W. Wright, Inc. v. Korshoj Corp.

250 N.W.2d 894, 197 Neb. 692, 1977 Neb. LEXIS 1081
CourtNebraska Supreme Court
DecidedFebruary 23, 1977
Docket40628
StatusPublished
Cited by11 cases

This text of 250 N.W.2d 894 (W. Wright, Inc. v. Korshoj Corp.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. Wright, Inc. v. Korshoj Corp., 250 N.W.2d 894, 197 Neb. 692, 1977 Neb. LEXIS 1081 (Neb. 1977).

Opinion

Brodkey, J'.

This is an appeal from the verdict of a jury, and judgment entered thereon, by the District Court for Douglas County, upholding the claim of a subcon *693 tractor for damages against the prime contractor for additional expenses incurred by the subcontractor as a result of suspension of work on a contract between the U.S. Government and the prime contractor. We affirm in part, and in part reverse and remand with directions.

In May 1972, the United States Government, through the Corps of Engineers, awarded a general contract to Korshoj Corporation (“Korshoj”), the defendant and appellant herein, for the construction of cooling towers and miscellaneous items at Offutt Air Force Base. W. Wright, Inc. (“Wright”), the plaintiff and appellee herein, submitted a bid as a subcontractor to Korshoj. This bid was accepted and a subcontract was executed on May 24, 1972. Under this subcontract, Wright agreed to be bound by all terms and conditions of the general contract, which was incorporated by reference into the subcontract. Wright agreed to do the mechanical work on the project, and the subcontract obligated Wright “to furnish materials and perform all of the work to be done by him hereunder promptly and in due time when required and as directed by the Contractor * * The subcontract also provided that Wright “shall be bound by any changes, alterations or amendments as is the Contractor made by the Owner concerning the subject matter of this contract.” The subcontract contained no provision regarding remedies for Wright should the project be delayed, causing additional expenses to Wright. The subcontract price was $228,500, and it provided that “the Subcontractor shall not be entitled to nor receive any compensation for extra work or additional work unless such extra work or additional work is approved in writing by the Contractor through its office at Omaha, Nebraska.”

The general contract provided that the project was to be completed within 180 days after the time the Corps of Engineers gave Korshoj notice to proceed. The general contract provided that Korshoj was en *694 titled to an equitable adjustment on the contract price if changed site conditions caused an increase in its cost of, or time required for, performance of any part of the work. It also permitted the Corps of Engineers to suspend, delay, or interrupt the work, but Korshoj was entitled to an adjustment in contract price in the event that such suspension, delay, or interruption caused an increase in its cost of performance.

Korshoj received notice to proceed on May 15, 1972, and began work within 10 days, in accordance with the terms of the general contract. A rain washout created difficulty with the proposed project site, however, and as a result work was delayed until July 6, 1972, at which time the Corps of Engineers agreed to certain modifications regarding the changed site, and again advised Korshoj to proceed.

Although Wright did minor work on the project in July, it was unable to do its primary job because completion of the concrete shells in the cooling towers, work to be done by Korshoj, was required before Wright could begin its mechanical work of installing “internals” in the towers. Both parties understood that Wright’s primary job would take 90 to 120 days after the completion of the concrete shells in the towers by Korshoj.

Subsequently Korshoj entered into negotiations with the Corps of Engineers to obtain time extensions on the general contract due to the delays caused by the changed site conditions. Ultimately three modifications were signed by Korshoj and the Corps of Engineers, extending the completion date on the project from November 12, 1972, to March 12, 1973. Pursuant to these modifications, Korshoj received adjustments on the contract price, including extra compensation for additional supervisory and overhead expenses caused by the delays.

When Wright learned that Korshoj was seeking extensions on the general contract, it advised Korshoj, first orally and then in writing, that it wished to be *695 compensated for additional costs it was incurring due to the delays on the project. Korshoj did not immediately respond to Wright’s request, but continued to negotiate for extensions of time with the Corps of Engineers, and eventually signed the general contract modifications which granted the extensions of time without advising Wright of that fact. Korshoj then notified Wright that the completion date for the project had been extended to March 12, 1973. A week after so advising Wright, Korshoj wrote Wright and stated that “[i]f you intend to be paid for any additional work or compensations your documented statements should also be presented to this office for submittal to proper authority promptly.” Wright then submitted to Korshoj a claim of $4,400 as its increased costs due to the delays, costs which consisted of additional supervisory and overhead expenses.

Korshoj forwarded Wright’s claim to the Corps of Engineers. The Corps rejected the claim, stating that it could not address the matter because all modifications between it and Korshoj had been negotiated for price and time extensions in good faith, and that they were complete and beyond further requirements by the Corps. Korshoj advised Wright of the Corps’ rejection of Wright’s claim, and Wright then informed Korshoj that it was looking to Korshoj for payment. Korshoj replied, stating that it would deny Wright’s claim because Korshoj was not responsible for any of the delays on the project.

Wright did complete its work on the project, working in the completed towers from January 1973, to April 1973. It was unable to begin its work in the towers until January 1973, because Korshoj had not completed the towers until that time. It is undisputed that Wright did work on the job continuously from November 1972, to April 1973, but that it did so with a reduced work force because the delays prevented it from doing the work in 90 to 120 days with a full-work force. It is *696 clear that Wright incurred additional supervisory and overhead expenses due to having to complete the work over an extended period of time.

Wright subsequently brought an action against Korshoj on January 23, 1974, alleging that during “the course of the work under Plaintiffs subcontract certain changes in and additions thereto were directed by the Corps of Engineers and Defendant for which Plaintiff was and is entitled to additional compensation under the terms of the contract documents.” This allegation was subsequently amended to delete the words “under the terms of the contract documents.” The petition listed among the changes “additional supervisory and overhead expense incurred as a result of the suspension of the work, during the course thereof, by the owner and Defendant,” said expense being $4,400. The petition also alleged that Korshoj owed Wright a total of $1,593.45 for other work that Wright had performed, but the parties stipulated during trial that Wright was entitled to this claim, and this part of the petition is not at issue in this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whorley v. First Westside Bank
485 N.W.2d 578 (Nebraska Supreme Court, 1992)
Grand Island Production Credit Ass'n v. Humphrey
388 N.W.2d 807 (Nebraska Supreme Court, 1986)
GRAND ISLAND PRODUCTION CREDIT v. Humphrey
388 N.W.2d 807 (Nebraska Supreme Court, 1986)
Thatcher Engineering Corp. v. Bihlman
473 N.E.2d 1022 (Indiana Court of Appeals, 1985)
Kansas-Nebraska Natural Gas Co. v. Swanson Bros.
338 N.W.2d 774 (Nebraska Supreme Court, 1983)
Pearce v. Elic Corp.
329 N.W.2d 74 (Nebraska Supreme Court, 1982)
Able Electric Co. v. Vacanti & Randazzo Construction Co.
324 N.W.2d 667 (Nebraska Supreme Court, 1982)
Havelock Bank of Lincoln v. Bargen
321 N.W.2d 432 (Nebraska Supreme Court, 1982)
Omaha Paper Stock Co., Inc. v. Harbor Ins. Co.
445 F. Supp. 179 (D. Nebraska, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
250 N.W.2d 894, 197 Neb. 692, 1977 Neb. LEXIS 1081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-wright-inc-v-korshoj-corp-neb-1977.