Brasher v. City of Alexandria

41 So. 2d 819, 215 La. 887, 1949 La. LEXIS 1005
CourtSupreme Court of Louisiana
DecidedFebruary 14, 1949
DocketNo. 38846.
StatusPublished
Cited by28 cases

This text of 41 So. 2d 819 (Brasher v. City of Alexandria) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brasher v. City of Alexandria, 41 So. 2d 819, 215 La. 887, 1949 La. LEXIS 1005 (La. 1949).

Opinions

McCALEB, Justice.

Brasher brought this suit to recover the sum of $16,659.43, representing the balance allegedly due for work done under a contract to construct a sewer system for the city of Alexandria. The facts upon which the claim is predicated are as follows:

On July 29, 1942, the parties entered into a written contract obligating Brasher to furnish “all material and labor and construction complete of an extension of the *891 municipal sanitary sewer system of the city of Alexandria, Louisiana, War Public Works Project Docket No. La. 16-116” for the sum of $161,641.23. Due to the fact that the project was sponsored by the Federal Works Agency, the agreement was of great length, comprising more than sixty pages, and contained provisions relative to the employment of labor which are not commonly found in ordinary construction contracts. The agreement also included other usual provisions, relative to time of completion and the obligations assumed by the contractor, coupled with the main obligation “ * * * to furnish all the materials, supplies, machinery, equipment, tools, superintendents, labor, insurance, and other accessories and services necessary to complete the said construction in accordance with the conditions and prices stated in the proposal attached hereto, and in accordance with all the General and Special Conditions of the Contract, and in accordance with the plans, which include all maps, plats, blue prints, and other drawings and printed or written explanatory matter thereof, and specifications and contract documents therefor as prepared by I. W. Sylvester, herein entitled the (Engineer), together with Contractor’s written proposal, the general and special conditions of the contract, the contract documents, construction regulations, and the Performance Bond, ■ * *

After the confection of the agreement, Brasher endeavored to perform the work under the supervision of the engineer of the city of Alexandria and various city inspectors. During the progress of the job, alterations in the original agreement were made which were necessitated by various conditions encountered by the contractor which were not foreseen by the parties at the time the contract was made. In all, there were 17 “change orders” executed in writing, aggregating a cost of $90,000, which increased the contract price to the sum of $216,239.

During the course of construction between stations 0 † 00 and station 39, the contractor was confronted with a serious soil condition necessitating, in his opinion, the use of extra materials as a cradle to stabilize the pipes to be laid in the trench. Inasmuch as the plans and specifications did not provide for the cradling of the sewer pipes, the contractor requested the Acting City Engineer 1 for a change order so that stabilization of the pipes could be had, recommending that concrete cradles be employed. The Engineer and the Commissioner of Streets and Parks took the position that the furnishing of concrete cradles, or, for that matter, any other material for stabilization of the sewer pipes, was an obligation of the contractor and that the city would not be responsible therefor. In view of the attitude of the city’s officers, the con *893 tractor laid the pipes in the trench as provided for in the specifications, using wooden boards as a stabilizer. These boards were not an adequate brace for the load sustained by the pipes and, as a result, some 78 pipes on this particular section of the sewer line collapsed. The city thereafter employed another contractor to make the proper repairs between stations 0 † 00 and station 39 at a cost of $13,588.45 and, when Brasher presented his estimate, it deducted that sum from its final payment on the ground that he had failed to fully comply with his agreement.

It further appears that, after the sewer extension had been laid between station 39 † 35 and station 41 † 05 on Wise Street, it failed because of similar soil conditions and resultant lack of stabilization of pipes in the trench to that occurring in the section of the work above mentioned, that is, between stations 0 † 00 and station 39. Upon discovery, the contractor applied to the Acting City Engineer for a written order to correct the condition but the latter refused on the ground that it was the contractor’s obligation to stabilize the pipe. Despite the refusal of the City Engineer, the contractor made the necessary repairs at the insistence of the government engineer, who urged him -to do so in order that a Negro housing project, which had been erected by the federal government, could be connected to the sewer line. In fact, the evidence shows that the government engineer assured plaintiff that he would see that he was paid under the “force work” provision of the contract. However, the city has never paid the amount of this extra work which is shown to be the sum of $3060.98.

