Pittman Construction Co. v. Board of Levee Commissioners

169 So. 2d 192, 1964 La. App. LEXIS 2063, 1965 A.M.C. 526
CourtLouisiana Court of Appeal
DecidedNovember 2, 1964
DocketNo. 1554
StatusPublished
Cited by3 cases

This text of 169 So. 2d 192 (Pittman Construction Co. v. Board of Levee Commissioners) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittman Construction Co. v. Board of Levee Commissioners, 169 So. 2d 192, 1964 La. App. LEXIS 2063, 1965 A.M.C. 526 (La. Ct. App. 1964).

Opinion

YARRUT, Judge.

Plaintiff appeals from a judgment of the District Court denying it recovery of $59,-725.25, interest and costs, for extra work alleged to have been caused by inadequate plans and specifications furnished by Defendant, for whom Plaintiff contracted to do the work. Plaintiff will be referred to herein as “Contractor”, and Defendant as “Levee Board”.

The contract was for the construction of a Marina on the lake front in the City of New Orleans, which involved the driving of 1800 underwater piles, 611 of which were driven beyond the 3-inch tolerance allowed by the contract and had to be “jetted” so that they could be realigned. The Contractor claims $97.75 for each of the 611 piles jetted for this purpose. “Jetting” of piling is described as the using of a hose pipe with water under force to drive the sand away from the piling. When this operation is done concurrently with the driving of the piling to penetrate the sand strata, it is called pre-jetting. When it is done to loosen the sand in order to realign the piling, this is called post-jetting.

[193]*193The Levee Board contends the “jetting” was due to the incompetency and negligence of the Contractor’s piling subcontractor; that the pre-soil borings of experts was sufficient to forewarn the Contractor of the subsoil conditions, none of which were unknown, and that no written approval for the correction or “jetting” of the 611 piles, or agreement to pay extra therefor, was given by the Levee Board.

There were three bidders for the contract. Plaintiff-Contractor was $56,000.00 lower than the second, and $182,388.00 lower than the third bidder.

The ultimate decision here must rest upon the terms of the contract and the applicable statutes and jurisprudence.

In its letter to the Levee Board accompanying its bid, Contractor stipulated that, having carefully examined the original and Supplemental General Conditions of the contract; the specifications (sections 1 through 29) and drawings (1 through 34), dated July 24, 1961, titled “Marina for Orleans Levee Board” prepared by Favrot and Grimball, Architects; and having visited the site and informed itself of all conditions affecting the work, it proposed to furnish all labor and materials called for in strict conformity therewith for the prices set out in detail in its bid.

With regard to the Change Orders, Contractor agreed that, if awarded the contract, and should extra work or credits for omissions be authorized, in writing only, by the Levee Board, the amount to be charged or credited therefor would be the same as the basic labor and material of the subcontractor’s proposal, or the actual cost to the Contractor, with applicable insurance, taxes, social security payments and bond, plus 15% for General Contractor’s profit and overhead.

The detailed specifications provide (Article 15) that:

“Should conditions encountered below the surface of the ground be at variance with the conditions indicated by the drawings and specifications the contract sum shall be equitably adjusted upon claim by either party made within a reasonable time after the first observance of the conditions.”

The subsoil conditions were set forth in a report made part of the contract by the Eustis Soil Boring Corporation. There is no evidence that they were at variance with those conditions actually encountered on the job.

The Piling Specifications provide:

“10. Jetting: No jetting is anticipated to obtain the desired penetration; however, in the event that it becomes essential, the contractor shall notify the Architect accordingly in writing and a change order for such work will be negotiated as indicated.”
“Any piling driven beyond a three inch tolerance shall be sufficient cause for driving additional pilings, all cost of which shall be borne by the contractor.” (Piling Specifications Exhibit “4”)

Two facts are undisputed: (1) The Contractor did not jet the 611 pilings in question while he was driving them in order to penetrate the sand strata; rather, he post-jetted them so that he could realign them within the three-inch tolerance allowed; (2) no written change order to post-jet the pilings was ever obtained by the Contractor from the Levee Board.

Plaintiff relies on the following provision in the bid proposal (page 6) : [194]*194Plaintiff argues that it can recover under this provision because it refers to the post-jetting, which it did, not the pre-jetting, which it didn’t do. He maintains that he did jet the piling and did wash the sand away from the piling in order to realign the piling and in doing so penetrated the sand strata. However, it would seem that the words “jetting of piling through sand strata” means driving piling through the sand strata and refers to pre-jetting, an interpretation in which George P. Rice, Plaintiff’s expert witness concurred.

[193]*193“In the event jetting of piling through sand strata is required as directed by the architect:
“Per piling driven on land:
“Add: Eighty-one dollars and fifty cents ($81.50)
“Per piling driven over water:
“Add: Ninety-seven dollars and seventy-five cents ($97.75)”

[194]*194Arnold Wolfe, a plaintiff witness, admitted he never encountered a sand strata that he had to pre-jet through; that he was exclusive and sole subcontractor for the pile-driving work, although the contract was taken in his brother’s name; most of the “jetting” was done after the pilings were driven to straighten them out, all by post-jetting; and that he did not know if the change order was secured after the pilings were driven and before post-jetting; that ten piles jetted were not covered by the Levee Board contract; that he made a mistake as pre-jetting was not required in the contract specifications, only in his own subcontract with Pittman; that he never read the subsoil investigation report of Eustis Engineering Company before starting the work, nor did he review the soil boring data available, even though soil boring is set forth in the Plans and Specifications; that his neglect was because the subcontract with Contractor was in his brother’s name and confected by his brother with the Contractor; that, normally, he examines soil borings before taking jobs, but had not done so in this case.

Gerald Gallinghouse, President of the Levee Board, testified there was no disagreement about the piling job being out of alignment, nor any disagreement that the Levee Board would not accept the pilings as driven; nor was there any question or suggestion that it was necessary to “jet” the piling in order to get through the sand strata.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CITY OF NEW ORLEANS, ETC. v. Vicon, Inc.
529 F. Supp. 1234 (E.D. Louisiana, 1982)
Pittman Construction Co. v. City of New Orleans
178 So. 2d 312 (Louisiana Court of Appeal, 1965)
Pittman Construction Co. v. Board of Levee Commissioners
170 So. 2d 865 (Supreme Court of Louisiana, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
169 So. 2d 192, 1964 La. App. LEXIS 2063, 1965 A.M.C. 526, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittman-construction-co-v-board-of-levee-commissioners-lactapp-1964.