Bentley v. State

41 N.W. 338, 73 Wis. 416, 1889 Wisc. LEXIS 158
CourtWisconsin Supreme Court
DecidedJanuary 29, 1889
StatusPublished
Cited by36 cases

This text of 41 N.W. 338 (Bentley v. State) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bentley v. State, 41 N.W. 338, 73 Wis. 416, 1889 Wisc. LEXIS 158 (Wis. 1889).

Opinion

Cassoday, J.

The only question raised by the demurrer is whether the complaint above set forth states facts sufficient to constitute a cause of action upon contract. The contract was only to be let after the state, through its board of commissioners, had procured and adopted “suitable and proper plans, drawings, and specifications ” for the construction of the two wings of the capítol. Sec. 3, ch. 252, Laws of 1882. Such commissioners were expressly “ authorized to employ an architect or superintendent to superintend the work on said building as it progressed,” and for which he was to receive from the state such compensation as the commissioners should determine. Id. sec. 4. Such architect was thereby required, at the close of each month, to [428]*428make out estimates in detail of all materials furnished and labor performed during said month, and duly certify the same to the board, who, after having examined, approved, and recorded the same, and after deducting fifteen per cent, of the total amount, to be retained until the completion of the contract, were to certify to the correctness thereof, when the same was to be paid by the state. Id. sec. 5. It appears that such commissioners were duly appointed and organized as a board, and employed such architect on or before May 25, 1882. It also appears that on or before that date the state, through such board and architect, did undertake to procure and adopRsuch “ suitable and proper plans, drawings, and specifications; ” and thereupon gave the requisite notice of receiving sealed proposals in the form of a blank contract furnished by them for the construction of such wings according to such plans and specifications; and that it became necessary twice to modify and alter such plans and specifications in order to secure any bids for such construction within the appropriation; and that the contract was awarded to the plaintiffs.

The contract is given above. It appears that it required all the materials to be furnished and all the work to be done according to such plans and specifications, and agreeably to such directions as might be given from time to time by such architect, and to his full and entire satisfaction; that it expressly authorized the state or its architect to vary from such plans and specifications, either by adding thereto or diminishing therefrom or otherwise, and the value of such alterations w-ere to be ascertained by him and to be added or deducted from the contract price named therein as the case might be; that such alterations and additions, as well as the work contained in the plans and specifications, were to be completed January 1, 1884; that any doubt or doubts as to the quality of materials being-used or the workmanship thereon, or as to estimating allow-[429]*429anees for extra materials or work, or for the rectification of any failure from whatever cause arising, the same was to be judged of, determined, and adjusted solely by such architect, and such determination was to be final and conclusive. From the whole contract it seems to have been the dutj" of such architect, from time to time, as the work progressed, to inspect and approve or disapprove all material and workmanship as it went into the buildings; and the plaintiffs were bound by his determinations, and required to follow his directions. In other words, the contract gave such architect complete control and superintendence over such construction, and made him the sole judge of all materials furnished and labor performed. He was, moreover, thereby authorized and empowered to modify, change, and alter such plans and specifications as he might from time to time deem expedient; and the plaintiffs had no alternative, under the contract, except to follow his directions and conform to such modified, changed, and altered plans and specifications, but with the right to additional compensation for any and all extra materials and work required by-such modifications, changes, and alterations.

