Lyman-Richey Sand & Gravel Co. v. State

243 N.W. 891, 123 Neb. 674, 83 A.L.R. 1301, 1932 Neb. LEXIS 267
CourtNebraska Supreme Court
DecidedJuly 29, 1932
DocketNo. 28437
StatusPublished
Cited by15 cases

This text of 243 N.W. 891 (Lyman-Richey Sand & Gravel Co. v. State) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lyman-Richey Sand & Gravel Co. v. State, 243 N.W. 891, 123 Neb. 674, 83 A.L.R. 1301, 1932 Neb. LEXIS 267 (Neb. 1932).

Opinion

Paine, J.

This is an appeal from a judgment rendered in the district court for Lancaster county for $4,006.46 against the state of Nebraska, together with an order directing the auditor of public accounts to issue and deliver a warrant to the appellee for said amount.

The extensive bill of exceptions in this case carries with it, as exhibit 5, the transcript of the proceedings had before the state auditor and secretary of state upon this claim, in which appears the original contract and specifications, making up a printed book of some 150 pages, which contract was entered into October 15, 1930, between the county of Douglas, by the chairman of its county board, and the department of public works of the state of Nebraska, by R. L. Cochran, its state engineer, as parties of the first part, and the Yant Construction Company, by its president, R. C. Yant, as party of the second part, for the paving by said construction company of state highway project No. 664-B, known as the Maple Street Road, which [676]*676paving extended five miles east from the intersection of that road with the Lincoln Highway, and lying northeast of the village of Elkhorn in Douglas county, Nebraska.

The case was brought to the district court on appeal from a decision of the auditor of public accounts and secretary of state, disapproving said claim of $4,006.46 to the amount of $2,643.49, but approving it as to the balance, of $1,362.97. Upon appeal, the case was tried in the district court for Lancaster county, without a jury, under the provisions of section 27-319, Comp. St. 1929, giving the district court jurisdiction to try appeals upon claims so disallowed.

It is admitted by the pleadings that this entire contract for five miles of paving was completed, according to its terms, within the time provided, and that the total contract amounted to the sum of $100,836.94, and that the deduction of $2,643.49, made by the state engineer from the last payment, without notice, is based upon the following provision of the contract, found in next to the last paragraph therein: “That it is mutually understood and agreed by the parties to this contract: That if the freight rates on materials required to complete this contract are increased after the date of the receipt of bids and before the date set for completing the work, the contractor will be paid extra an amount equal to the amount of the increase in freight rates on the materials required to complete this contract, likewise that deductions will be made should freight rates be decreased during said period.” That soon after receiving the contract from the state for this five miles of paving, Mr. Yant had received a bid from the Lyman-Richey Sand & Gravel Company to deliver the proper mixture of sand and gravel, referred to hereafter as “sand-gravel,” required under the contract, but, as Mr. Yant had leased a gravel pit in the vicinity, he did not finally decide whether to furnish the sand-gravel from his leased pit, or to contract with the Lyman-Richey Sand & Gravel Company until March 11, 1931, when he entered into a contract with that company to furnish all sand-gravel [677]*677for $11,599.72. At the time that it took the contract, the Lyman-Richey Sand & Gravel Company planned to haul the sand-gravel by truck from its Brown pit, which was directly west on the same section line and less than five miles in actual distance from this Maple Street job, from which Brown pit over 20,000 tons of gravel was trucked in the year 1931 to road construction jobs in the western part of Douglas county, and which would have required them to have paid 7 cents for transporting each cubic yard of sand-gravel each mile, or 35 cents per cubic yard to truck the same from the Brown pit. No railroad sidetrack was adjacent to the Brown pit, and the material from this, the nearest pit of the Lyman-Richey Sand & Gravel Company, would necessarily have been required to be transported by trucks.

