Barnhill Bros. v. Louisiana Department of Highways

147 So. 2d 650, 1962 La. App. LEXIS 2630
CourtLouisiana Court of Appeal
DecidedDecember 14, 1962
DocketNo. 5676
StatusPublished
Cited by4 cases

This text of 147 So. 2d 650 (Barnhill Bros. v. Louisiana Department of Highways) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnhill Bros. v. Louisiana Department of Highways, 147 So. 2d 650, 1962 La. App. LEXIS 2630 (La. Ct. App. 1962).

Opinion

ELLIS, Judge.

This suit was instituted by the plaintiffs, Barnhill Brothers, Inc. and C. E. Williams Construction Co., Inc., against the defendant, Louisiana Department of Highways, alleging that the defendant was indebted unto the plaintiffs in the sum of Ninety-eight Thousand Seven Hundred Sixty-six and S3/100 Dollars ($98,766.53) for failure to pay the balance due on a contract entered into between plaintiffs and defendant on March 31, 1960, on State Project No. 25-08-20, Summer Grove-Shreveport Highway, Route La. U.S. 171.

Plaintiffs and defendant executed a stipulation of certain facts which were entered into the record prior to the trial of the case in District Court. The agreed stipulation of fact is as follows:

“1. That on March 31, 1960, a contract was entered into between the plaintiffs and the defendant for the construction of State Project No. 25-08-20, entitled Summer Grove-Shreve[651]*651port Highway, Route La.-U.S. 171, Parish of Caddo, consisting of 3.082 miles of Portland Cement concrete pavement; that the original contract amount was Nine Hundred Twenty-five Thousand Three Hundred 'Ninety-nine and 59/100 Dollars ($925,399.59) which amount was increased by virtue of ‘extra work orders’, etc, during the period of construction to a total sum of Approximately Nine Hundred Eighty-five Thousand and no/100 Dollars, ($985,000.00); That certain of these amounts have been paid by the defendant to the plaintiffs and due credit has been given therefore; that should the plaintiffs be held by the Court to be entitled to judgment in this case, then it is stipulated and agreed that the proper amount of that judgment is the full sum of Ninety-four Thousand Nine Hundred Ninety-nine and 84/100 Dollars ($94,999.84), together with legal interest from judicial demand until paid and for all costs of this suit.
“2.' That the contractors, plaintiffs herein, pursued to execute the contract with due diligence and within the time allowed by said contract and did, on August 9, 1961, submit said project for final inspection; that same was inspected by the defendant on that date and that all of the project was acceptable to the defendant with the exception of the overpass over the T & P Railway; that the defendant refused to accept the overpass over the T & P Railroad because it could not be used for the purposes intended; that the entire project would have been accepted and payment made therefor had it not been for the deteriorated condition of those portions of the overpass in which Class ‘Y’ concrete was used on that date.
“3. That all of the drawings, plans and specifications for this project were prepared by the defendant and its agents, reviewed by the United States Department of Commerce, Bureau of Public Roads, and furnished to the contractors and that they, the said contractors, followed them.
“4. That the contract was performed by the plaintiffs with the defendant’s employees performing their functions of supervision and inspection as set forth in the Standard Specifications for Roads and Bridges, dated July, 1955, which said publication was made a part of the contract between the plaintiffs and defendant, and specifically as set forth in said publication in Sections 5.07, 5.08 and 5.09.
“5. That prior to the construction of the project the defendant sampled, tested and approved, as being in accordance with plans and specifications, all of the component materials that went into the construction of the overpass.
“6. That the defendant furnished to the contractors, and/or to the supplier of the contractors, the mix design for the Class ‘Y’ concrete that was used in the project and that the contractor and/or the supplier of said contractor followed it.
“7. That the locations, dimensions and details of the finished work conformed strictly to the approved plans.
“8. That to the best of the knowledge, information and belief of the defendant, the contractors performed the contract, insofar as material used and workmanship performed, as was required by the plans and specifications furnished them, without deviations therefrom.
“9. That the pouring of the Class ‘Y’ concrete on the overpass was commenced on or about October 11, 1960, and the pouring of the last span of ‘Y’ concrete was completed about December 27, 1960; that the overpass was opened to traffic about February 2, [652]*6521961, and upon traffic using it, cracking of the Class ‘Y’ concrete appeared; the overpass was closed to traffic June 20, 1961, by the defendant and the cracked portions were patched and an ''extra work order’ issued therefore; that the overpass was then reopened to ■traffic about July 5, 1961, and the cracking became progressively worse; that as of August 19, 1961, the cracking was of such extent that the defendant’s engineers considered said overpass to be unsafe and it was closed to traffic on that date and has been closed ever since; the contractor was ordered to crack out and replace all of the decking, walkways and handrails in which fhe Class ‘Y’ concrete was used, at the contractors expense; that the contractors refused to do so.
"10. That, to the best of the information, knowledge and belief of the defendant, there were no deviations from the plans and specifications insofar as material or workmanship on the part of the contractor, its agents or employees, on this project.
"11, That a-new contract was let for cracking out and replacing of the Class ‘Y’ concrete on this project; that the new contract was for the total sum of Eighty-nine Thousand Four Hundred Sixty and-02/100 Dollars ($89,460.02).
"12. That the plaintiffs made a formal request to the defendant that Caddo Lightweight Aggregate Company be approved as a supplier of lightweight aggregate material; that a sample of this material was submitted to the defendant whereupon the Department tested the lightweight material and said material passed the standard tests made by the defendant and was approved as an acceptable lightweight material.”

The contract entered into between the plaintiffs and defendant provided withholding five per cent (5%) of the contract price until full completion of the contract and its acceptance by the Department of Highways. Plaintiffs contend that all the work was completed under the contract on August 9, 1961, and the completed project was submitted to defendant for its final inspection and acceptance. Defendant refused to accept the project as completed because the concrete decking and concrete handrail on the overpass over the T & P Railroad, which had been constructed of Class ‘Y’ Concrete in accordance with the specifications, has cracked and deteriorated when the State project was opened to traffic. Defendant called upon plaintiff to tear out and remove all the cracked concrete decking and concrete handrail from the overpass and replace it at their own expense. Plaintiffs refused to comply with the demand and defendant advertised for bids and awarded this contract to Minden Concrete Company for the contract amount of $98,406.02.

Plaintiffs then brought this suit to recover the balance claimed under its contract alleging that it had faithfully performed all the work called for by the contract in strict accordance with its plans and specifications and under the supervision and direction of defendant’s authorized agents and engineers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sisters of the Good Shepherd v. Quinn Const. Co.
225 So. 2d 225 (Louisiana Court of Appeal, 1969)
Washington Parish Police Jury v. Belcher & Son, Inc.
215 So. 2d 849 (Louisiana Court of Appeal, 1968)
Pittman Construction Co. v. City of New Orleans
178 So. 2d 312 (Louisiana Court of Appeal, 1965)
Pittman Construction Co. v. Board of Levee Commissioners
169 So. 2d 192 (Louisiana Court of Appeal, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
147 So. 2d 650, 1962 La. App. LEXIS 2630, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnhill-bros-v-louisiana-department-of-highways-lactapp-1962.