Marriott Corp. v. Thomas P. Harkins, Inc.

30 Va. Cir. 515, 1990 Va. Cir. LEXIS 437
CourtFairfax County Circuit Court
DecidedMay 15, 1990
DocketCase No. (Law) 94589
StatusPublished

This text of 30 Va. Cir. 515 (Marriott Corp. v. Thomas P. Harkins, Inc.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marriott Corp. v. Thomas P. Harkins, Inc., 30 Va. Cir. 515, 1990 Va. Cir. LEXIS 437 (Va. Super. Ct. 1990).

Opinion

BY JUDGE LEWIS HALL GRIFFITH

This matter is before the Court on the Motion to Strike and Dismiss a Portion of Defendant’s Counterclaim (“Motion to Strike”) filed by the Plaintiff Marriott Corporation. The parties briefed and argued the issue. The Court grants Marriott’s Motion to Strike for the following reasons.

The Defendant, Thomas P. Harkins, Inc., seeks two forms of relief in its Counterclaim. In numbered paragraph three of the Counterclaim, Harkins seeks to recover damages which it suffered as a result of Marriott’s alleged material breaches of contract and Marriott’s alleged interferences with contracts; this claim is not the subject of this motion. In numbered paragraph four, Harkins seeks to recover damages on behalf of the following subcontractors: A. Tasker, Inc., t/a Saleo Mechanical Contractors, The Aitken Company, O’Dell Electric, Stedman Construction Companies, Inc., and Progressive Wallcovering.

The relevant portions of the Counterclaim, as amended by Orders of the Court and by the Bill of Particulars, allege that certain subcontractors “submitted claims [to Harkins] for additional work and/or acceleration which are the fault or responsibility of Plaintiff.” These costs were exclusive of any claimed in paragraph three. The amended Counterclaim requests different amounts beside each subcontractor’s name, plus four percent overhead and three percent profit; Harkins asserts it “is entitled to receive” these sums as compensation for the benefit of the named subcontractors.

[516]*516The Bill of Particulars on the Counterclaim indicates that these claims are based on the same allegations of misconduct contained in paragraph three. Harkins also maintains that:

the nature of this two-year construction project with its continuing history of changes, delays, disruptions, etc., make it impossible for Defendant to inform Plaintiff in a pleading of all specific facts, circumstances, and conduct which form the basis of the Counterclaim

(Harkins’ Bill of Particulars at p. 5.) Counsel for Harkins indicated in argument that the subcontractors incurred these costs to pay additional labor, supervisory personnel, and overhead to perform the work at the scheduled pace after Marriott had caused the various delays.

Marriott’s Answer denies the allegations in the relevant portion of the Counterclaim. Marriott asserted the following defenses: failure to state a claim upon which relief may be granted, estoppel and waiver, accord and satisfaction, and failure to comply with conditions precedent to payment. Marriott further asserted that Harkins’ claims were subject to offset for work Harkins performed improperly and for damage to the work of other subcontractors that was caused by Harkins.

Marriott moved to strike and dismiss this portion of the Counterclaim. Marriott contends that Harkins’ pleadings fail to support the claim. Marriott argues that Harkins is not liable to the subcontractors for the claimed amounts, based on Harkins’ refusal to plead or admit any liability to the subcontractors, as well as on settlements between Harkins and the subcontractors. Marriott also argues that when a contractor is not liable to subcontractors, pass-through claims cannot be recovered because of lack of privity of contract between the owner and the subcontractors.

Hankins asserts that because Marriott failed to plead lack of standing as an affirmative defense, Marriott’s motion is untimely. Harkins also relies on the 1988 case of The George Hyman Construction Co. v. McLean Hotel Associates Limited Partnership, 14 Va. Cir. 187 (1988), in which this Court denied a motion for partial summary judgment in a case raising similar issues. Harkins seeks to avoid the effect of a recent Virginia Court of Appeals case, APAC-Virginia v. Department of Highways and Transportation, 9 Va. App. 450, 388 S.E.2d 841 (1990), which appears to have decided the issue in the opposite manner. Harkins maintains that this court is not bound by the appellate decision [517]*517because the Court of Appeals has no jurisdiction to review the decision. Harkins also attempts to distinguish the facts and the reasoning of the APAC case from the Hyman case to show that the Hyman ruling survives the ABAC case and should govern the case at bar.