The assistant general freight agent of the Union Pacific testified in the district court that the railroads had lost the greater part of the traffic in this commodity, as well as in live stock, stating that in 1930 and in 1931 90 per cent, of live stock going into South Omaha from a radius of 25 miles moved by truck, and that in March, 1931, the Union Pacific solicited the appellee to allow it to haul the sand-gravel for this Maple Street contract from its pits near Valley, Nebraska, which were upon the Union Pacific tracks at a distance of some 8.3 miles from the Maple Street job, for which haul the rate had been 90 cents per cubic yard, a cubic yard weighing about 3,000 pounds. The appellee company agreed to give this business to the Union Pacific if it could be hauled at the rate of $25 per 60-ton car, and thereupon the first emergency rate, to expire May 31,1931, was put in by the Union Pacific to secure the hauling of sand-gravel for this particular job, and in the application to the state railway commission, of April 1, 1931, as set out in exhibit 3, the Union Pacific stated that they were publishing this emergency rate “only for the purpose of meeting truck competition there present.” That the executive vice-president of the Burlington, Mr. Spens, asked Mr. George P. Abel, of the Abel Construction Company, to come to Chicago to tell them how the railroads [678]*678could obtain some of the gravel business, and after that conference it was decided that the Burlington would also install similar emergency rates between certain points, and the testimony discloses that Mr. Abel switched six or seven projects from truck to railroad haul under the emergency rates, but he testifies that no contractor gained anything by the change, for the railroads dropped their rates only just enough to meet the truck rates. Thereafter such emergency rates were extended to some 200 stations in Nebraska by the different railroads.

The appellant claims there were no established freight rates for shipping sand-gravel by trucks. The appellee denies this, and insists that practically all sand-gravel required for highway construction projects within ten miles of the Platte river during 1930 had been hauled by trucks, and that while the rates varied slightly, depending upon the length of the haul and the kind of roads over which it was to be transported, yet truck rates on sand-gravel had finally reached an average freight rate of 7 cents per cubic yard per mile upon all of such projects, and that this was well known to the highway department of the state.

It is conceded by all parties that the emergency railroad rate in this case, of $25 per 60-ton car, was still higher than the appellee could have had the sand-gravel hauled by truck from its Brown pit, but that there was a slight advantage in loading it at the Valley pits into railroad cars over loading it into trucks at the Brown pit, but that in dollars and cents it cost the appellee more to transport this sand-gravel to the Maple Street job by rail than it would have cost it to have transported it from the Brown pit by truck. The total shipment was 15,447 tons in 265 railroad cars.

The rail rate in force for the 8.2-mile haul from the Valley pit was, at the time of signing the contract, 60 cents per ton, or 90 cents per cubic yard, while the rate by truck for the five miles from the Brown pit was 35 cents per yard and 10 cents per yard for piling it in a stock pile, a total of 45 cents, or just one-half the rail rate then in force. The [679]*679emergency rail rate, of $25 per 60-ton car, was about 41 cents per ton, or 60 cents per yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DaLee Realty, Inc. v. Kuhl
305 N.W.2d 891 (Nebraska Supreme Court, 1981)
METRO. UTIL. DIST., ETC. v. Fid. & Dep. Co. of Maryland
264 N.W.2d 854 (Nebraska Supreme Court, 1978)
Metropolitan Utilities District v. Fidelity & Deposit Co.
264 N.W.2d 854 (Nebraska Supreme Court, 1978)
Custom Leasing, Inc. v. Carlson Stapler & Shippers Supply, Inc.
237 N.W.2d 645 (Nebraska Supreme Court, 1976)
Gallagher v. Vogel
61 N.W.2d 245 (Nebraska Supreme Court, 1953)
Triway Co. v. Teper
194 Misc. 996 (Albany City Court, 1949)
People v. Ackert
187 Misc. 67 (Middletown City Court, 1946)
Cox v. Rippe
19 N.W.2d 514 (Nebraska Supreme Court, 1945)
Roadmix Construction Corp. v. State
9 N.W.2d 741 (Nebraska Supreme Court, 1943)
Alexander v. Turner
297 N.W. 589 (Nebraska Supreme Court, 1941)
Henson v. Lamb
199 S.E. 459 (West Virginia Supreme Court, 1938)
Ericson v. Nebraska-Iowa Farm Investment Co.
278 N.W. 841 (Nebraska Supreme Court, 1938)
Helfrich v. Baxter
267 N.W. 922 (Nebraska Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
243 N.W. 891, 123 Neb. 674, 83 A.L.R. 1301, 1932 Neb. LEXIS 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lyman-richey-sand-gravel-co-v-state-neb-1932.