Biltmore Construction Co. v. Tri-State Electrical Contractors, Inc.

224 S.E.2d 487, 137 Ga. App. 504, 1976 Ga. App. LEXIS 2510
CourtCourt of Appeals of Georgia
DecidedFebruary 6, 1976
Docket51008
StatusPublished
Cited by15 cases

This text of 224 S.E.2d 487 (Biltmore Construction Co. v. Tri-State Electrical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Biltmore Construction Co. v. Tri-State Electrical Contractors, Inc., 224 S.E.2d 487, 137 Ga. App. 504, 1976 Ga. App. LEXIS 2510 (Ga. Ct. App. 1976).

Opinion

Pannell, Presiding Judge.

Tri-State Electrical Contractors, Inc., a subcontractor, brought an action against Biltmore Construction Company, Inc., the general contractor, seeking recovery of payment for the balance due under the contract and for certain changes or extras and materials and labor claimed required or authorized by the general contractor, and for attorney fees in the amount of $3,000, based on Code § 20-1404.

The dispute is over the changes or extras which are listed below, with the exception of the first two. Light *505 fixture change, $1,001; split service electrical entrance, $1,710.51; overtime labor charges, $1,217.56; sunlight fixture light stems change, $179.07; telephone service entrance, $1,002.31; standby labor, $4,195.24; punch list charge, $98.28; the alleged balance on the original contract, which was altered later by stipulation.

The defendant admitted liability for the light fixture change and the amount thereof and admitted liability for the split service change, and contested the amount thereof upon the trial, but does not contest it in this court after verdict. A verdict was directed as to the light fixture change of $1,001. Pursuant to instructions the jury rendered a special verdict which is as follows:

"1. We, the Jury, allow the Plaintiff the sum of $1,710.51 for 'split service’ change.
"2. Under the evidence and charge of this Court, did the parties by way of mutual intent of both, depart from the terms of the contract relating to the payment of 'extras’ as to all or any of the items outlined in Paragraph 3 below? Answer: Yes.
"3. If the above has been answered 'yes,’ we, the Jury, allow the following amounts as extras for the Plaintiff. $1,002.31 for 'telephone service’ change; $179.07 for 'light stems’ change; $98.28 for 'punchlist’ change; $1,217.56 for 'overtime’; $4,195.24 for 'standby’ time change.
"4. Under the evidence and charge of this Court, is Plaintiff entitled to attorney’s fees from defendant? Answer: Yes. If answer is yes, then in what amount? $3,500.00.”

The trial judge in entering judgment reduced the attorney fees from $3,500 to $3,000, the amount prayed for in the complaint; then reduced the amount of the verdict as to the contract changes and extras from $8,402.97 to $8,079.41 as prayed for in the plaintiffs last amendment. The only question on appeal presented by the enumerations of error is whether the jury’s finding Numbers 2 and 3 were authorized, there being exceptions to the refusal to direct a verdict as to these matters, the refusal to grant a new trial, the refusal to enter a judgment n.o.v.; and error on the charge of the court relating to the jury finding Number 2. Held:

*506 1. The jury finding Number 2 is substantially controlling as to some of the items listed in finding Number 3 and will be first considered.

It has long been the law of this state that the provisions of a building contract requiring a written change order before beginning work for which recovery is sought are valid and binding provisions. Heard v. Dooly County, 101 Ga. 619 (28 SE 986); Fin v. Carden, 100 Ga. App. 270 (110 SE2d 693); Bailey v. Martin, 101 Ga. App. 63 (112 SE2d 807); Anno. 66 ALR 649; Anno. 2 ALR3d 620. However, where the parties by a course of conduct have departed from the terms of the contract and operated without prior written change orders, there may be a waiver, or oral variation of the provisions of the contract. Id. See also State Hwy. Dept. v. Wright Contracting Co., 107 Ga. App. 758 (2) (131 SE2d 808); Mion Chemical Brick Corp. v. Daniel Const. Co., 111 Ga. App. 369 (141 SE2d 839); Clark v. Belleau, Inc., 114 Ga. App. 587 (2) (151 SE2d 894); Parker v. Brown House Co., 117 Ga. 1013, 1015 (44 SE 807). As was said in McDaniel v. Mallary Bros. Machinery Co., 6 Ga. App. 848 (66 SE 146): "Where a contract prescribes conditions precedent to a party’s right to set up a cause of action or defense, and the terms are reasonable, the opposite party may usually successfully plead a failure to comply with the conditions, as a reason for the court’s refusal to entertain the action or defense. But forfeiture of rights is not favored, and the courts will readily seize upon circumstances arising in the subsequent conduct or transactions of the parties and imply a waiver, in order to prevent a forfeiture because of non-compliance with formal prerequisites.” An examination of such conduct, as may be here involved, is therefore in order.

