BL Montague Co., Inc. v. Somers

96 S.E.2d 629, 94 Ga. App. 860, 1957 Ga. App. LEXIS 945
Court of Appeals of Georgia·Decided January 8, 1957·No. 36346·Published·Cited by 9 cases

Opinion

Felton, C. J.

The plaintiff contends that it submitted to the defendants an offer containing certain stipulations and specifications for certain construction work on which the defendants were general contractors and that the defendants accepted such offer and became bound by the terms thereof. The defendants in turn contend that the instrument which the plaintiff contends was an acceptance of the plaintiff’s offer was not an acceptance but was a counteroffer which the plaintiff accepted and which, therefore, became the contract between the parties. The plaintiff’s offer was as follows:

“Date: 24 December 1952 277-S

Contract No.

Contractor: Coite-Somers Company, Vidalia, Georgia

Job Name: Heating Plant and Whse.

Job Location: Hunter AFB Savannah, Ga.

Owner: Corps of Engineers

Architect: Corps of Engineers

In accordance with conditions listed below, we agree to furnish the following material:

Structural Steel to include:

A. Anchor bolts

B. Base plates and columns

C. Beams and purlins

D. Canopy framing

E. All necessary clip angles and connection bolts

Mise. Steel and Iron to include:

A. Pipe rails

B. Fire door jamb angles

C. Channel door frames

D. Angles and blots for wood bumpers

E. Expansion joints

F. Ceiling hatches

G. Pipe barricades

H. Lintels

*862 Above structural steel items consisting of about 460 tons to be erected in place under this contract. All mise, steel and iron items to be placed by others. All foundations and anchor bolts to be set by others. Anchor bolts to be furnished by BLM Co. To the firm of The Coite Somers Co. Located At Vidalia, Georgia For the sum of $110,000.00

Prices are F.O.B. Job Site, erection as outlined above Conditions: 1. No State, Federal or local taxes are included in this contract price.

2. No back charges are authorized against this contract, unless approved in writing in advance by B. L. Montague Co.

3. Invoices are due and payable on 10th. of month following shipment and are to be paid in full, unless exceptions in writing are approved by the B. L. Montague Co.

4. No items furnished on this contract except those listed above. Accepted_ B. L. Montague Co. /s/ James

D. Riel

________. James D. Diel”

The instrument which the plaintiff contends was an unqualified and conditional acceptance of their offer and which the defendants contend was a counteroffer was as follows:

“B. L. Montague Co., Inc. Date: January 7, 1963

East Liberty Street Project Whse & Htg plant

Sumter, S. C. Contract: DA-09-133-eng 1695

Terms: Reg.

Ship To

The Coite Somers Company Hunter Field Savannah, Georgia It is agreed that delivery will be made on or before See or right is reserved to cancel order below Bid Item #3A Warehouse (Bays 1,2,3) and Heating Plant to conform to architect’s drawings 26-02-02 1 thru 12; 33-02-03 1 thru 42; 33-02-04-01, all dated 10/20/52; addenda 1 & 2 dated 12/1/52 & 12/8/52

Furnish and erect all structural steel

Furnish all miscellaneous steel and iron]

\iox lump sum price of $110,000.00

Above structural steel items consisting of approximately 460 tons to be erected in place under this contract. All miscellaneous steel and iron items to be placed by others. All foundations and *863 anchor bolts to be set by others. Anchor bolts to be furnished by B. L. Montague Co., Inc.

Purchase Order No. 5005 FG

Description of Controlled Material Alloted here by

1st. QTR 2nd. QTR

1953 1953

Item 13 20xOT

Item 14 220xOT 240xOT

Allotment No. C-2 Certified under revised CMP Regulation No. 6

Priority rating DO-C2 Certified under revised C.MP Regulation 6

/s/ William C. Somers, Jr. Partner Signature & title of authorized official Allot, for use in filling this order in compliance CMP REG. 1.

Delivery required May 1953

Order & allotment Accepted: B. L. Montague Co. Inc.

Date required for delivery and erection

By: Gen. Mgr.

Anchor Bolts and mise, .all delivered by February 15, 1953 Columns at exterior walls and fire walls and beams connecting these columns all delivered by 15 March 1953 and erection started Bal delivered and erect, started 15 May 1953

Date: 1-19-53 Invoices must state order number and point of delivery

Mail Invoices to company at Vidalia, Georgia

The Coite Somers Company By /%/ Coite Somers”

The issue involved in this case is whether or not the defendants were bound by condition one of the plaintiff’s offer which read, “No State, Federal or local taxes are included in this contract price.” If the defendants’ alleged counteroffer was in reality an acceptance of the plaintiff’s offer, then the plaintiff would have been entitled to recover. If as contended by the defendants the alleged acceptance was not an acceptance but a counteroffer which was accepted by the plaintiff, then the plaintiff was not entitled to recover.

The defendants’ instrument was not an acceptance of the plaintiff’s offer but was a counteroffer to the plaintiff which was accepted by the plaintiff and which became the contract between *864 the parties. Estes Lumber Co. v. Palmyra Yellow Pine Co., 29 Ga. App. 15 (113 S. E. 821). An acceptance of an offer must be unequivocal, unconditional and without variance of any sort; otherwise, there is no meeting of minds and assent thereto necessary to form a contract. Robinson v. Weller, 81 Ga. 704 (8 S. E. 447); Phinizy v. Bush, 129 Ga. 479 (4) (59 S. E. 259); Dillin-Morris Co. v. Gillespie, 15 Ga. App. 210 (1) (82 S. E. 812); Good Roads Machinery Co. v. Neal & Son, 21 Ga. App. 160 (1, 2) (93 S. E. 1018). There are several instances of variance between the plaintiff’s offer and the defendants’ counteroffer.

Free access — add to your briefcase to read the full text and ask questions with AI

BL Montague Co., Inc. v. Somers, 96 S.E.2d 629, 94 Ga. App. 860, 1957 Ga. App. LEXIS 945 (Ga. Ct. App. 1957).

96 S.E.2d 629 (BL Montague Co., Inc. v. Somers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Panfel v. Boyd
367 S.E.2d 54 (Court of Appeals of Georgia, 1988)
Chilivis v. ROGERS OIL COMPANY
217 S.E.2d 179 (Court of Appeals of Georgia, 1975)
J. Henry Jones Company v. Smith
494 P.2d 526 (Utah Supreme Court, 1972)
State Highway Department v. Wright Contracting Co.
131 S.E.2d 808 (Court of Appeals of Georgia, 1963)
Massachusetts Bonding & Insurance v. Bins & Equipment Co.
112 S.E.2d 626 (Court of Appeals of Georgia, 1959)