Omaha Paper Stock Co., Inc. v. Harbor Ins. Co.

445 F. Supp. 179, 1978 U.S. Dist. LEXIS 20229
CourtDistrict Court, D. Nebraska
DecidedJanuary 11, 1978
DocketCiv. 75-0-454
StatusPublished
Cited by5 cases

This text of 445 F. Supp. 179 (Omaha Paper Stock Co., Inc. v. Harbor Ins. Co.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Omaha Paper Stock Co., Inc. v. Harbor Ins. Co., 445 F. Supp. 179, 1978 U.S. Dist. LEXIS 20229 (D. Neb. 1978).

Opinion

MEMORANDUM OPINION

SCHATZ, District Judge.

This litigation results from a major fire which destroyed substantial stock and also damaged equipment and buildings of plaintiff, Omaha Paper Stock at 1401 Laird Street, Omaha, Nebraska. The different categories of types of damage were separately insured under different policies by different insurers. The insurance policy involved here was written by Harbor Insurance Company to cover the “use and occupancy” of the 1401 Laird Street plant. (This coverage has also been referred to as “business interruption” coverage.) Plaintiff’s operations at the Laird Street plant were suspended from the time of the fire, April 20, 1975, until October 21, 1975, a total of 152 days. At issue is whether the suspension of operations at Laird Street is covered under the use and occupancy policy and if so, whether Harbor Insurance Company must pay the per diem rate for the full 152 days or for only a portion thereof.

The facts are these: plaintiff Omaha Paper Stock Company (hereafter OPS) processes waste paper for sale. It operates two plants in this city: the Laird Street plant which processes large quantities of low-grade papers and a plant at 18th Street which processes higher grades of paper and requires more personal handling in the operations than does the Laird Street plant.

Prior to the fire, the paper market became severely depressed. As a result, OPS decided to stockpile its waste paper until the market conditions changed for the better. At the time of the fire, OPS had approximately sixteen thousand tons of paper at the Laird Street plant. The fire in question destroyed the entire stock. Eight million gallons of water were required to extinguish the fire and as a direct result, the physical plant, aside from the ground surrounding the buildings, was flooded.

OPS was unable to operate the Laird Street plant until the grounds were cleared of debris and the equipment was back in working condition. The plant equipment consisted in part of a baling machine and several conveyor belts of various sizes which fed the paper into the baler. The conveyors were continuous belts that approached the baler from several directions. In the case of three of these conveyors, the lower half of the continuous belt moved in a pit which was below ground or floor level. During the time that the fire was being extinguished, these pits filled with water, thus submerging the metal belts and causing extensive rust and corrosion of the belts. In order for the plant to resume operation, the damage to the conveyor belts had to be remedied either by repair or replacement. On April 30, following the fire, the insurance adjusters for all companies insuring the various losses, General Adjustment Bureau (hereafter GAB), OPS personnel, the public adjuster hired by OPS (Mr. Conant) and the original installers of the equipment in question met to survey the damage. The installer’s opinion was that the conveyor belts were beyond repair and should be replaced. He estimated that the conveyor belts could be delivered within twelve to fourteen weeks. GAB, through its engineer (Mr. Rogers) felt that the belts could be dismantled, cleaned, oiled and re *182 paired. No decision to repair or replace was made at that point. During the next two weeks, GAB explored both the possibility of repair as well as of replacement, securing estimates for both.

By May 15, power had been restored to the building. GAB’s engineer, accompanied by the OPS equipment service man, attempted to operate the conveyor belts to ascertain the extent of damage. Upon discovering that the rust was causing the belts to buckle on their tracks, the conveyor belts were shut off, having only operated for somewhere between half a minute to three minutes.

By letter of May 19, Economy Baler Company (hereafter Economy), one of the companies contacted, confirmed its offer of a delivery time of four to six weeks for new replacement conveyor belts. Economy also agreed to install the equipment. However, no order was placed at that time.

Approximately a week later, GAB authorized the replacement of the belts and instructed Robert Epstein, president of OPS, to place the order with Economy as per the earlier quotation stated in the letter sent by Economy to GAB. Epstein telephoned Economy and placed the order. It is unclear whether Epstein or his public adjuster Conant had seen the quotation confirmation at the time that Epstein referred to it in placing his order.

The belts arrived in Omaha on June 27, 1975. When they arrived OPS notified GAB of their arrival so that installation could proceed. However, Economy had forgotten about its role concerning the installation contract and had made no arrangements. On July 14, its installer, Edward Cavanaugh, Jr., arrived in Omaha, but without men or equipment, expecting OPS to provide both. OPS was unaware of its intended participation in the installation role and was unable to supply either manpower or equipment. Unable to begin work, Cavanaugh left the next day and did not return. GAB assumed the responsibility to provide another installer and asked Epstein to contact Charles Cook, the original installer of the equipment, to ascertain whether Cook could install the equipment. Cook agreed but only in light of pre-existing commitments to finish other jobs.

Cook arrived on July 23 to begin installation. In tearing down some of the machinery, it was then discovered that one of the drive shafts had been bent and needed replacement. Epstein ordered a replacement from Economy on July 26. A mistake was made in the order which was corrected on July 29. Cook worked the week of July 23 and was able to install one of the belts. On August 5, Cook discovered that the belt which had been installed thus far was a cleated belt as opposed to a non-cleated belt. A decision was made the next day by Cook, GAB and the public adjuster, Conant, to order replacement sections for the belt. The order was placed with Economy on August 8, but Economy did not ship the belts until late September and they were received by OPS on September 30. Consequently, Cook was unable to replace that belt until after October 1.

The entire installation process by Cook covered two and a half months since his crew was interrupted from time to time with previous commitments. Cook worked July 23 through 25, August 12 through 15, August 19 through 22, September 22 through 27, and finally, October 6 through the 10th. The only delay caused by the mistaken order of the cleated belt was in the final five days in October since the belt did not arrive until September 30. The reason that Cook did not work between August 22 and September 19 was because Cook had other commitments to meet and was uncertain about who was responsible to pay for the installation in question. After the cleated belt sections had been replaced with non-cleated sections, the equipment was tested on October 10. After the conveyors were completely assembled, the serviceman for the plant equipment finished checking the baler itself so that it was in workable order. It was impossible to make final repairs on the baler and to test it until conveyors were in operation and could feed the baler itself.

*183

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
445 F. Supp. 179, 1978 U.S. Dist. LEXIS 20229, Counsel Stack Legal Research, https://law.counselstack.com/opinion/omaha-paper-stock-co-inc-v-harbor-ins-co-ned-1978.