State Highway Department v. Wright Contracting Co.

131 S.E.2d 808, 107 Ga. App. 758, 1 A.L.R. 3d 1260, 1963 Ga. App. LEXIS 975
CourtCourt of Appeals of Georgia
DecidedApril 11, 1963
Docket39894
StatusPublished
Cited by30 cases

This text of 131 S.E.2d 808 (State Highway Department v. Wright Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Department v. Wright Contracting Co., 131 S.E.2d 808, 107 Ga. App. 758, 1 A.L.R. 3d 1260, 1963 Ga. App. LEXIS 975 (Ga. Ct. App. 1963).

Opinion

Felton, Chief Judge.

It must first be determined whether or not the items claimed by the plaintiff in count 3 constituted “extra work” as defined by § 1.29 of the State Standard Specifications, in accordance with which the contractor agreed to perform the work under the contract. “Extra work” is defined as “work or material, the performance or furnishing of which is found necessary for proper completion of the improvement and which in principle is an obligation of the contractor, but which is not covered by any item in the bid schedule in the *762 Proposal and for which no means of payment, direct or indirect, has been provided in the Contract, and which is an obligation for which special remuneration, by an ‘extra’ price or by other consideration, in any case to be duly negotiated, or by ‘Force Account’, shall be paid to the Contractor.”

The plaintiff in error argues that the work done does not come within the definition of “extra work” above for the reason that the defendant in error failed to comply with the requirements of § 2.06 of the Standard Specifications, which provide that “The bidder is required to examine carefully the site of, and the proposal, plans, Specifications and Contract Form for the work contemplated and it will be assumed that he has judged for and satisfied himself as to the conditions to be encountered, as to the character, quality and quantities of work to be performed and the materials to be furnished, and as to the requirements of these Specifications, Special Provisions and Contract. No adjustments on compensations will be allowed for losses caused by failure to comply with the above requirements.” Construing this provision most strongly against the defendant, who formulated it, we do not believe that the conditions encountered on the project were such that the contractor should have been expected to have anticipated in the exercise of reasonable diligence. The fact that the contract makes provisions for extra work necessitated by unforeseen conditions is evidence enough that not every condition is expected to be anticipated. The additional fact that the defendant executed a supplemental agreement compensating the plaintiff for materials used in the extra work estops it from asserting the defense that the plaintiff was barred from a recovery for failure to comply with this section. Paragraph 24 (d) of the plaintiff’s amended petition alleges that there is no dispute between the parties over the fact that the work was “extra work” and that the only issue with reference to this claim is the amount due the plaintiff for this work. The defendant’s general demurrer to this allegation admits its truth for purposes of pleading.

Having decided that under the allegations of the petition the work was “extra work,” we must now determine whether there was either such a compliance by the plaintiff with the provisions *763 of the contract concerning compensation for extra work, or a waiver of these provisions by the defendant. Section 4.04 of the Standard Specifications provides in part that “before any ‘Extra Work’ is started a ‘Supplemental Agreement’ shall be signed by both contracting parties or an Extra Work Order from the Engineer to do the work on a ‘Force Account’ basis given the Contractor.” (Emphasis supplied). Section 9.05 provides in part that “[i]n all cases such agreements shall be made before the work is started . . .” (emphasis supplied) and that “[t]he Engineer shall secure from the Contractor a written agreement for the work to be done and basis of payment (lump sum, force account or unit price) and submit the same together with his estimate of amount and cost of work to the Department for authorization to perforin such Extra Work.” In § 9.05 (D), it is further provided that “[n]o extra work on a Force Account Basis will be paid for unless unit prices for labor, materials, and equipment rentals have been agreed upon in writing before such work is started. In no case shall the unit prices paid to the Contractor exceed the amount of the quoted unit price for each item stipulated in the Force Account Agreement.” (Emphasis supplied). From the above provisions, it seems clear that a prerequisite to the contractor’s recovery upon a force account is a written agreement with the Department, stipulating unit prices, made before the work is started. No such agreement is alleged by the plaintiff to have been executed and, construing the petition most strongly against the pleader, we must assume that there was none.

