Edward E. Gillen Co. v. John H. Parker Co.

171 N.W. 61, 170 Wis. 264, 1919 Wisc. LEXIS 1
CourtWisconsin Supreme Court
DecidedDecember 2, 1919
StatusPublished
Cited by14 cases

This text of 171 N.W. 61 (Edward E. Gillen Co. v. John H. Parker Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward E. Gillen Co. v. John H. Parker Co., 171 N.W. 61, 170 Wis. 264, 1919 Wisc. LEXIS 1 (Wis. 1919).

Opinions

The following opinion was filed March 4, 1919:

Eschweiler, J.

The material points upon which the appealing defendant challenges the rulings of the court below and its disposition of the case are substantially as follows :

First. In entering judgment for $8,275, the amount fixed by the stipulation recited above of May 25, 1917, on the grounds: (a) that such amount, by the terms of the stipulation referred to, is out of this case and could form no part of thé judgment herein; and (b) that in any event it could not be allowed until and after the defendant itself had been paid its final balance due .from the owner of the building by reason of the terms of the contract.

[276]*276Second. In allowing interest from July 7, 1916, on the damages found, for the reason that, the claim for such being in the nature of unliquidated damages, interest was not a proper charge upon the same.

Third. That by the contract between the parties, particularly articles VIII and XXIII, above quoted, the parties had provided in effect that as between them the remedy plaintiff might have for any delay caused to plaintiff in its carrying on the work wás limited solely to an extension of time to be given to plaintiff for its completion of the work beyond the time stipulated in the contract equal to the length of time it was so delayed, and by necessary implication excluding any monetary allowance.

Fourth. In permitting the jury to consider improper elements of damages, if any such were to be allowed, in arriving at their verdict, including (a) rental value of plaintiff’s plant during such periods of delay; (b) the value of the services of Mr. Gillen, the president and general manager, and Mr.'Harrington, the secretary of the plaintiff.

We are satisfied the lower court took the proper view of the stipulation in holding that the purpose and intent was to withdraw, so far as the trial of the case was concerned, any question as to the amount of the items therein included, and to dispense with the necessity of proof being offered by either party on the trial with reference thereto, and that when the trial as to the disputed items was ended and ripe for judgment upon them there then should be included in any judgment the agreed sum of $8,275. The trial court was also right in holding that interest should be allowed by the language of the stipulation itself, and from June.l, 1917.

This stipulated amount was the sum of three of the items, together with some accrued interest, in plaintiff’s two causes of action. Defendant executed its voucher' therefor and took a receipt from plaintiff ás a release for such claims. All this was therefore, by virtue of sdch stipulation and by the portion of the amended answer quoted above, an admission [277]*277and not a denial of liability. It was a present liability and payable presently. Douglas v. Vorpahl, 167 Wis. 244, 166 N. W. 833. It could not be controlled as to time of payment by the provisions of the contract relied upon by the defendant, first, because it did not say so, and secondly, because it was an unqualified admission as to an obligation payable in money, while the provision in the contract relied upon provided for the payments to be partly in money and partly in stock of the corporation owner of the building, and it therefore took itself out from the contract.

We are satisfied also that the court below ruled correctly in allowing interest upon whatever sum is properly to be found as the amount of damages for the claim of delay.

While the earlier authorities in this court, which alone are relied upon by appellant, drew the line somewhat strictly as to the allowance of interest in such class of cases where recovery was sought for unliquidated damages, the rule has been extended in later years so as to permit, in cases involving a claim for. damages arising from breach of a contract and where the amount cannot be ascertained from the contract itself and requires the consideration of evidence before it can be assessed, a sum to be allowed equal to interest at the statutory rate from the time when the br'each occurred, rather as an additional penalty and to more nearly make the injured party whole for the use of the money which has been thus determined to have been withheld from him, than as interest in the ordinary acceptation of the term. Such has been the repeated holding, of this court. Gross v. Heckert, 120 Wis. 314, 330, 97 N. W. 952; Bagnall v. Milwaukee, 156 Wis. 642, 146 N. W. 791; Voigt v. Milwaukee Co. 158 Wis. 666, 149 N. W. 392; Peters v. Nat. S. Co. 167 Wis. 131, 163, 166 N. W. 43.

