Terrill Const. Co. v. Town of Pineville

123 So. 611, 168 La. 894, 1929 La. LEXIS 1891
CourtSupreme Court of Louisiana
DecidedJune 17, 1929
DocketNo. 29846.
StatusPublished
Cited by5 cases

This text of 123 So. 611 (Terrill Const. Co. v. Town of Pineville) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terrill Const. Co. v. Town of Pineville, 123 So. 611, 168 La. 894, 1929 La. LEXIS 1891 (La. 1929).

Opinion

LAND, J.

This is a suit for the alleged breach by the town of Pineville of a certain contract for the construction of a sewer system, entered into between the town authorities and the Terrill Construction Company, the plaintiff.

The breach alleged on the part of the town was its failure to obligate itself in advance to pay for certain sheath piling which plaintiff company thought proper to use in making excavations in Melrose street.

This breach is alleged to have occurred when two-sevenths of the work was as yet incomplete, and plaintiff brings this suit to recover the retained percentage held by the town under the contract, and for anticipated profits on the balance of the work.

Plaintiff company prosecutes this appeal from a judgment maintaining defendant’s exception of no cause or right of action, and dismissing its suit.

1. At the outset it is necessary to dispose of the objection of defendant to the form of action brought by plaintiff.

Plaintiff company’s suit is predicated upon a state of facts alleged in its petition and from which it deduces an active breach by defendant of the contract for which it claims damages. Plaintiff’s action is clearly brought under articles 1930, 1931, 1932, and 1934 of the Civil Code, relating to damages resulting from the inexecution of obligations.

Defendant contends that Act No. 224 of 1918, relating to contracts for public works, prescribes an exclusive remedy and one that must be followed by plaintiff company, as contractor in the present case.

Section 4 of this act provides: “That if, at. the expiration of said forty-five days (from the default of the contractor or the acceptance of the worlc) there are recorded claims filed with the said authorities and recorded in the mortgage office unpaid, the said au *897 ■thorities shall' file a petition in the proper court where the work was clone citing such claimants and tho contractor, subcontractor and surety on the bond, anil the said authorities shall assert whatever claims they have against any and all of them in said petition, and require the said claimants to assert whatever claims they have against any and all of them, and all of said claims shall be tried in coneursus.”

This act, by its plain provisions, contemplates recorded claims of furnishers of labor and material, and either an admitted default of the contractor or an acceptance of the work.

Not one of these prerequisites is present in this case. The petition alleges no recorded claims, no acceptance of the work, and admits no default on the part of the contractor. On the contrary, it is alleged by plaintiff: that defendant itself is in default, having breached its contract. If the only remedy plaintiff, as contractor, had under these circumstances was to wait until defendant (the town authorities) took the initial step by filing a petition under Act No. 224 of 1918, admitting its breach of contract and provoking a concur - sus, the result might be that plaintiff would be without remedy or redress at all in the present case, as the defendant, in our opinion, ■would not have filed such a petition in any event. The contention of defendant is therefore without merit.

2. It appears from the allegations of the petition that the Terrill Construction Company on March 21, 192S, entered into a written contract with the town of Pineville to build and construct a sewerage system, and that, after completing only five-sevenths of the work contemplated, plaintiff company stopped work on December 14, 1928. At that date it is estimated that 1,200 feet of the sewer line were left incomplete on Melrose street, and that 20,800 feet of the line remained to he completed exclusive of this street.

The sewer pipe was to be laid in trenches excavated by the contractor, the Terrill Construction Company. In order to lay the pipe along Melrose street according to the plans and specifications, it was necessary to excavate the trench to a depth of from 17 to 34 feet. In beginning the excavation on that street, the contractor encountered running sand or quicksand. In attempting to proceed properly according to the terms of the contract, the contractor found that it would be very expensive for him to excavate the trench for the laying of the sewer pipe line on Mel-rose street, in that it would be necessary for him to brace the walls with four-inch instead of two-inch sheathing. Plaintiff alleges that the difference in the contract price ranged from- $13,500 to $22,500, amounts in excess of the avails of the special issue of bonds sold by the town of Pineville for the construction of its sewerage system.

In our opinion, plaintiff’s whole cause of action is predicated upon the following erroneous construction of its contract:

First. That plaintiff, as contractor, is not primarily bound to properly support the trenches, as they are excavated, with temporary sheathing of such thickness as the engineers for the town of Pineville may require.

Second. That the cost of all sheathing in excess of two inches in thickness must be borne by the town of Pineville, when used temporarily in excavations.

Third. That the engineers of the town having ordered plaintiff in advance to use four-inch -sheathing in the excavations on Melrose street, the town authorities actively violated the contract with plaintiff by setting aside this order.

Fourth. That the town, having finally ordered plaintiff to proceed with the excavation *900 on Melrose street with two-inch sheathing, made th.e contract impossible of performance as well as dangerous in execution, in that the walls of the excavation would cave and imperil the lives and limbs of plaintiff’s workmen, and would break the gas main of the Southern Gas Company, located on Melrose street, with resulting danger to the lives and property of the entire town.

The contract between plaintiff and defendant is annexed to and made a part of the petition in this case. It is stated in this contract that: “He (the cpntraetor) declares that he has examined the site of the work and informed himself fully in regard to all the conditions pertaining to the place where the work is to be done; and that he has examined the form of the contract and of bond set forth in the specifications, the specifications and the drawings therein referred to, and has read the Instructions to Bidders referring to the work, and has satisfied himself as to all matters relating to the work to be performed.’’

Plaintiff is therefore presumed to have known the depth of the excavations on Mel-rose street, the fact that the gas main of the Southern Gas Company was located on that street, and in close proximity to the sewer line to be excavated.

In other words, the Terrill Construction Company is presumed to have been acquainted with the dangerous character of the work undertaken by it under its contract with defendant.

Plaintiff company alleges the possibility of the performance of the contract with four-inch sheathing as support to the walls of the excavation.

In Picard Construction Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kewaunee Scientific Corp. v. RAGUSA & SON
723 So. 2d 470 (Louisiana Court of Appeal, 1998)
George A. Fuller Company v. Coastal Plains, Inc.
290 F. Supp. 911 (E.D. Louisiana, 1968)
Pittman Construction Co. v. City of New Orleans
178 So. 2d 312 (Louisiana Court of Appeal, 1965)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
123 So. 611, 168 La. 894, 1929 La. LEXIS 1891, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terrill-const-co-v-town-of-pineville-la-1929.