Western Contracting Corp. v. State Highway Department

187 S.E.2d 690, 125 Ga. App. 376, 1972 Ga. App. LEXIS 1342
CourtCourt of Appeals of Georgia
DecidedJanuary 26, 1972
Docket46603
StatusPublished
Cited by6 cases

This text of 187 S.E.2d 690 (Western Contracting Corp. v. State Highway Department) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Contracting Corp. v. State Highway Department, 187 S.E.2d 690, 125 Ga. App. 376, 1972 Ga. App. LEXIS 1342 (Ga. Ct. App. 1972).

Opinion

Clark, Judge.

Plaintiff-appellant’s several count complaint alleges existence of a highway construction contract between the parties and breach thereof in several respects. This appeal is from an order granting both a motion to dismiss the complaint and a motion for a judgment on the pleadings as to all counts of the complaint.

The record in this case is voluminous consisting of 133 pages plus six separate books or documents containing Standard Specifications, Notice to Contractors, Proposal, and Highway Construction Engineering Plans. This court owes thanks to the able counsel on both sides for the manner in which each of them aimed towards making our task of decision easier by simplifying the issues provided through the extensive research and learned briefs.

This is the second appearance of this case, the first appeal being reported as Western Contracting Corp. v. State Hwy. Dept., 123 Ga. App. 331 (181 SE2d 89) which refrained from dealing with the questions now presented.

Essentially, the complaint alleges plaintiff entered into a contract with defendant State Highway Department to construct the 5.049 miles of grading, dredging, and hydraulic embankment on Interstate 95 in Glynn-Mclntosh Counties; that as a part of the contract defendant provided plans designating certain "borrow pit” areas adjacent to the proposed right of way from which plaintiff was to pump the hydraulic material in order to construct the embankment; that after construction began plaintiff learned certain of the designated privately owned borrow areas were unavailable for use, which was contrary to the contract; and that borrow pit areas farther away from the proposed embankment had to be used, thus requiring increased expenditures. Of particular importance is a document entitled Sheet 22 of the plans captioned "Pit Location Sketches Hydraulic Borrow” which [377]*377is more fully discussed herein:

Count 1 alleges defendant was promptly notified of the landowner’s refusal to allow acquisition of material from their property, but defendant took no action whatsoever to acquire these borrow areas notwithstanding they had been designated in the plans as available for use at the date the contract was made. Plaintiff thus had to expend more funds for labor, machinery, equipment and fuel than was contemplated at the date of the making of the contract. This count also alleges a retainage now due is being withheld by the defendant because of the dispute between the parties; and that plaintiff has complied with all provisions in the contract required prior to the bringing of the complaint, including a request for arbitration, which was denied.

Count 2 repeats the unavailability of the designated borrow pits. It further alleges the Highway Department was contractually obligated to obtain options from the owners of any lands shown on the plans as designated sources of borrow material; that only after plaintiff began performance of its obligations was it learned defendant had breached the contract by failing to obtain such options; that defendant was immediately notified of the breach but failed and refused to cure same by obtaining the options from all the owners, although plaintiff allowed defendant a reasonable period of time to do so; that plaintiff then attempted to obtain agreements but was unsuccessful with respect to some of the areas; and that because of this breach plaintiff suffered extensive delays in performance of its obligations, resulting in additional costs.

Count 3 realleges the unavailability of the designated borrow pits and further alleges plaintiff notified defendant that being denied use of the designated borrow areas would result in "extra work under the contract” (the contract which is a part of the complaint defines "extra work” as work necessary for completion which was unforeseen during preparation of the Plans and Specifications) but that defendant refused to enter into a [378]*378supplemental agreement (the contract provides a basis for such agreement) and instead directed plaintiff to continue its work.

Count 4 again alleges the unavailability of the designated borrow pits and proceeds upon the theory that defendant’s failure to obtain the necessary options for the borrow pit area shown on the plans constituted a "change in the plans” and thus a change in the nature and extent of the work to be performed under the contract; that the defendant was notified that this change in plans had resulted in an alteration in the character of the work and a substantial change in the nature of the construction and materially increased the cost of performance, but defendant failed to enter into a supplemental agreement regarding the increased cost of performance, and directed plaintiff to continue with its work.

Count 5, couched in quantum meruit, repeats the failure to obtain the options and further alleges the unavailability of the designated borrow pits shown in the plans constituted a "mistake” in the plans; that plaintiff was required to do additional work which was accepted by the defendant; but that defendant has failed and refused to pay plaintiff therefor despite work completion and demand for payment.

Count 7 realleges the unavailability of the designated borrow pits, and further states that defendant was notified thereof; that defendant would not execute a supplemental agreement; and that before undertaking that portion of the work in question it further notified the defendant of its intention to claim extra compensation in accordance with the procedure delineated in the contract therefor.

Each count of the complaint, with the exception of Count 1, additionally alleged that the defendant’s failure to perform in accordance with the obligations alleged in the respective counts was such as to amount to bad faith or fraud. These allegations undoubtedly are pleaded to meet the ruling of this court in State Hwy. Dept. v. W. L. Cobb Constr. Co., 111 Ga. App. 822 (143 SE2d 500).

[379]*379Other counts originally contained in the complaint have been abandoned.

Defendant’s motion to dismiss the complaint was addressed to each count therein except Count 1. The motion was made and sustained as to each count to which it was addressed on the grounds of (1) failure to state a claim upon which relief might be granted, (2) failure to state a claim upon which relief might be granted in that no recovery was authorized by the contract as a matter of law, and (3) failure to state a claim upon which relief might be granted in that the complaint shows a claim for rescission which had been waived.

Defendant’s motion for a judgment on the pleadings was addressed to all counts of the complaint, certain grounds of which necessarily draw in issue the sufficiency of each count of the complaint as stating a claim for which relief might he granted. Held:

1. The rule which we apply when a complaint or a count therein is tested by a motion to dismiss for failure to state a claim is set forth in Harper v. DeFreitas, 117 Ga. App. 236, 238 (160 SE2d 260): "On a motion to dismiss, a complaint should be construed in the light most favorable to plaintiff with all doubts resolved in his favor. . . The plaintiff is entitled to the most favorable inferences that can reasonably be drawn from the complaint, even if contrary inferences are also possible. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Estate of Madelyn Cleveland
Court of Appeals of Tennessee, 2017
Forsyth County v. WATERSCAPE SERVICES, LLC
694 S.E.2d 102 (Court of Appeals of Georgia, 2010)
Jahncke Service, Inc. v. Department of Transportation
213 S.E.2d 150 (Court of Appeals of Georgia, 1975)
WESTERN CONTR. CORP. v. State Hwy. Dept.
187 S.E.2d 690 (Court of Appeals of Georgia, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
187 S.E.2d 690, 125 Ga. App. 376, 1972 Ga. App. LEXIS 1342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-contracting-corp-v-state-highway-department-gactapp-1972.