Decatur County v. Praytor, Howton & Wood Contracting Co.

142 S.E. 73, 165 Ga. 742, 1928 Ga. LEXIS 58
CourtSupreme Court of Georgia
DecidedFebruary 14, 1928
DocketNo. 5997.
StatusPublished
Cited by7 cases

This text of 142 S.E. 73 (Decatur County v. Praytor, Howton & Wood Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Decatur County v. Praytor, Howton & Wood Contracting Co., 142 S.E. 73, 165 Ga. 742, 1928 Ga. LEXIS 58 (Ga. 1928).

Opinion

Hines, J.

(After stating the foregoing facts.)

The writ of error in this case was returnable to the Court of Appeals. Counsel for the plaintiff in error moved that court to transfer the case to this court, upon the ground that that court was without jurisdiction to decide the case. The alleged lack of jurisdiction was based upon the ground that the second count of the petition made a case in equity, of which the Court of Appeals was without jurisdiction, and of which this court had jurisdiction, to decide the questions raised in the bill of exceptions. The Court of Appeals refused to transfer the case to this court, holding that the petition, brought in two counts, when properly construed, made in each count a plain action at law based upon a breach of contract,, and that it had jurisdiction of the case. Decatur County v. Praytor, Howton & Wood Contracting Co., 36 Ga. App. 611 (137 S. E. 918). In its application to this court for certiorari to review rulings made by the Court of Appeals, the plaintiff in error excepts to the ruling of the Court of Appeals touching its jurisdiction, and seeks, to have the same reviewed and reversed. So we are first confronted with the question: Did the Court of Appeals have jurisdiction of this cause? The proper answer to this question depends upon whether or not the case is one in equity. It is *753 conceded by counsel for the county that the first count of the petition, if it sets forth any cause of action, makes one at law.

The second count of the petition, briefly stated, makes this case: The contracting company and the county entered into a contract for the erection of a bridge over Flint river at Bainbridge. The contractor agreed to furnish all materials and perform all the work required in the construction of the bridge in strict and entire conformity with the provisions of the contract, the notice to contractors, the proposal of the contractor, and the plans and specifications prepared by the State highway engineer or his assistant. The county agreed to pay to the contractor for such work when completed, in accordance with the provisions of the contract, the unit prices set forth in the contractor’s proposal, amounting approximately to $154,000, payments to be made as provided in the specifications. The plans and specifications provided that the foundations of the piers of the bridge should be at certain elevations above,, sea-level. The foundation of pier (d) was to be excavated to an elevation about 30 feet above sea-level. The foundation of pier (e) was to be at an elevation about 36 feet above sea-level. The specifications contained this provision: “The elevation shown on the plans for the bottom of piers, abutments, or footings represent the foreseen conditions. In case the actual elevations necessary to obtain a foundation satisfactory to the engineer differ from those shown on the plans, an allowance will be made either for or against the contractor at an equitable unit price to be estimated by the engineer.” The contractor constructed pier (e) on the west bank of the river, and partially completed pier (b) on the east bank of the river, and built and completed the approaches to piers on both sides of the river, in accordance with the plans and specifications. The work on said piers and the approaches thereto was duly accepted by the county, and paid for in accordance with the terms of the contract, less 15 per cent, of the amount or value of said completed work, which percentage amounted to $10,-380.07, and was reserved by the county as provided by the terms of the contract. After completing said work the contractor commenced work on pier (d) located near the center of the river. It was then discovered that the foundations of piers (d) and (c) could not be erected at the elevations designated in the plans and specifications. The foundation of pier (d) would have to be con *754 structed at an elevation of at least 14 feet above sea-level, and that of pier (c) would have to be constructed at an elevation of eight feet seven inches above sea-level. Petitioner alleges that the representation in the plans and specifications, as to the elevations to which excavations would have to go for the foundations for the piers of the bridge, were regarded as material by the parties to the contract, for the reason that a material variance from the subsurface conditions as represented by the plans would require larger, heavier, and more expensive equipment from that which would be necessary if the subsurface conditions were as represented in the plans; that, before said contract was entered into, it inquired of the lawfully authorized engineer, representing the county and the State Highway Department in all matters relating to obtaining the contract and the construction of the bridge, if the State Highway Department was certain that .the excavations specified were correct, petitioner stating to the engineer that it would not bid on said project unless. core-drills had been made, and it was certain that the depth would not go below elevation 30, for the reason that petitioner was not financially able to enter into a contract to construct any bridge where the depth required was greater than the above elevation. In reply the engineer represented to petitioner that core-drills had been made, and that the elevations specified in the plans'were certain and fixed; and petitioner relied on such representation and said plans in bidding upon said work, and in entering into the contract for the construction of the bridge. Petitioner further alleges that the contract was based upon the existence of essential and material facts, to wit: that solid or bed-rock could be found at the elevations set forth in the plans, which facts did not exist; and -had petitioner known that they did not exist, it would not have entered into the contract, as it was in no condition, either financially or physically, to go below the elevations set forth in the contract, which fact was known to the county. Petitioner further alleges, that it entered into the contract in ignorance of the true conditions, which were fundamental, without any negligence on its part, and that it was assured by both parties to the contract that solid or bed-rock could be reached at the elevations called for in the specifications and plans, which facts were essential and fundamental and did not exist, their existence being so vital that petitioner would not have en *755 torecl into the contract had if known that the conditions as shown by the plans and specifications did not exist; that as soon as it discovered the depths to which said piers would have to go and that the actual conditions were not as had been represented to it by the contracting parties, it notified the State Highway Department that the contract could not be carried out in accordance with the plans and specifications and had been breached, that it would not proceed with the contract, and that the same was canceled; that to construct the bridge according to the plans and specifications would require such' material changes in the plans and specifications and such additional expense that the contract should be declared null and void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rome Housing Authority v. Allied Building Materials, Inc.
355 S.E.2d 747 (Court of Appeals of Georgia, 1987)
Robert E. McKee, Inc. v. City of Atlanta
414 F. Supp. 957 (N.D. Georgia, 1976)
State Highway Department v. Hewitt Contracting Co.
149 S.E.2d 499 (Court of Appeals of Georgia, 1966)
Hewitt Contracting Co. v. State Highway Department
149 S.E.2d 735 (Court of Appeals of Georgia, 1966)
Stone & Webster Engineering Corp. v. Brunswick Pulp & Paper Co.
209 A.2d 890 (Superior Court of Delaware, 1965)
Blackwell v. Blackwell
4 S.E.2d 168 (Supreme Court of Georgia, 1939)
Decatur County v. Praytor, Howton & Wood Contracting Co.
142 S.E. 919 (Court of Appeals of Georgia, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
142 S.E. 73, 165 Ga. 742, 1928 Ga. LEXIS 58, Counsel Stack Legal Research, https://law.counselstack.com/opinion/decatur-county-v-praytor-howton-wood-contracting-co-ga-1928.