Was there a waiver by the defendant of this provision requiring a prior written agreement? Section 4.03 provides in part that “ [supplemental agreements . . . increasing or decreasing the quantity of work by more than twenty [20] percent as provided above, are independent of and do not waive any of the provisions regarding extra work as stipulated in Article 4.O4.” (Emphasis supplied). This would seem to indicate that the supplemental agreement did not waive the necessity for the supplemental agreement or the extra work order to have been executed before the work was started.

As described above, the defendant's actions evidenced its ac *764 knowledgment that the work was “extra work” and hence would require additional compensation. With this knowledge it directed the performance of the extra work, without taking the action required of it by § 9.05 of the Standard Specifications, to wit: “The Engineer shall secure from the Contractor a written agreement for the work to be done and basis of payment . . .” The plaintiff notified it both before commencing the work and before executing the supplemental agreement that it expected to submit a claim for the cost in excess of the contract amount plus a reasonable profit. The supplemental agreement covered merely the cost of materials, which was obviously only a part of the total extra cost incurred. The supplemental agreement contains no provision indicating that it is payment in full for all the compensation due the contractor. An additional indication of the defendant’s waiver of this contractual requirement is the allegation of paragraph 24 (a) of the petition as amended (which the general demurrer admits, for pleading purposes, to be true) that “Following the completion of said extra work, as was its custom and practice at that time, defendant submitted to petitioner, with reference to said extra work, a Supplemental Agreement. . .” (Emphasis supplied). This alleged practice, plus the fact that the defendant directed the plaintiff to do the work without first securing a written agreement as provided in the contract, led the plaintiff to assume that the provision had been waived, and it would be manifestly unjust for the defendant to insist upon the strict terms of the contract after having so misled the plaintiff and received the fruits of its labors. “Where the owner, without claiming that the work is covered by the contract, orally orders extra work, as such, with notice that the contractor regards the work as extra and expects additional compensation therefor, the contractor can recover for the work notwithstanding a stipulation of the contract requiring a written order therefor.” 66 ALR 649, 674; Id., p. 701; Southern Life Ins. Co. v. Citizens Bank of Nashville, 91 Ga. App. 534, 538 (86 SE2d 370); Kaufman v. Young, 32 Ga. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia Department of Labor v. Rtt Associates, Inc.
786 S.E.2d 840 (Supreme Court of Georgia, 2016)
Western Surety Co. v. Department of Transportation
757 S.E.2d 272 (Court of Appeals of Georgia, 2014)
Circle Y Construction, Inc. v. WRH Realty Services, Inc.
721 F. Supp. 2d 1272 (N.D. Georgia, 2010)
Department of Transportation v. Dalton Paving & Construction, Inc.
489 S.E.2d 329 (Court of Appeals of Georgia, 1997)
Pro Metal Building Systems, Inc. v. T. E. Driskell Grading Co.
316 S.E.2d 574 (Court of Appeals of Georgia, 1984)
Harry Norman & Associates, Inc. v. Bryan
282 S.E.2d 208 (Court of Appeals of Georgia, 1981)
Stubbs v. Tattnall Bank
259 S.E.2d 466 (Supreme Court of Georgia, 1979)
King v. Gilbert
445 F. Supp. 479 (N.D. Georgia, 1977)
CCC Builders, Inc. v. City Council
229 S.E.2d 349 (Supreme Court of Georgia, 1976)
Daniel & Daniel, Inc. v. Stewart Brothers, Inc.
228 S.E.2d 586 (Court of Appeals of Georgia, 1976)
Biltmore Construction Co. v. Tri-State Electrical Contractors, Inc.
224 S.E.2d 487 (Court of Appeals of Georgia, 1976)
Board of Regents of the University of Texas v. S & G Construction Co.
529 S.W.2d 90 (Court of Appeals of Texas, 1975)
Duval & Co. v. Malcom
214 S.E.2d 356 (Supreme Court of Georgia, 1975)
Southeastern Highway Contracting Co. v. State Highway Department
202 S.E.2d 520 (Court of Appeals of Georgia, 1973)
Frey v. Friendly Motors, Inc.
200 S.E.2d 467 (Court of Appeals of Georgia, 1973)
Western Contracting Corp. v. State Highway Department
187 S.E.2d 690 (Court of Appeals of Georgia, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
131 S.E.2d 808, 107 Ga. App. 758, 1 A.L.R. 3d 1260, 1963 Ga. App. LEXIS 975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-department-v-wright-contracting-co-gactapp-1963.