: “6. To complete the work within 450 calendar days of the notice to proceed.” The notice to proceed was issued on November 28, 1977.

The job was admittedly late in starting and by the spring of 1979 was far behind schedule. Able became concerned about this matter and contacted Vacanti. Abie’s president testified that it relied upon the 450-day completion period contained in the project manual in calculating labor costs, due to the fact that its employees’ union contract would expire in June of 1979, thereby affecting Abie’s cost of labor after June 1979. Able went to Vacanti and requested additional compensation to defray the increased costs. Based upon an expected completion date of mid-August 1979, Able offered to finish the job for an additional $10,500. Vacanti refused the offer. When it became apparent to Able that the project could not possibly be completed before its labor contract expired, Able left the job. The entire project was eventually completed in February or March of 1980, more than 1 year beyond the specified completion date as contained in the contract and the project manual.

As of April 30, 1979, Able had been paid a total of $82,800 for labor and materials valued at $92,000. The difference of $9,200 was withheld by Vacanti un *622 der a provision of the subcontract which entitled Vacanti to withhold 10 percent of the amount due to a subcontractor until completion of the project. In addition, Able did not receive payment for labor and materials furnished during May and June of 1979 in the amount of $5,956.40, although payment had been made by the owner to Vacanti.

Vacanti maintains that the verdict of the jury must be set aside because of improper instructions given by the trial court. Vacanti maintains that the trial court erred in giving instruction Nos. 3, 4, and 5, as they “placed undue emphasis upon the claims of the Plaintiff unsupported by the evidence which failed to state a cause of action.” We may dispose of that matter quickly. Instruction Nos. 3, 4, and 5 were merely an outline of Vacanti’s answer and cross-petition and Abie’s reply. Instruction No. 5 specifically advised the jury that “The foregoing outline of the contents of the pleadings of the parties are merely their statements and contentions made in this lawsuit; and, except as to any admissions contained therein, are not to be considered by the jury as evidence in the case.” Instruction Nos. 3, 4, and 5 merely advised the jury what the appellant’s issues were and were entirely proper. Watson Bros. Transp. Co. v. Jacobson, 168 Neb. 862, 97 N.W.2d 521 (1959). We are unable to determine how or in what manner Vacanti can find fault with those instructions.

Free access — add to your briefcase to read the full text and ask questions with AI

Able Electric Co. v. Vacanti & Randazzo Construction Co., 324 N.W.2d 667, 212 Neb. 619, 1982 Neb. LEXIS 1263 (Neb. 1982).

324 N.W.2d 667 (Able Electric Co. v. Vacanti & Randazzo Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Donaldson v. Farm Bureau Life Insurance
440 N.W.2d 187 (Nebraska Supreme Court, 1989)
Ford v. First Municipal Leasing Corporation
838 F.2d 994 (First Circuit, 1988)
Ford v. First Municipal Leasing Corp.
838 F.2d 994 (Eighth Circuit, 1988)