Circle Y Construction, Inc. v. WRH Realty Services, Inc.

721 F. Supp. 2d 1272, 2010 U.S. Dist. LEXIS 67812, 2010 WL 2696761
CourtDistrict Court, N.D. Georgia
DecidedJuly 8, 2010
Docket1:08-cv-01010
StatusPublished
Cited by5 cases

This text of 721 F. Supp. 2d 1272 (Circle Y Construction, Inc. v. WRH Realty Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Circle Y Construction, Inc. v. WRH Realty Services, Inc., 721 F. Supp. 2d 1272, 2010 U.S. Dist. LEXIS 67812, 2010 WL 2696761 (N.D. Ga. 2010).

Opinion

ORDER AND JUDGMENT

TIMOTHY C. BATTEN, SR., District Judge.

I. Summary

This case illustrates the perils of litigation. A contractor entered into a written contract with the owner of an apartment project pursuant to which the contractor performed some renovation work at the project. After the contractor completed the work, one or more of the owner’s employees/agents asked the contractor to perform additional work, which it did. When the contractor invoiced the owner $60,566.30 for that additional work, the owner, in effect, told the contractor to pound sand. The owner contended that it didn’t have to pay for the additional work because (1) the parties did not execute a written change order for that work (and the parties’ original contract said that all changes to the scope of work had to be in writing), and (2) the additional work was not authorized by the owner’s employee designated in the original contract as the person with whom the contractor should communicate when dealing with the owner. The owner felt that the contractor’s additional work was worth about $37,000 and made the contractor a “take-it-or-leave-it” *1274 offer to pay that amount, which the contractor refused. Instead of paying the $37,000 and then fighting over the approximately $23,000 difference, the owner refused to pay anything unless the contractor dropped its claim.

The contractor refused to blink. It insisted on the full $60,566.30 for the additional work that it did, threatening to add a claim for its attorneys’ fees if the matter went to litigation.

Like a riverboat gambler, the owner was undeterred, sticking to its defenses, apparently convinced that they barred any possible recovery by the contractor — even though the owner indisputably benefited from the contractor’s additional work. Instead of paying the $37,000 and negotiating over the remaining $23,000, the owner remained intransigent and took the risk of having to pay the $60,566.30 plus interest and the contractor’s attorneys’ fees.

Evidently, the owner was not aware that under Georgia law parties to a contract can, by their conduct, waive provisions of the contract — including provisions that (1) disavow the ability to change the contract orally, (2) require contract changes to be in writing, and (3) require that one party deal with only one designated employee of the other party. The owner also seemed ignorant of the fact that the contract (and its requirement that changes be written) arguably did not cover the additional work. Nor did the owner seem to recognize that the theory of quantum meruit has long been used in construction cases to allow a contractor to recover for additional work performed outside the scope of the parties’ original contract.

So the parties went to trial over $60,566.30 plus the contractor’s claim for attorneys’ fees. The trial was supposed to last about two days. Instead, it went a tortuous four. In the end, the contractor cleaned house.

II. Procedural Background

On March 14, 2008, Plaintiff Circle Y Construction, Inc. filed this action against Defendants WRH Realty Services, Inc. and WRH Hidden Colony, seeking to recover the $60,566.30 for renovation work that it performed at the Hidden Colony Apartments located in Doraville, Georgia. 1 Circle Y asserted claims against Defendants for breach of contract (both oral and written), quantum meruit, unjust enrichment, and attorneys’ fees.

On August 14, 2009, Defendants moved for summary judgment.

On November 6, 2009, the Court granted in part and denied in part Defendants’ motion, allowing the following claims to proceed to trial: (1) breach of written contract against WRH Hidden Colony; (2) breach of oral contract against both Defendants; (3) quantum meruit against both Defendants; (4) unjust enrichment against both Defendants; and (5) attorneys’ fees against both Defendants.

On March 17, 2010, the case came before the Court for a bench trial. The parties had estimated that it would take two or three days to resolve this $60,566.30 dis *1275 pute. In fact, it took four days, which forced the trial to be interrupted due to scheduling conflicts. The saga concluded on April 13, 2010.

Circle Y’s main contention at trial was that it should be paid for the additional renovation work that it performed because Defendants’ agents expressly requested that it perform such work. According to Circle Y, Defendants took several actions that amounted to a waiver of the parties’ AIA form contract’s requirement that all changes in the scope of work had to be in writing and authorized by Grahame Brown, Defendants’ designated representative.

By contrast, Defendants contended that Circle Y failed to follow the letter of the contract. They argued that they should not have to pay Circle Y for the additional work because Brown did not authorize the additional work and there was no written change order evidencing their assent to pay for that work. Defendants also argued that none of their agents who requested the additional work had authority to do so.

Following closing arguments, the Court orally announced its verdict, finding entirely in favor of Circle Y. The Court explained that this “is a wholesale victory for Circle Y, because I believe the evidence clearly compels that conclusion. It is breathtaking to me what [Defendants] did to [Circle Y]. I think [Defendants] used [Circle Y], they manipulated [Circle Y], they tried to hide behind these legal contracts. I don’t think there’s a jury in America that would sanction that type of approach to this relationship that they had.”

The Court specifically found that Defendants’ refusal to pay what they owed Circle Y was motivated by bad faith. Thus, the Court announced that the judgment would include Circle Y’s attorneys’ fees, pursuant to O.C.G.A. § 13-6-11. Moreover, article 12.14 of the parties’ contract specifically authorized an award of attorneys’ fees to the prevailing party as follows: “The substantially prevailing party in any action brought to enforce or interpret this Agreement shall be awarded and receive its costs and reasonable attorney’s fees (including those of in-house counsel), including for any appellate review.” The Court allowed the parties to brief the issue of the amount of attorneys’ fees and costs to be awarded so that a single judgment could be entered.

III. Findings of Fact

The Court finds the following facts from the evidence presented at trial. In July 2007, Defendant WRH Hidden Colony acquired the Hidden Colony Apartments. At the time of the acquisition, the apartment complex had an occupancy rate of about fifty percent and was in need of substantial renovation work. WRH Hidden Colony retained its subsidiary company, WRH Realty Services, to serve as the property manager for the renovation project.

Circle Y is a small, family-owned construction and repair company that is operated by Greg Young and his wife Cindy.

In July 2007, Bud Phillips, a regional director for WRH Realty Services, contacted Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
721 F. Supp. 2d 1272, 2010 U.S. Dist. LEXIS 67812, 2010 WL 2696761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/circle-y-construction-inc-v-wrh-realty-services-inc-gand-2010.