State Highway Department v. Hewitt Contracting Co.

149 S.E.2d 499, 113 Ga. App. 685, 1966 Ga. App. LEXIS 1177
CourtCourt of Appeals of Georgia
DecidedApril 14, 1966
Docket41860
StatusPublished
Cited by12 cases

This text of 149 S.E.2d 499 (State Highway Department v. Hewitt Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Department v. Hewitt Contracting Co., 149 S.E.2d 499, 113 Ga. App. 685, 1966 Ga. App. LEXIS 1177 (Ga. Ct. App. 1966).

Opinion

Jordan, Judge.

This case was transferred to the Supreme Court by this court because of the allegations and prayers of count 5 of the petition seeking rescission of the contract on the ground of mutual mistake so that recovery could be had, independently of the contract, for the reasonable value of all the work performed and of all the materials furnished in the construction of the highway project on the basis of quantum meruit. In State Hwy. Dept. v. Hewitt Contracting Co., 221 Ga. 621 (146 SE2d 632), the Supreme Court held that this case did not come within the equity jurisdiction of that court and remanded the case to this court. This ruling was based upon two grounds: (1) that the plaintiff was not entitled to the equitable relief of rescission of contract since it was not shown that the plaintiff had acted promptly to seek such relief upon discovery of the alleged mutual mistake but on the contrary had continued for a year or two to perform the contract until completion; and (2) that rescission of the contract was not necessary “in order *688 for the plaintiff to recover, if entitled to recover, the value of the additional work allegedly caused by the mistake found in the specifications of the project,” since the contract itself anticipated that there might be errors and omissions in the specifications which would cause extra or additional work not set out in the specifications and made ample provision for compensation to be paid the contractor for such additional work. As pointed out in the opinion at page 622: “The contract was attached as an exhibit to count 5. It plainly appears from the terms of the contract that, while the specifications which constituted a part of the contract were relied upon as the basis of the same, there might be errors and omissions in the specifications which would cause extra or additional operations not set out in the specifications. The contract made ample provision for compensation to be paid the contractor for such additional work. It furnished two formulas to be used in determining the value of the work: one that the parties agree upon the price to be paid; the other that they submit the matter to arbitration. From count 5 or elsewhere in the petition it did not appear that the mistakes referred to in the count were not of the nature contemplated by the contract or that the extra work caused by the alleged mistakes was not within the provisions of the contract, stipulating compensation for such work would be paid the contractor.”

The Supreme Court in denying the plaintiff’s right to equitable relief held in effect that the plaintiff contractor must recover, if at all, under the contract executed by the parties; and in so ruling reached the same result arrived at by that court in Decatur County v. Praytor, Howton &c. Co., 165 Ga. 742 (142 SE 73). In that case, the plaintiff contractor brought suit against the county with which it had contracted to build a bridge to recover damages for the county’s alleged breach of an implied warranty that the plans and specifications for the construction of the bridge were correct. The petition alleged that there were errors in these plans and specifications of which the county had knowledge when the contract was executed, that the plaintiff did not have knowledge of the same at the time of the execution of the contract and had relied upon their correctness in bidding, and that upon discovering such errors, the plaintiff immediately re *689 nounced the contract and brought suit to recover the reasonable value of the work performed and materials furnished up to the time of discovering the errors in the plans and specifications plus lost profits resulting from failure to complete the contract because of the county’s breach of same.

The court in holding that there was no implied warranty of the correctness of the plans and specifications and that the contractor had no right to repudiate the contract because of the errors therein but was under a duty to do whatever work was necessary to complete the project, pointed out that the subject contract clearly anticipated that there might be errors in the plans and- specifications and that additional work might be caused by such errors and by changes in the plans and specifications and provided for the contractor to be compensated for the actual work done upon completion of the project which included compensation for any additional work required because of errors or changes in the plans and specifications. After considering the various provisions of the contract anticipating errors and changes in the plans and specifications, the court stated as follows at page 763 of the opinion: “[W]e do not think that the county intended that the representation that the elevations for the bottoms of-the piers represented foreseen conditions was a warranty of the representation, upon which the contractor could act in erecting these piers, and that the untruthfulness of the representation would be a breach of the warranty for which the county would be liable to the contractor in damages. The contractor certainly was not led to believe, that these piers were to be built on foundations at the elevations above sea level shown on the plans. In consequence the contractor would not be hurt by the falsity of the representation. For the additional material and work rendered necessary by erecting the piers at lower elevations above sea level, it would be paid the unit prices at which it agreed to erect them at the elevations shown on the plans.

“But the contractor insists that it was not financially able to erect this bridge on these piers at the reduced elevations, and that it would not have submitted a proposal if it had known that the piers had to be built upon these lower foundations. This contention is not well taken. The specifications provided for *690 such situation, and for increased compensation to the contractor in consequence of the changed situation. In these circumstances the contractor submitted a proposal to build this bridge, and contracted to build it, if the piers could not be built at the elevations shown upon the plans, and the county agreed to pay it for all additional material which would have to be furnished and for all additional labor which would have to be performed, in constructing these piers upon different foundations and at lower levels. Its proposal was not alone to build these piers upon the elevations shown in the plans, in which case it would have been relieved from so doing if the piers could not be so built, but its proposal was to build these piers upon different foundations if the foundations represented upon the plans were unsatisfactory to the engineer. The contractor was as much bound by its proposal and contract to build the piers upon different and lower foundations, if the foundations shown on the plans were unsatisfactory to the engineer, as it was to build these piers on the foundations shown in the plans. If the contractor did not wish to run the risk of having to furnish the additional material and do the additional work necessary to erect them at lower elevations than called for in the plans, because of its financial inability to do so, it should not have submitted this proposal and entered into the contract which required the contractor to erect them on different foundations which might involve additional expenditures for material and labor.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Surety Co. v. Department of Transportation
757 S.E.2d 272 (Court of Appeals of Georgia, 2014)
Department of Transportation v. Dalton Paving & Construction, Inc.
489 S.E.2d 329 (Court of Appeals of Georgia, 1997)
Apac-Georgia, Inc. v. Department of Transportation
472 S.E.2d 97 (Court of Appeals of Georgia, 1996)
Department of Transportation v. Fru-Con Construction Corp.
426 S.E.2d 905 (Court of Appeals of Georgia, 1992)
Rome Housing Authority v. Allied Building Materials, Inc.
355 S.E.2d 747 (Court of Appeals of Georgia, 1987)
Jahncke Service, Inc. v. Department of Transportation
322 S.E.2d 505 (Court of Appeals of Georgia, 1984)
New Pueblo Constructors, Inc. v. State
696 P.2d 203 (Court of Appeals of Arizona, 1984)
Department of Transportation v. Claussen Paving Co.
273 S.E.2d 161 (Supreme Court of Georgia, 1980)
State Highway Department v. Charles R. Shepherd, Inc.
168 S.E.2d 922 (Court of Appeals of Georgia, 1969)
Clark v. Belleau, Inc.
151 S.E.2d 894 (Court of Appeals of Georgia, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
149 S.E.2d 499, 113 Ga. App. 685, 1966 Ga. App. LEXIS 1177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-department-v-hewitt-contracting-co-gactapp-1966.