The complainant testified that prior to the beginning of any work on the contract, complainant was instructed by the executive vice president of the defendant to change the specifications and install a cheaper conduit in a concrete slab, which change was complied with.

There is testimony that the electrical service entrance change, not in controversy here, was ordered orally by the superintendent on the job for the defendant, and the work ordered started, which oral change order *507 was subsequently rendered in writing. This written change order however, was not given until estimates of the cost of the change were delivered to the defendant.

The complainant was told verbally by the superintendent to hold up on installing the light fixtures in the workroom because of a change in the light fixtures and the layout. The complainant notified the supplier to cancel the light fixture order. New and different light fixtures for a new layout were ordered by the general contractor and charged to the contract. It does not appear, however, whether the installation of the new fixtures was started before receiving the written change order. The new fixtures were more expensive than those originally specified in the contract and this was the basic difference. While this item is not in controversy on this appeal it is pertinent to the question being discussed.

The complainant was instructed by the superintendent to immediately go on overtime. The complainant complied with this oral order of the superintendent and subsequently received a ratification in writing, in the form of a telegram. There is evidence that this was done after the light fixture change and stem mix-up delayed the contract.

The new lighting fixtures came without the proper light stems from which to hang the lights. A change in this was ordered orally by the superintendent and complainant ordered and installed the new stems. This again raised the price of the light fixtures change. No additional written change order was ever issued as to the stems.

Complainant was instructed orally by the superintendent that he wanted certain standby labor on the job. Complainant complied with this order, but no written change order or approval or disapproval came from the general contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HANHAM v. ACCESS MANAGEMENT GROUP, LP
305 Ga. 414 (Supreme Court of Georgia, 2019)
Hanham v. Access Mgmt. Grp. L.P.
825 S.E.2d 217 (Supreme Court of Georgia, 2019)
RHL PROPERTIES, LLC v. Neese
668 S.E.2d 828 (Court of Appeals of Georgia, 2008)
Governor's Towne Club, Inc. v. Caffrey Construction Co.
614 S.E.2d 892 (Court of Appeals of Georgia, 2005)
Allgood Electric Co. v. Martin K. Eby Construction Co.
959 F. Supp. 1573 (M.D. Georgia, 1997)
Apac-Georgia, Inc. v. Department of Transportation
472 S.E.2d 97 (Court of Appeals of Georgia, 1996)
Caribbean Lumber Co. v. Anderson
422 S.E.2d 267 (Court of Appeals of Georgia, 1992)
Backus Cadillac-Pontiac, Inc. v. Brown
365 S.E.2d 540 (Court of Appeals of Georgia, 1988)
United States v. Centex Const. Co., Inc.
638 F. Supp. 411 (W.D. Virginia, 1985)
Pro Metal Building Systems, Inc. v. T. E. Driskell Grading Co.
316 S.E.2d 574 (Court of Appeals of Georgia, 1984)
Colonial Pipeline Co. v. Robert W. Hunt Co.
296 S.E.2d 633 (Court of Appeals of Georgia, 1982)
Jordan Bridge Co. v. I. S. Bailey, Jr., Inc.
296 S.E.2d 107 (Court of Appeals of Georgia, 1982)
Puritan Mills, Inc. v. Pickering Construction Co.
262 S.E.2d 586 (Court of Appeals of Georgia, 1979)
Daniel & Daniel, Inc. v. Stewart Brothers, Inc.
228 S.E.2d 586 (Court of Appeals of Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
224 S.E.2d 487, 137 Ga. App. 504, 1976 Ga. App. LEXIS 2510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/biltmore-construction-co-v-tri-state-electrical-contractors-inc-gactapp-1976.