Picard Const. Co. v. Board of Com'rs

109 So. 816, 161 La. 1002, 1926 La. LEXIS 2169
Supreme Court of Louisiana·Decided May 31, 1926·No. No. 27287.·Published·Cited by 28 cases

Opinion

ST. PAUL, J.

This case comes before us on appeal from a judgment against plaintiff on the merits; the defendant has answered the appeal, praying that its exception of no 'cause of action be sustained.

. As we think the exception is well taken, and as in fact the supplemental petition and the trial on the merits has simply amplified the allegations of the main petition, adding thereto nothing new on which a judgment for plaintiff could be based, we will dispose of the case on that exception.

I.

Plaintiff alleges that it entered into a certain (amended) contract 'to do certain excavating work for defendant, and thereupon alleges the following:

“(10) That during the work of excavating under the said contract so amended the contractor encountered a peculiarly hard formation. * * *
“(11) That attention was not called, either in the advertisement or in the information furnished to the contractor, to the presence, or the probable presence, of such unusually hard subsoil formation along the route of the jn-oject advertised and contracted for. * * *
“(12) That neither the original reconnaissance nor the subsequent surveys revealed the presence of the hard bottom which was later encountered when the work of dredging was actually commenced; and that up to such time the presence of such unusually hard formation was never hnown, foreseen, or suspected by any one, whether engineers, members of the defendant board, contractors or any one else whomsoever. (Italics ours.)
“(13) That such unusually hard subsurface formation had never been encountered in any drainage work in this section of the state, and no reason existed for suspecting .its existence; that the reconnaissance and survey did not indicate, nor would anything done in the exercise of reasonable diligence of prudence have revealed, the presence of such formation.”
“(19) That such unexpected, unforeseen, and unusual hard subsoil formation rendered it much more expensive to the contractor to carry out the work; and caused gréat and unusual outlays, not due to the fault of the contractor, in order to carry out the work; but that, despite all such additional cost, expense, delays, and unusual difficulties, the work * * * has now been finally completed to the satisfaction of the state engineer in charge. * * *
“(20) That the original contract -and the extensions thereof were entered into upon the part of the contractor and defendant under and through a material error of fact as to the sub~ stance of the thing which was the object of the contract, such error being mutual on the part of the contractor and of said board; and the contractor would not have entered into said con *1005 tract for the price therein set out but for such material error, resulting from the fact that all parties supposed that they were dealing with conditions and formations usually encountered in such drainage work; none of the parties being called upon to foresee or to suspect the presence of the unusually hard subsurface formation hereinabove referred to, and which rendered the work to be accomplished by the contractor of a totally different nature from that which was intended. (Italics ours.)
“(21) That, upon first ascertaining the existence of said unusually hard formation, the contractor notified the board thereof and that he would claim additional compensation by reason thereof. (Italics ours.)
“(22) That at the request of the board thfe contractor continued with the execution of the work called for by the contract and its extensions, upon the promise and agreement and representation of the said board that all matters relating to the error in question would be adjusted when the work should have been accomplished; and that throughout the performance of the original contract your petitioners have insisted upon their right to such additional compensation, and have proceeded with the execution of the work under the understanding with said board that all matters relating to such additional compensation would be adjusted upon final completion of the work. (Italics ours.)”

Wherefore the petitioners claim additional compensation, beyond the contract price, in a sum sufficient to make them whole for their total outlay, plus a reasonable profit.

Such is the petition which defendants contend, and which, we hold, shows no cause of action.

II.

We may therefore sum up the matter in substance as follows: Plaintiffs undertook to do' a certain work for defendant; they encountered certain difficulties unknown and unsuspected by either party; they notified defendant at once of the existence of such difficulties, and of their intention to claim additional compensation on that account; they were told by defendant to proceed with the work notwithstanding such difficulties, and that the matter of additional compensation would be. adjusted upon final completion of the work; they did complete the work, and now claim said additional compensation, which defendant refuses to pay.

Incidentally, it will be observed that it is not charged that defendant made any misrepresentations or withheld any information which it had as^ to the character of the work to be done. On the contrary, it is alleged affirmatively that defendant had no mor.e knowledge on that- subject than had plaintiffs, and could no more have foreseen the difficulties to be encountered than could plaintiffs themselves.

III.

Pretermitting for the moment the question whether the allegations set forth in the petition show such a material error of fact as will annul the contract for want of consent on the part of plaintiffs, the question then arises whether plaintiffs can take anything by the (virtual) promise of the defendant to pay them the additional compensation which they notified defendant they would claim.

This, of course, begs the question whether plaintiffs were bound to complete the contract without any right to claim extra compensation because of the unforeseen difficulties which they encountered. If they were not, then the promise made by defendant was not gratuitous, but based upon sufficient.consideration. If they were, then the promise was purely gratuitous, and based upon no consideration whatever.

Again pretermitting the question whether or not even an individual can be bound by a purely gratuitous (executory) promise to give or to do something, the fact remains that public bodies cannot so bind themselves. For, without going in search of authorities generally so holding (whose name is legion), it suffices in this state to point to the constitutional inhibition on the subject:

“The Legislature shall have no power to grant, or authorize any parish or municipal authority to grant any extra compensation, fee or -allowance to a public officer; agent, servant, or

Free access — add to your briefcase to read the full text and ask questions with AI

Picard Const. Co. v. Board of Com'rs, 109 So. 816, 161 La. 1002, 1926 La. LEXIS 2169 (La. 1926).

109 So. 816 (Picard Const. Co. v. Board of Com'rs) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Payne v. Hurwitz
978 So. 2d 1000 (Louisiana Court of Appeal, 2008)
Associated Acquisitions, L.L.C. v. Carbone Properties of Audubon, L.L.C.
962 So. 2d 1102 (Louisiana Court of Appeal, 2007)
Associated Acquisitions v. CARBONE PROP.
962 So. 2d 1102 (Louisiana Court of Appeal, 2007)
Opinion Number
Louisiana Attorney General Reports, 2003
State v. Davis
539 So. 2d 803 (Louisiana Court of Appeal, 1989)
Shell Oil Co. v. Williams, Inc.
428 So. 2d 798 (Supreme Court of Louisiana, 1983)
McElveen v. Callahan
309 So. 2d 379 (Louisiana Court of Appeal, 1975)
Admiral Paint Company v. Goltzman
254 So. 2d 104 (Louisiana Court of Appeal, 1972)
Pittman Construction Co. v. City of New Orleans
178 So. 2d 312 (Louisiana Court of Appeal, 1965)
Bumby & Stimpson, Inc. v. Peninsula Utilities Corp.
169 So. 2d 499 (District Court of Appeal of Florida, 1964)
Texas Co. v. McDonald
82 So. 2d 37 (Supreme Court of Louisiana, 1955)
Stanley v. Pereira
73 So. 2d 337 (Louisiana Court of Appeal, 1954)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Burk v. Livingston Parish Police Jury
21 So. 2d 719 (Supreme Court of Louisiana, 1945)
Bourne v. Southern Railway Co.
31 S.E.2d 382 (Supreme Court of North Carolina, 1944)
Bell v. Leiendecker
170 So. 386 (Louisiana Court of Appeal, 1936)
Jung v. Gwin
147 So. 47 (Supreme Court of Louisiana, 1933)
P. Olivier Son v. Board of Com'rs
148 So. 12 (Supreme Court of Louisiana, 1933)
Sumerall v. Wetherbee
130 So. 875 (Louisiana Court of Appeal, 1930)