Under the third point presented by defendant, namely, that by the terms of the contract itself monetary damages for any delay were by implication excluded, it urges that under article XXIII, above quoted, giving the general con[278]*278tractor the right at any time to suspend the whole or any part of the work without compensation to the subcontractor other than extending the time for completing the work to an equal period, there was in effect such suspension of the work rather than a delay. That it was so considered by the plaintiff is urged by reason of negotiations between the parties at the end of March, pursuant to which plaintiff wrote a letter of confirmation to the effect that plaintiff was to take one of its pile-drivers out of this foundation entirely; it was then to begin driving with its other one and 'finish a certain portion of the area left outside the Birchard Block; then to proceed in another portion of the area where the excavator was then working, and that as soon as the Birchard Block was razed and the excavating completed, to proceed with the area covered by that block. It further recited that this arrangement is made on plaintiff’s part to help overcome the decided delays and .extensive expense that it had been subjected to on this site.

No reference, however, was made at any time by either of the parties to this being considered in any way the exercise of any right by the defendant under this particular clause. Neither was it apparently so considered at any time during the trial, nor were any requests made to the court to submit any question possibly arising under this particular clause to the jury, nor was it specified in the motions made by defendant for a nonsuit or directed verdict. There is not sufficient in this letter nor in the testimony to warrant the court on this appeal to how say fhat there was such an exercise of any power or right given to the defendant under this particular clause, or any such recognition by plaintiff of any such power, that the question of the liability of defendant for the delays in question can be now so determined.

Defendant further urges that by the provisions of article VIII,. considered in connection with the provisions in article VII for the payment of $100 for each day’s delay as liquidated damages, and the following undisputed facts, it [279]*279must be now held as a matter of law that the allowance of additional time for the completion by plaintiff of its part of-the work was the sole remedy for the delays:

’By a letter written February 11, 1916, when the plaintiff had been unable to start as yet with the pile-driving, although under the contract it was required to have finished the west half of the required area by the 31st of January, it refers to this clause for $100 per day and asks that the same be annulled.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kroger Ltd. Partnership I v. Cabinet for Health Services, Commonwealth
174 S.W.3d 516 (Court of Appeals of Kentucky, 2005)
Lily Penn Food Stores, Inc. v. Commonwealth
472 A.2d 715 (Commonwealth Court of Pennsylvania, 1984)
State v. Service Electric & Supply, Inc.
316 N.W.2d 390 (Wisconsin Supreme Court, 1982)
State v. Service Electric & Supply, Inc.
310 N.W.2d 626 (Court of Appeals of Wisconsin, 1981)
Continental Masonry Co. v. Verdel Construction Co.
369 A.2d 566 (Court of Appeals of Maryland, 1977)
Ryan v. Napier
252 F. Supp. 730 (N.D. Illinois, 1966)
Cunningham Brothers, Inc. v. City of Waterloo
117 N.W.2d 46 (Supreme Court of Iowa, 1962)
In Re Appeal of Roberts Construction Company
111 N.W.2d 767 (Nebraska Supreme Court, 1961)
Studer v. Rasmussen
344 P.2d 990 (Wyoming Supreme Court, 1959)
Necedah Manufacturing Corp. v. Juneau County
237 N.W. 277 (Wisconsin Supreme Court, 1932)
Spielberg v. Harris
232 N.W. 547 (Wisconsin Supreme Court, 1930)
Fritz v. Woldenberg
225 N.W. 700 (Wisconsin Supreme Court, 1929)
Trester v. Kahn
205 N.W. 826 (Wisconsin Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.W. 61, 170 Wis. 264, 1919 Wisc. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-e-gillen-co-v-john-h-parker-co-wis-1919.