Doyle & Russell, Inc. v. Welch Pile Driving Corp.

194 S.E.2d 719, 213 Va. 698, 1973 Va. LEXIS 211
CourtSupreme Court of Virginia
DecidedMarch 5, 1973
DocketRecord 7966
StatusPublished
Cited by16 cases

This text of 194 S.E.2d 719 (Doyle & Russell, Inc. v. Welch Pile Driving Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doyle & Russell, Inc. v. Welch Pile Driving Corp., 194 S.E.2d 719, 213 Va. 698, 1973 Va. LEXIS 211 (Va. 1973).

Opinion

Poff, J.,

delivered the opinion of the court.

This is an appeal by Doyle & Russell, Inc., from a summary judgment order entered on July 7, 1971, awarding Welch Pile Driving Corporation the full ad damnum in its amended motion for judgment.

Welch, subcontractor, claimed damages against Doyle, general contractor, the owner, and the owner’s architect and engineer arising out of contracts for the construction of an addition to the Dixie *699 General Medical and Surgical Hospital for Hampton Training School for Nurses, Inc.

The defendants filed separate demurrers to the amended motion for judgment; all but that of Doyle were sustained.

At the pre-trial conference, the parties stipulated that the bases for Welch’s cause of action would be that “(a) Plaintiff is entitled to certain additional sums for additional work done as evidenced by the execution of change orders D-l, D-2, and D-6; (b) Plaintiff is entitled to compensation for additional work done during the course of its stay on the job, which additional work is in addition to that provided in the subcontract and change orders thereto; (c) Plaintiff is entitled to consequential damages for delays incurred because of the failure of the owner and/or his agents to advise plaintiff of the final driving schedule within a reasonable time after the driving of the test piles on November 4 and 5, 1964, there being an implied obligation on the part of the defendant, Doyle & Russell, to Welch under their contract to so provide Welch with a final driving schedule within a reasonable period of time.”

The parties stipulated further that “the delays complained of and the damages, if any, resulting therefrom were in no way occasioned or in any way caused by acts or omissions of Doyle & Russell or entities over whom Doyl'e & Russell had the right or obligation of direction or control.”

In context with the stipulation, the trial court entered a pre-trial order ruling as a matter of law that Doyle could not raise the defense that the delays incurred by Welch were caused by those over whom Doyle had no control; that the contract documents did not afford Doyle any defense to Welch’s claims; and that “the parties contemplated, at the time they entered into the contract, that damages, if any, to Welch resulting from delay caused by the owner or the architect or their agents were to be the responsibility of Doyle & Russell.”

The trial court ordered further that Doyle should not disclose to the jury that the delays were caused by those over whom Doyle had no control and that Welch should not disclose to the jury that it had no cause of action against the owner or the owner’s agents.

At trial, the evidence showed that the subcontract schedule required Welch to complete the pile driving project in 30 days. On November 4, 1964, Welch moved his crew and equipment on the job and proceeded to drive the test piles. Unexpected subsurface conditions were encountered. Differences of opinion developed *700 among the architect, the engineer, and Doyle’s project manager concerning pile driving requirements, standards and procedures. As orders were given and countermanded, Welch complied, stopping or. starting, continuing or suspending work according to the latest command. Between changes, there were protracted intervals in which Welch’s crew and 'equipment, stood idle. Some changes required Welch to perform work in addition to or different from the “scope of work” defined in the contract documents. As a result, the pile driving operation was not completed until January 20, 1965, some 78 days after commencement.

During the period of indecision and vacillation, three change orders were issued. Each was approved, by signature, by Doyle, the owner, and the architect. One required Welch to “Drive 6 addition 45' piles under west wall of North Wing.”; another provided, as an exception to the original specifications, for “Pre-jetting for piles to an elevation of minus 16 ... at the option of the Contractor on all remaining pile foundation work in the North Wing area.”; the third gave authority to “Modify pile driving procedure in the South Wing as follows: . . .”.

