CITY OF NEW ORLEANS, ETC. v. Vicon, Inc.

529 F. Supp. 1234, 1982 U.S. Dist. LEXIS 18260
CourtDistrict Court, E.D. Louisiana
DecidedJanuary 4, 1982
DocketCiv. A. 79-4878, 79-4987, 80-281 and 80-3409
StatusPublished
Cited by1 cases

This text of 529 F. Supp. 1234 (CITY OF NEW ORLEANS, ETC. v. Vicon, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CITY OF NEW ORLEANS, ETC. v. Vicon, Inc., 529 F. Supp. 1234, 1982 U.S. Dist. LEXIS 18260 (E.D. La. 1982).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

BEER, District Judge.

To the extent that the following findings of fact contain conclusions of law, or the conclusions of law contain findings of fact, they are so adopted.

Findings of Fact

1. These suits involve claims brought by the City of New Orleans acting through New Orleans Aviation Board (“NOAB”). Basically, the claims relate to certain asphalt overlay projects performed at separate but closely related times on the North-South and East-West runways at New Orleans International Airport. The North-South project began in 1976 and continued through September, 1977. The East-West project began in late 1977 and continued into November, 1978.

2. NOAB initially sued Vicon, Inc. (“Vi-con”), the contractor on both projects, and its surety, Reliance Insurance Company (“Reliance”), in state court. Those proceedings were removed to this court in December, 1979, and January, 1980.

3. Thomas B. Catchings and Associates, succeeded by Laurence L. Lambert and Associates, and, thereafter, succeeded by Laurence L. Lambert, C. E. (“Lambert”), were the engineering firms successively (and con *1231 tinuously) engaged to perform services as project engineer on both projects.

4. Delta Testing and Inspection, Inc. (“Delta”) designed the so-called “job mix” with respect to the asphalt and was generally responsible for performing various testing services and functions on both projects.

5. Southland Oil Company, Inc. (“South-land”) supplied the liquid asphalt used by Yicon in the preparation of the asphalt mix on both projects.

6. During the course of this litigation, various insurers were added as defendants. These include Northbrook Insurance Company (“Northbrook”), the insurer of Lambert, Independent Laboratories Assurance Company, Ltd. (“Independent”), the insurer of Delta, and Fidelity & Casualty of New York (“Fidelity”), the insurer of Southland.

7. The Federal Aviation Administration (“FAA”), which provided grant funds to finance portions of each runway project pursuant to the Airport and Airway Development Act of 1970, 49 U.S.C. § 1701, et seq., was sued as a third party defendant by the original defendants.

8. In September, 1976, the City advertised for bids for the restoration of the pavement on the North-South runway. In conjunction with this action, Lambert was retained as the engineer on the project under a contract between Lambert and the NOAB. Detailed plans and specifications were prepared by the engineer consistent with current FAA specifications. These were then made available to bidders and ultimately became part of the construction contract. Vicon was the successful bidder for a proposed price of $1,601,024.13 based in part on estimates of the quantities of asphalt materials to be supplied. The contract between Vicon and NOAB was executed October 22, 1976. Delta was appointed the testing laboratory for the project under the provisions of a separate contractual agreement with NOAB.

9. In September, 1977, NOAB accepted bids for the restoration of the pavement on the East-West runway. In conjunction with this action, Lambert was retained as the engineer on the project under a contract between Lambert and NOAB. Detailed plans and specifications were prepared by the engineer consistent with current FAA specifications. These were then made available to bidders and ultimately became part of the construction contract. Vicon was the successful bidder for a proposed price of $3,378,545.89 based in part on estimates of the quantities of asphalt materials to be supplied. The contract between Vicon and NOAB was executed September 13, 1977. Delta was appointed the testing laboratory for the project under the provisions of a separate contractual agreement with NOAB.

10. Reliance provided performance and payment bonds in behalf of Vicon on the North-South and East-West runway projects. Those bonds were executed as integral parts of the contracts and were at risk in the amounts provided for in the contracts.

11. On the North-South runway job, the plans and specifications called for the placement of an asphalt base course, an asphalt wearing course and a covering porous friction course. On the East-West runway, a base course and wearing course were specified. On both jobs, the liquid asphalt that was specified was furnished by Southland.

12. Premature failures occurred on both the North-South and East-West runways which rendered the runways unfit to provide the service required under applicable safety regulations and considerations. The failure on each runway became apparent shortly after the acceptance of the jobs. Although failures occurred on both the runways, the mechanisms by which the runways failed were, in some ways, different. Failures occurred primarily in the wearing courses — or P — 401 layer — of each runway.

13. The porous friction course (“pfc”) was the top layer of asphalt mixture placed by Vicon on the North-South runway. It was designed to provide traction for takeoffs and landings and to facilitate the runoff of rainfall. Immediately after the completion of the North-South runway job, problems developed in the pfc. When air *1232 planes landed on the runway, aggregate in the pfc would be dislodged by the airplane wheels and created a dangerous condition to jet aircraft. This failure of the aggregate to remain part of the pavement could be described as “ravelling,” a situation in which, the aggregate becomes separated from the asphalt. This loose aggregate on the runway created a hazard because the loose material could be ingested into a jet engine. In an attempt to correct this problem, an emulsion was laid on a portion of the runway in October, 1977. The problem of aggregate pick-up subsided sometime after the emulsion was placed on the pfc, although the lessening of the problem was due, in part, to the onset of cooler weather.

14. The North-South runway developed further problems in the summer of 1978. When aircraft took off from the runway, the blasts of jet engines were responsible for blowing quantities of asphalt out of the runway, leaving potholes several inches deep. These holes began to appear in July, 1978, and their appearance increased in frequency thereafter. In addition, depressions began to appear in the pfc, evidencing a lack of cohesion in the asphalt mixture below the surface. It was discovered that sections of the wearing course (below the pfc) had deteriorated to the point where the consistency of the wearing course was that of loose aggregate held down only because of the presence of the porous friction course.

15. The material below the pfc was wet or damp, and it was essentially confirmed that “stripping,” a process in which the asphalt is stripped from the aggregate in the presence of water, had occurred. The NOAB was required, thereupon, to institute daily inspection and repair operations because of the frequent appearance of depressions and potholes on the runway.

16. Very soon after the East-West runway was completed and accepted, “ravelling” began to occur on that runway. Loose rocks broke apart from the asphalt pavement in the trafficked areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loney v. MHA v. Aetna
D. New Hampshire, 1995

Cite This Page — Counsel Stack

Bluebook (online)
529 F. Supp. 1234, 1982 U.S. Dist. LEXIS 18260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-orleans-etc-v-vicon-inc-laed-1982.