L. W. Kinnear, Inc. v. City of Lincoln Park

244 N.W. 463, 260 Mich. 250, 1932 Mich. LEXIS 1110
CourtMichigan Supreme Court
DecidedOctober 3, 1932
DocketDocket No. 172, Calendar No. 36,249.
StatusPublished
Cited by6 cases

This text of 244 N.W. 463 (L. W. Kinnear, Inc. v. City of Lincoln Park) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. W. Kinnear, Inc. v. City of Lincoln Park, 244 N.W. 463, 260 Mich. 250, 1932 Mich. LEXIS 1110 (Mich. 1932).

Opinion

North, J.

In August, 1926, plaintiff, a Michigan corporation, entered into a contract with defendants for the construction of. 15,000 feet of lateral and trunk line sewer. Claiming performance of its contract, plaintiff brought this suit to recover a claimed unpaid balance on the contract price of $5,938.20; also to recover $9,854.74 which plaintiff claims is due it because defendant changed the method of operation in constructing the sewer from that contemplated when the contract was signed to a more expensive method of installation claimed to have been ordered by defendants’ engineer; and to recover the further sum of $2,114.58 for repairs which plaintiff claims it made to the sewer subsequent to its completion.

The defense urged is that plaintiff did not perform its contract and that it refused to- complete the sewer in accordance with the contract and specifications ; that its work was not performed in a thorough *252 and workmanlike manner and in accordance with, the plans and specifications. Defendants urge that, because of plaintiff’s failure to properly perform its contract, expenses were incurred in repairing, and replacing portions of the sewer incident to which $5,974.54 was expended. This was pleaded as a set-off, and affirmative judgment asked.

At the close of the proofs verdict for plaintiff was directed in the sum of $1,857, with costs to be taxed. In arriving at this result the circuit judge disallowed plaintiff’s claim of $9,854.74 for extra expenses of construction, and also disallowed the $2,114.58 for repairs, and deducted from the $5,938.20, which plaintiff claimed as the balance of the contract price, the amount the court found defendants had paid for repairs and to complete construction in accordance with the terms of the contract. This left a net balance, which, with accrued interest, totaled $1,857, for which verdict for plaintiff was directed. Plaintiff and the defendant city of Lincoln Park have appealed.

The city urges as a defense that it is not a party to the contract and is not bound thereby. The defendants Harvey B. Wallace and Henry Richardson were the owners of the subdivision in which the sewer was constructed. The written contract for the work was signed by them, but not by the city. However, the contract as drafted names the city of Lincoln Park and Wallace & Richardson as parties of the first part; and attached to the contract are specifications in which the city is referred to as the “first party.” The trial judge held that because the city had received the benefits of this sewer construction, and during the course of construction assumed and acted as though it were a party to the contract, as well as since the construction, that the city is estopped from denying liability.

*253 The city did not specifically deny by its plea or by its notice of special defenses that it was a party to the contract. On the contrary, in defendants ’ notice of special defenses, it is alleged:

‘ ‘ Said defendants will show * * * that on the 12th day of August, 1926, the said plaintiff entered into a certain written contract with said defendants, a copy of which is attached hereto.”

The bond accepted incident to the construction of this sewer ran to the city of Lincoln Park, as well as to the defendants Wallace & Richardson. Unquestionably Mr. Pate, who as engineer supervised and controlled this sewer construction, represented both the city and Wallace & Richards on;, and when the question arose of changing from segment block to the use of concrete pipe, Mr. Pate testified: “I told him (plaintiff’s president) I would take the matter up with the committee;” and that he did so. Even after plaintiff had discontinued work on this sewer and on August 1, 1927, the city council unanimously passed a resolution notifying plaintiff and its surety:

“To start work on the repairing and completion of sewers * * * covered by the contract in which the city of Lincoln Park and Wallace & Richardson are parties of the first part.”

The city owns the sewer constructed under this contract, it has used it, had it repaired and seems to have taken it fully under city control. Defendants’ witness, city engineer Pate, on direct examination, testified that the sewer here in suit “completed a sanitary trunk line system of Lincoln Park.” The city under its charter had power to contract for the construction of sewers, and even though this power was irregularly exercised it is nonetheless'obligated. The city’s contention that it *254 cannot be estopped from disavowing liability on the ground that the contract was not consummated in accordance with the charter provision is without merit.

“Where the power exists in a municipal corporation to bind itself, where the contract is intra vires, it will be bound even though it may have proceeded irregularly and in disregard of directory provisions as to the exercise of its power.” Commercial State Bank of Shepherd v. School District (syllabus), 225 Mich. 656.
“A municipality cannot retain the benefits of a contract which has been fully performed by the other party, and which is neither malum prohibitum nor malum in se, and at the same time deny the validity of the contract because of defects in the manner of its execution.” Coit v. City of Grand Rapids (syllabus), 115 Mich. 493.

See, also, Carey v. City of East Saginaw, 79 Mich. 73.

The circuit judge was right in holding that the city will not now be heard to disavow liability under the contract, or at least liability under the common counts in plaintiff’s declaration, if any such liability is established by the proofs in the case.

Before stating or considering the various grounds of plaintiff’s appeal, it will be helpful to note certain important provisions of the contract. Plaintiff agreed to furnish all the materials, tools, and labor necessary to complete on or before November 15, 1926, in every detail the construction of this sewer “to the satisfaction and acceptance of the party of the first part by its engineer, Edwin H. Pate, all according to plans and specifications.” The contract further provides:

“It is expressly understood and agreed that the entire work shall be done in a thorough, workman *255 like manner under the direction of the engineer. All loss or damage arising out of the nature of the work or any detention or other unforeseen obstruction or difficulties which may be encountered in the prosecution of the work or from any action of the elements shall be borne by the contractor. * * *
“Any unsatisfactory work that may be discovered before the work is finally completed and accepted shall be corrected by the second party. * * * Any inspection or passing by an inspector does not relieve the contractor from any obligation in this respect.
“No claim for extra work shall be allowed, made or entertained unless such work shall have been ordered in writing by the engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Diponio v. City of Garden City
30 N.W.2d 849 (Michigan Supreme Court, 1948)
City of Pontiac v. Ducharme
270 N.W. 754 (Michigan Supreme Court, 1936)
A. J. Smith Construction Co. v. City of Marine City
255 N.W. 209 (Michigan Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
244 N.W. 463, 260 Mich. 250, 1932 Mich. LEXIS 1110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-w-kinnear-inc-v-city-of-lincoln-park-mich-1932.