Thus, plaintiff’s claim is comprised of two items, $13,588.45, which he contends was wrongfully deducted-by the city from the balance due on the contract, and $3060.-98, for the extra work in repairing the Wise Street sewer extension. The basis of the cause of action in each instance is that the extra cradling work required for the stabilization of the sewer pipes was' due to defective plans and specifications prepared by the City Engineer and that, this being so, he is entitled to recover as he has fully complied with his obligation. ■

The city, on the other hand, contends in the main that the repairs to the sewer system were necessitated by the contractor’s failure to perform in accordance with the conditions of the contract which required him to examine the site and acquaint himself with the general conditions under which the work was to be done and, thus, made it his obligation to overcome any difficulties encountered resulting from soil conditions or otherwise to the end that he deliver a complete sewer system free from defects.

After a protracted trial in the lower court in which a mass of evidence was adduced, there was judgment in plaintiff’s favor, as prayed for. The city prosecuted this appeal.

*895 In this court, the city reurges the contention that it is not responsible because the repairs rendered necessary as a result of the soft soil rested upon plaintiff and not upon it. 2 It also complains about certain conclusions of fact of the trial judge which we find unnecessary to discuss as the record leaves no doubt that the defects in the sewer system were due to soil conditions which made it imperative that the sewer pipes be stabilized by concrete cradling. Hence, the narrow question for decision is whether the obligation rested on plaintiff or upon the city to provide the cradling.

The City Attorney relies upon the general rule that a contractor will not be excused from his obligation by reason of unforeseen difficulties encountered in the work. In support of his argument, he directs attention to various general provisions of the contract, making it the duty of the contractor to examine tíre site where the work is to be performed, check the plans and specifications, etc., and the cases of O’Leary v. Board of Port Com’rs for Port of New Orleans, 150 La. 649, 91 So. 139; Picard Const. Co. v. Board of Com’rs, 161 La. 1002, 109 So. 816 and Terrill Const. Co. v. Town of Pineville, 168 La. 894, 123 So.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Semco, LLC v. Grand Ltd.
221 So. 3d 1004 (Louisiana Court of Appeal, 2017)
Frey v. Amoco Production Co.
603 So. 2d 166 (Supreme Court of Louisiana, 1992)
Hanna-Abington Alexandria, Inc. v. BUDD CONST. CO., INC.
487 So. 2d 743 (Louisiana Court of Appeal, 1986)
Shell Oil Co. v. Williams, Inc.
428 So. 2d 798 (Supreme Court of Louisiana, 1983)
Wetmore v. Blueridge, Inc.
391 So. 2d 951 (Louisiana Court of Appeal, 1980)
Charles Carter & Co. v. Dixie Electric Membership Corp.
380 So. 2d 632 (Louisiana Court of Appeal, 1979)
Orleans Parish Sch. Bd. v. Pittman Const. Co., Inc.
372 So. 2d 717 (Louisiana Court of Appeal, 1979)
Lewis v. Anchorage Asphalt Paving Co.
535 P.2d 1188 (Alaska Supreme Court, 1975)
Peak v. Cantey
302 So. 2d 335 (Louisiana Court of Appeal, 1974)
McGowan-Rigsby Sup., Inc. v. CHARLES CARTER & CO. INC.
268 So. 2d 716 (Louisiana Court of Appeal, 1972)
Charbonnet v. Ochsner
236 So. 2d 86 (Louisiana Court of Appeal, 1970)
Baton Rouge Contracting Co. v. West Hatchie Drainage District
304 F. Supp. 580 (N.D. Mississippi, 1969)
Wurst v. Pruyn
202 So. 2d 268 (Supreme Court of Louisiana, 1967)
Murphy Corporation v. Petrochem Maintenance, Inc.
180 So. 2d 716 (Louisiana Court of Appeal, 1965)
Pittman Const. Co. v. Housing Auth. of New Orleans
169 So. 2d 122 (Louisiana Court of Appeal, 1965)
Pittman Construction Co. v. Board of Levee Commissioners
169 So. 2d 192 (Louisiana Court of Appeal, 1964)
Cox v. East Baton Rouge Parish School Board
165 So. 2d 667 (Louisiana Court of Appeal, 1964)
Dinon Terrazzo & Tile Co. v. Tom Williams Construction Co.
162 So. 2d 795 (Louisiana Court of Appeal, 1964)
Pontchartrain Park Homes, Inc. v. Sewerage & Water Board
159 So. 2d 774 (Louisiana Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
41 So. 2d 819, 215 La. 887, 1949 La. LEXIS 1005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brasher-v-city-of-alexandria-la-1949.