Each change order provided that “It is acknowledged that a change in price is involved subject to later determination.” Welch submitted three itemized invoices addressed to the three change orders. No item was challenged as unreasonable, and Doyle’s project manager testified that he considered them fair.

At the conclusion of all the evidence, the trial court sustained Welch’s motion to strike Doyle’s evidence and entered summary judgment for Welch. The judgment order was based on the three change orders, and damages were measured by Welch’s three invoices in the total sum of |22,874.78. The trial court denied Welch’s claim for interest from January 20, 1965, the date of completion of his contract. Doyle gave notice of appeal and assigned as error the trial court’s rulings in the pre-trial order and the entry of summary judgment for Welch. Welch assigned as cross error the ruling denying interest.

The essential question raised by Doyle’s several assignments of error is whether a general contractor is liable to its subcontractor for es flowing from delays not caused by the general contractor or any person or circumstance under his control.

Absent a contractual commitment contra, a general contractor is not liable to its subcontractor for damages flowing from delays incurred by the subcontractor unless the delays were caused by the *701 general contractor or some agency or circumstance under his direction or control. Norcross v. Wills, 198 N.Y. 336, 91 N.E. 803 (1910); McGrath v. Electrical Construction Company, 230 Ore. 295, 364 P.2d 604 (1961).

Doyle did not cause the delays. The question is whether Doyle had either an agency responsibility or a contractual responsibility for delay damages (as distinguished from compensation for additional work).

Clearly, there was no agency responsibility; the parties stipulated that neither Doyle nor any entities over whom Doyle had direction or control caused the delays.

However, the parties did not stipulate that Doyle had no contractual responsibility for the consequences of the delays. The thrust of the trial court’s pre-trial rulings, to which error is assigned, was that Doyle had assumed such contractual responsibility.

Article I of the subcontract, headlined “Scope of Work”, provides in part:

“The lump sum amount of this Subcontract is based on the number and lengths of piles specified. In the event the total number of piles or the approved scheduled lengths, or the minimum penetration specified be changed at the direction of the Architect, an adjustment in the Subcontract amount will be made as follows: . . .”

Article IV of the subcontract, headlined “Changes in the Work”, provides in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lagerman v. Charter Communities, Inc.
34 Va. Cir. 331 (Stafford County Circuit Court, 1994)
Reid v. Ayscue
436 S.E.2d 439 (Supreme Court of Virginia, 1993)
Triangle Sheet Metal Works, Inc. v. JAMES H. MERRITT & CO.
588 N.E.2d 69 (New York Court of Appeals, 1991)
Marriott Corp. v. Thomas P. Harkins, Inc.
30 Va. Cir. 515 (Fairfax County Circuit Court, 1990)
Nelson v. Commonwealth
368 S.E.2d 239 (Supreme Court of Virginia, 1988)
Marks v. Sanzo
345 S.E.2d 263 (Supreme Court of Virginia, 1986)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Thatcher Engineering Corp. v. Bihlman
473 N.E.2d 1022 (Indiana Court of Appeals, 1985)
Coastland Corp. v. Third National Mortgage Co.
611 F.2d 969 (Fourth Circuit, 1979)
Hewitt v. Hutter
432 F. Supp. 795 (W.D. Virginia, 1977)
Continental Masonry Co. v. Verdel Construction Co.
369 A.2d 566 (Court of Appeals of Maryland, 1977)
W. Wright, Inc. v. Korshoj Corp.
250 N.W.2d 894 (Nebraska Supreme Court, 1977)
Builders Equity Corp. v. Hurwitz
530 F.2d 1072 (D.C. Circuit, 1976)
Roanoke Hospital Ass'n v. Doyle & Russell, Inc.
214 S.E.2d 155 (Supreme Court of Virginia, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
194 S.E.2d 719, 213 Va. 698, 1973 Va. LEXIS 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doyle-russell-inc-v-welch-pile-driving-corp-va-1973.