Keating v. Miller
This text of 292 So. 2d 759 (Keating v. Miller) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
E. Roland KEATING
v.
Alton J. MILLER.
Court of Appeal of Louisiana, Fourth Circuit.
*760 Daniel E. Becnel, Jr., Reserve, for defendant-appellant.
Alfred Abramson, LaPlace, for plaintiff-appellee.
Before GULOTTA, STOULIG and SCHOTT, JJ.
GULOTTA, Judge.
This is a suit by plaintiff contractor for the balance owed (less credits) on a building contract. The owner seeks, in reconvention, additional costs to complete the construction required because of plaintiff's alleged defective workmanship. From a judgment in favor of plaintiff, defendant appeals. In answer to the appeal, plaintiff seeks attorney fees and the assessment of costs and expert fees against defendant. We reverse and remand.
The facts are that the contractor gave a written estimate to defendant on January 8, 1972 for the construction of a residence consisting of 1,700 square feet for the price of $19,000. Charge orders brought the price to $19,300. A building contract was entered into on January 10. No square footage was mentioned in the contract; however, references were made to plans and specifications. Plans were not attached to the contract. Subsequent agreed upon plans specified 1,850 square feet.
The initial dispute arose when defendant discovered that the slab for his house was two feet shorter than specified in the plans. Construction work continued on the house but was subsequently terminated upon demand of owner when a substantial part of a veneer brick wall fell. Defendant wanted the brick work completely replaced while the plaintiff wanted to repair only those parts of the work which plaintiff claimed were defective. Herein lies the primary dispute. When agreement could not be reached on the extent of the brick replacement, defendant terminated the contract and completed the work. *761 Plaintiff then filed a lien, and this suit followed.[1]
Defendant, in seeking reversal, claims plaintiff breached the contract by constructing the house with less square footage than specified in the plans and by placing such defective masonry on the building as to require complete replacement. The owner urges further that the court erred in concluding that there was substantial performance by the contractor resulting in an award in plaintiff's favor based on this performance. Defendant lastly urges the trial judge erred in not permitting the use of depositions to impeach plaintiff's testimony.
Plaintiff, on the other hand, argues that there was an agreement for the construction of a house containing 1,700 square feet for the contract price of $19,000. While the plans call for a greater amount of square footage, according to plaintiff, there was never any agreement to construct a building containing in excess of 1,700 square feet for the agreed price. Nevertheless, plaintiff insists defendant received a house containing 1,780 square feet. Furthermore, plaintiff argues the plans cannot be controlling because extensive changes were made in variation from the plans. While acknowledging that part of the brick work was defective, plaintiff disputes the necessity for the entire replacement of the bricks. Plaintiff seeks attorney fees, costs and expert witness fees to which he claims he is entitled under the contract.
We are confronted with two questions primarily. The first is whether or not plaintiff has breached the contract by reducing the length of the building by two feet; and if so, has there been a waiver by the defendant. And, secondly, whether the masonry work was so defective as to necessitate its complete replacement justifying the termination of the contract by defendant.
The contract reads "see plans and specs" and did not specify the number of square feet. However, the plans call for 1,850 square feet, according to plaintiff. When plaintiff reduced the square footage from 1,850 square feet to 1,780 square feet by reducing the length of the slab by two feet without prior assent of the defendant, he breached the contract. It is clear, however, that defendant waived the breach by permitting plaintiff to continue construction after he became aware of the reduced footage. Under the circumstances, defendant cannot rely on the breach as justification for terminating the contract and completing the construction.
However, the defective brick work constituted justification for termination and completion by defendant under the terms of the contract.
Article 23 of the contract provides:
"The Contractor shall correct any Work that fails to conform to the requirements of the Contract Documents where such failure to conform appears during the progress of the Work, and shall remedy any defects due to faulty materials, equipment or workmanship which appear within a period of one year from the Date of Substantial Completion of the Contract or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required by the Contract Documents. The provisions of this Article 23 apply to Work done by Subcontractors as well as to Work done by direct employees of the Contractor."
Article 25 of the contract provides:
"If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents or fails to perform any provision of the Contract, the Owner may, after seven days' written notice to the Contractor and without *762 prejudice to any other remedy he may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor or, at his option, may terminate the Contract and take possession of the site and of all materials, equipment, tools, and construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever method he may deem expedient, and if the unpaid balance of the Contract Sum exceeds the expense of finishing the Work, such excess shall be paid to the Contractor, but if such expense exceeds such unpaid balance, the Contractor shall pay the difference to the Owner."
It is clear that when these articles are read together, the owner may terminate the contract and complete the work if, after notice, the contractor fails to comply with the terms of the contract by correcting the deficiencies. The deficiency complained of was the defective brick job.
Plaintiff admitted the brick work was poor and needed partial replacement. He stated that the mortar joints were "really sloppy" and needed cleaning. He further testified the brick walls fell on two occasions. The first was when the brick work was being constructed and the second was after the completion of the brick job. In his testimony at trial, he stated vibration from nearby passing trains caused the bricks to fall. However, in his deposition,[2] plaintiff stated that lack of wall ties caused the brick to fall. Keating testified further that there were no wall ties in the section of brick wall that fell after the house was completed. However, he did state that he knew some wall ties were used in the brick work.
Larry Boudreaux, a bricklayer, examined the walls after completion but before the wall fell on the second occasion. He noticed "a couple of walls" were not plumb and had to be torn down. He further testified the brick work was "smeary". He did state, however, that in his opinion it was not necessary to replace the entire brick work. According to Boudreaux, because he examined the walls after completion, he could not ascertain if wall ties were used.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
292 So. 2d 759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/keating-v-miller-lactapp-1974.