As a preliminary matter, the Motion to Strike should be treated as a motion for summary judgment in the procedural posture of this case. See e.g., Costner v. Lackey, 223 Va. 377, 381, 290 S.E.2d 818, 820 (1982) (motion to strike was, in effect, a motion for summary judgment). Such a motion should be granted only if there is no genuine dispute over a material fact and the action is barred as a matter of law. In ruling on the motion, the Court considers, inter alia, pleadings, pretrial orders, and any admissions. Rule 3:18, Rules of the Supreme Court of Virginia. The Court also considers the copies of settlement agreements between Harkins and subcontractors, which documents were attached to Marriott’s supporting memorandum as exhibits and were used in Marriott’s oral and written argument, without objection from Harkins. Such documents may appropriately be considered in a motion for summary judgment. Cf., Richmond Development and Housing Authority v. Laburnam Construction Corp., 195 Va. 827, 831, 80 S.E.2d 574 (1954) (affimn mrming summary judgment under former Rule 3:20 based, inter alia, on the pleadings, contract and accompanying documents, and answers to interrogatories and the exhibits in connection therewith); and Bryson, Handbook on Civil Procedure, 2d ed. 258 (Michie 1989) (summary judgment can be based, inter alia, on documents produced pursuant to Rule 4:9).

Summary judgment is appropriate in the present circumstances because the record before the Court shows that them is no genuine dispute over any material fact, and the Counterclaim is barred as a matter of law. The Counterclaim fails to set forth any facts giving rise to a cause of action cognizable under Virginia law. Although Virginia law has progressively evolved towards the theory of notice pleading, a pleading must still set forth facts warranting the grant of the relief sought, e.g., Ted Lansing Supply Co. v. Royal Aluminum & Construction Corp., 221 Va. 1139, 277 S.E.2d 228, 229 (1981). “No court can base its decree upon facts not alleged, nor render its judgment upon a right, however meritorious, which has not been pleaded and claimed ... and if so entered, [the decree] is void ...” Id. at 1141, 277 S.E.2d at 229. Harkins should not be allowed to prove what it has failed to plead.

[518]*518The Counterclaim as amended merely concludes that Harkins is entitled to recover compensation for the benefit of subcontractors who submitted claims based on Marriott’s unjustified requests for accelerated performance. Hankins identifies no basis for the claims asserted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Copenhaver v. Rogers
384 S.E.2d 593 (Supreme Court of Virginia, 1989)
Brokers, Inc. v. High Point City Board of Education
234 S.E.2d 56 (Court of Appeals of North Carolina, 1977)
Ted Lansing Supply Co. v. Royal Aluminum & Construction Corp.
277 S.E.2d 228 (Supreme Court of Virginia, 1981)
Doyle & Russell, Inc. v. Welch Pile Driving Corp.
194 S.E.2d 719 (Supreme Court of Virginia, 1973)
Cemetery Consultants, Inc. v. Tidewater Funeral Directors Ass'n
254 S.E.2d 61 (Supreme Court of Virginia, 1979)
Apac-Virginia, Inc. v. Virginia Department of Highways & Transportation
388 S.E.2d 841 (Court of Appeals of Virginia, 1990)
Blake Const. Co., Inc. v. Alley
353 S.E.2d 724 (Supreme Court of Virginia, 1987)
Costner v. Lackey
290 S.E.2d 818 (Supreme Court of Virginia, 1982)
George Hyman Construction Co. v. McLean Hotel Associates Ltd. Partnership
14 Va. Cir. 187 (Fairfax County Circuit Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
30 Va. Cir. 515, 1990 Va. Cir. LEXIS 437, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marriott-corp-v-thomas-p-harkins-inc-vaccfairfax-1990.