Under the pleadings, we must assume that the plaintiffs proceeded in good faith to perform their said contract according to such plans and specifications, and under the direction of the architect, and without any knowledge of any defects or inefficiency; that on November 8,1883, they had a very large portion of said two wings completed, and had placed therein a large quantity of cast-iron materials, furnished by a contractor selected by said architect, and which cast-iron materials had been approved and accepted by the architect on behalf of the state; that by reason and in consequence of defects in such plans and specifications, and without any fault or negligence of the plaintiffs, and on November 8, 1883, the south wing broke down and fell, [430]*430destroying a very large amount of material and the fruits of a very large amount of labor bestowed thereon by the plaintiffs; that all the material and work so destroyed and lost had previously been approved and accepted by the architect, and been accepted by the board of commissioners, and paid for by the state upon the certificates of the architect; that thereupon other architects were employed by the state, and extensive amendments to such plans and specifications were thereupon made on behalf of the state, both for the north and south wings, whereby the same were greatly strengthened, and at large additional cost and expense; that such alterations were, then made and the buildings finished by the plaintiffs, at the special request of the state, in accordance with such new amended plans and specifications; that such work was done by the plaintiffs under the direction of said board and said architect; that in doing the same they were obliged to expend, and did expend, $22,038.20 for labor and materials in restoring so much of said south wing as had been finished and was destroyed by such fall; that the building was completed by the plaintiffs and accepted by the state, November 29, 1884; that the state has paid for the same, except the amount last stated; that the architect unreasonably and without just cause refused to certify the work done and materials furnished in rectifying such failures and restoring such south wing.

Under such a contract, and upon such facts, it is strenuously urged upon the part of the state that the plaintiffs were bound to furnish all the materials and perforin the necessary work to restore the south wing, according to such new or modified and altered plans and specifications, to the point and in the condition where it was when it fell, at their own' cost and expense. In other words, the contention is that the plaintiffs assumed the risk of the sufficiency and efficiency of the plans and specifications, and the ma[431]*431terials and workmanship thus exacted, approved, accepted, and paid for by the state; and hence must suffer and make good the loss occasioned by such defects. Under the contract, it is very manifest that, had the plaintiffs departed, from such plans and specifications and refused to follow the directions of the architect, there could have been no recovery for the building of the south wing, even had they in the first instance built it as they were finally directed by the architect to do. On the contrary, they could only recover by furnishing materials and doing the work according to such plans, specifications, and directions, as they allege they did. The fall was not the result of inevitable accident, as in several of the cases cited by counsel. According to the allegations of the complaint, it was in consequence of inefficient and defective plans and specifications therein mentioned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Johnson Construction Company v. The United States
854 F.2d 467 (Federal Circuit, 1988)
Fidelity & Deposit Co. v. City of Sheboygan Falls
713 F.2d 1261 (Seventh Circuit, 1983)
Burgess Mining & Construction Corp. v. City of Bessemer
312 So. 2d 24 (Supreme Court of Alabama, 1975)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)
Klipfel v. Neill
494 P.2d 115 (Colorado Court of Appeals, 1972)
Condon-Cunningham, Inc. v. Day
258 N.E.2d 264 (Cuyahoga County Common Pleas Court, 1969)
McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
Our Lady of Victory College & Academy v. Maxwell Steel Co.
278 S.W.2d 321 (Court of Appeals of Texas, 1955)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
Sandy Hites Co. v. State Highway Commission
149 S.W.2d 828 (Supreme Court of Missouri, 1941)
State v. Commercial Casualty Insurance
248 N.W. 807 (Nebraska Supreme Court, 1933)
L. W. Kinnear, Inc. v. City of Lincoln Park
244 N.W. 463 (Michigan Supreme Court, 1932)
Hammaker v. Schleigh
147 A. 790 (Court of Appeals of Maryland, 1929)
Reinhart Construction Co. v. Mayor of Baltimore
146 A. 577 (Court of Appeals of Maryland, 1929)
Decatur County v. Praytor, Howton & Wood Contracting Co.
142 S.E. 73 (Supreme Court of Georgia, 1928)
Louisiana Shipbuilding Co. v. Bing Dampskibsaktieselskab
104 So. 364 (Supreme Court of Louisiana, 1925)
Oklahoma City v. Derr
1928 OK 159 (Supreme Court of Oklahoma, 1925)
Heman Construction Co. v. Mason
212 P. 1089 (Supreme Court of Kansas, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
41 N.W. 338, 73 Wis. 416, 1889 Wisc. LEXIS 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bentley-v-state-wis-1889.