Roadmix Construction Corp. v. State

9 N.W.2d 741, 143 Neb. 425, 1943 Neb. LEXIS 89
CourtNebraska Supreme Court
DecidedMay 28, 1943
DocketNo. 31400.
StatusPublished
Cited by18 cases

This text of 9 N.W.2d 741 (Roadmix Construction Corp. v. State) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roadmix Construction Corp. v. State, 9 N.W.2d 741, 143 Neb. 425, 1943 Neb. LEXIS 89 (Neb. 1943).

Opinion

Wenke, J.

This action for damages for breach of a contract was commenced by the Roadmix Construction Corporation, appellee herein, filing its claim, with the auditor of public accounts, in the sum of $20,491.83 against the state of Nebraska, appellant herein, for work, labor, materials, supplies, and equipment as therein set forth by virtue of a contract entered into with the department of roads and irrigation on August 1, 1936, for the construction of 6.3 miles of bituminous sand surface on project No. 203-A in Antelope county, Nebraska, a federal aid project, which was completed and accepted on September 27, 1937. From a disallowance thereof appellee appealed to the district court for Lancaster county and in its petition on appeal claimed the amount thereof to be due for the following:

A. Amount of money retained by the state of Nebraska on Estimate No. 11, dated May 23, 1938 $ 2,573.88
B. 34,058 gal. of M-C-2 asphaltic oil applied on the work by direction of engineers, accepted by the state and unpaid at 9c per gallon 3,260.79
C. Extra manipulation and mixing expense due to erroneous directions of engineers *427 as to oil content to be applied to the aggregate to wit':
1. Pay roll 3,175.67
2. Gas and oil consumed by equipment 2,361.19
3. Equipment rental 6,469.47
4. Repairs on equipment , 732.65
5. Supervision, insurance, petty cash expense 1,362.18
G. Demurrage on 9 cars M-C-2 road oil on job and ready to be used 556.00
Total $20,491.83

for the reason that prior to September 27, 1937, the appellee fully performed the contract by completing the road according to the provisions of the contract and the same was on said day inspected and approved and accepted but in the construction thereof the appellee alleges that the appellant, through its engineers in the field, mistakenly and erroneously sampled and tested the soil in the road for the purpose of determining the amount of oil that should be used and because of these mistaken and erroneous tests the oil requirements so calculated were insuifcient, and when added to the surface material the appellee was not able to mix the surface in the manner desired and additional manipulation and mixing, together with additional oil, was required, and because appellant’s engineers misdirected the mixing and manipulation of the surface material after the oil was added it became dry and overaerated, filled with oil balls and dry streaks of surface material and as a result the appellee was damaged thereby for the additional labor, ■materials, work, supplies, and equipment as in the claim set forth, all of which constituted a breach of the contract. For the reasons herein set forth and for the further reason that possession of the highway for work was withheld from August 1 to August 8, 1936, the time limit as fixed by the contract was waived, together with the liquidated damages therefor. That at all times the appellee notified the appellant’s engineers', either orally or 'in writing, that it expect *428 ed- compensation for the extra work and materials required because thereof and demanded a written order or supplemental contract and agreement therefor which they failed and refused to give. Praying for a judgment requiring the proper officers to approve and allow the claim and issue a warrant for the amount thereof, with interest, to the appellee.

' To this petition on appeal the appellant, and all other defendants, filed an answer admitting the corporate capacity of the appellee and the contract entered into by it with the appellant through the department of roads and irrigation, but denying all other allegations of appellee’s petition, and further alleging the tests of the surface material on the highway were accurate and made by approved methods and indicated the proper amount of oil to be added; that the instructions given by the engineers in charge as to manipulation were proper and correct and if followed a proper road would have been obtained, but due to appellee not having proper road construction equipment and not applying the oil in accordance with instructions given but in a careless and negligent manner, a greater depth of soil was included in the mix than contemplated by the contract and specifications and as a result thereof the quantity of oil was insufficient; that the mixing and manipulation were done in a careless and negligent manner and due thereto oil balls formed in the mix and the same became overaerated, as a result of which it was not in proper condition to be accepted in the fall of 1936; that under the terms of the contract all of the work which was rejected was required to be remedied or removed and replaced in an acceptable manner by the appellee at its own expense; that appellee failed to complete the work within the time provided in the contract and was therefore subject to the provisions as to liquidated damages; and that all damage suffered was the result of careless, negligent, and incompetent manner of performing the terms of the contract. Praying that the claim on appeal be dismissed.

Appellee’s reply denies the allegation that it was careless *429 or negligent in the mixing and manipulating of the surface materials, alleges it had sufficient and proper equipment; that mixing of the surface soil at a greater depth than contemplated was at the direction of the appellant’s engineers in charge over appellee’s objections and caused by errors and mistakes of the engineers; that mixing to a certain depth was a physical impossibility because of the loose condition of the soil; that the oil balls were due to shortage of oil and excess of manipulation; that the appellant waived its claim to liquidated damages and praying for the allowance of its claim.

The matter was tried to the court, jury being waived, and the trial court found that on August 1, 1936, appellee and department of roads and irrigation of the state of Nebraska entered into a contract for the construction of the road described as Federal Aid Road No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Public Safety & Correctional Services v. Ara Health Services, Inc.
668 A.2d 960 (Court of Special Appeals of Maryland, 1995)
RaDec Construction Inc. v. School District No. 17
535 N.W.2d 408 (Nebraska Supreme Court, 1995)
RaDEC v. SCHOOL DIST. OF DOUGLAS COUNTY
535 N.W.2d 408 (Nebraska Supreme Court, 1995)
Weatherly v. Blue Cross Blue Shield Insurance
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
Weatherly v. BLUE CROSS BLUE SHIELD INS.
513 N.W.2d 347 (Nebraska Court of Appeals, 1994)
Williams v. Brown
437 S.E.2d 775 (West Virginia Supreme Court, 1993)
Opinion No. (1993)
Nebraska Attorney General Reports, 1993
J.L. Healy Construction Co. v. State
463 N.W.2d 813 (Nebraska Supreme Court, 1990)
Smith v. Sorensen
748 F.2d 427 (Eighth Circuit, 1984)
St. Paul Fire & Marine Insurance Co. v. Amerada Hess Corp.
275 N.W.2d 304 (North Dakota Supreme Court, 1979)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
In Re Appeal of Roberts Construction Company
111 N.W.2d 767 (Nebraska Supreme Court, 1961)
Humphreys v. J. B. Michael & Co.
341 S.W.2d 229 (Court of Appeals of Kentucky (pre-1976), 1960)
Fuchs v. Parsons Construction Company
88 N.W.2d 648 (Nebraska Supreme Court, 1958)
Reed v. Consolidated Feldspar Corp.
23 N.W.2d 154 (South Dakota Supreme Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
9 N.W.2d 741, 143 Neb. 425, 1943 Neb. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roadmix-construction-corp-v-state-neb-1943.