Colonial Pipeline Co. v. Robert W. Hunt Co.

296 S.E.2d 633, 164 Ga. App. 91, 1982 Ga. App. LEXIS 2715
CourtCourt of Appeals of Georgia
DecidedOctober 22, 1982
Docket64620
StatusPublished
Cited by1 cases

This text of 296 S.E.2d 633 (Colonial Pipeline Co. v. Robert W. Hunt Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colonial Pipeline Co. v. Robert W. Hunt Co., 296 S.E.2d 633, 164 Ga. App. 91, 1982 Ga. App. LEXIS 2715 (Ga. Ct. App. 1982).

Opinion

Birdsong, Judge.

Robert W. Hunt Company, appellee, sued Colonial Pipeline Company, appellant, for monies due for pipe inspection services performed by Hunt for Colonial. Hunt, as an impartial third-party [92]*92inspector, agreed to inspect and did inspect specified foot lengths of pipeline being manufactured for Colonial by certain steel mills. The basis of Hunt’s complaint for monies owed was that the steel mills overran the scheduled or projected time required to produce Colonial’s pipeline, and thus more time was required for Hunt to inspect the pipeline during manufacture.

The essential facts of the written contractual agreement between Hunt and Colonial are these: Colonial submitted to Hunt an inquiry setting forth the specific jobs and pipeline lengths to be manufactured, and asking Hunt to “please quote prices firm through completion.” On this inquiry form, Hunt quoted the jobs on a cents “per foot” basis, and noted thereon: “Our attached letter proposal dated August 31,1979 forms an integral part of this quotation.” Hunt signed the inquiry document after placing its quotation thereon, under a printed statement that “[i]f favored by an order, we agree to furnish items enumerated hereon at prices and under conditions indicated. ” (Emphasis supplied.) The letter attached by Hunt to the inquiry form, stated: “Based on total number of production turns received by each mill for your 36-inch pipe, Hunt quotes the following for mill inspection:

MILL TOTAL PER MILL PRODUCTION
FEE FOOT HRS.
USS/McKeesport $14,186 6.6$ 288
Beth/Steelton 17,377 6.1 320
Kaiser/Napa 17,188 7.6 320”

Colonial replied with purchase orders which described the mill and footages of pipeline, and under the price column for each, stated only the cents-per-foot rates quoted by Hunt, just as Hunt had quoted on Colonial’s inquiry form, and stating, “prices firm through delivery.” Colonial’s purchase orders made no reference to the projected mill time schedule, which Hunt had incorporated as “an integral part of this quotation” by reference to its attached letter. After receiving Colonial’s purchase orders, Hunt, by reply letter, thanked Colonial for the assignments and in connection with requesting a correction on a two-cent error by Colonial, stated: “You will note our proposal is based on covering the mill scheduled number of turns for your order, therefore, the two cents per foot, although seemingly a small number, comes to 1.1 turns of coverage when extended over the total order.” During the jobs, Colonial and Hunt apparently orally negotiated and discussed an additional pipe loading inspection. Colonial issued a purchase order pricing the job at 1.11 cents per foot; while the job was proceeding, Hunt replied by letter: “Our verbal quote was based on [93]*93the girth-welding schedule of 23 days.” After the jobs were done, Hunt billed Colonial for the extra inspection time required by the mills’ overruns, calculating the reasonable value on a basis proportionate to the original cents-per-foot joh quote per scheduled mill production hours.

The trial judge denied Colonial’s motion for directed verdict and ultimately gave judgment to Hunt for the “extra and additional work which Colonial authorized and accepted.” On appeal Colonial excepts to these rulings and complains of errors inherent in them, as well as the admission of evidence that the custom in the trade required extra pay for extra inspection work required by mill overruns. Held:

Essentially, Colonial contends Hunt agreed to do the inspection jobs on a “per foot” basis and is not entitled to payment for extra time required to inspect the footage because of mill overruns. Colonial contends that if Hunt’s quotations were based on projected schedule time, they were nevertheless offers which Colonial counter-offered by its purchase orders stating only a “per foot” rate of compensation, which counter-offers Hunt accepted by its letter thanking Colonial for the assignments and merely requesting the two-cents error change.

Appellant Colonial Pipeline expounds the relative merits of the language of the documents, and of the documents as contract offers, counter-offers, variations, or acceptances, and in general expresses profound mystification that the trial court went outside the clear terms of the documents and received evidence of trade custom and usage, and on a quantum meruit basis granted judgment to Hunt for its extra-work claims. Hunt replies in kind. There are more facts in the case than we recite here, and many more arguments made, but we see no reason to explore them because they are immaterial to the interpretation of the parties’ agreement.

The cardinal rule of construction of a contract is to ascertain the intention of the parties. Brooke v. Phillips Petroleum Co., 113 Ga. App. 742, 744 (149 SE2d 511). Hunt says the extra pay for extra work is inherent in its quotations and in Colonial’s purchase orders. We think the language quoted from the documents in this case, particularly in light of the conflicting claims and positions of the parties arising therefrom, shows that the ultimate agreement was sufficiently ambiguous, latent and patent, so as to permit evidence in explanation thereof (Code Ann. § 20-704 (1)) and so as to permit evidence concerning the custom and usage in the trade. Biltmore Constr. Co. v. Tri-State Elect. Contractors, 137 Ga. App. 504, 508-509 (224 SE2d 487). The evidence shows that since third-party pipeline inspection during manufacture necessarily depends upon the [94]*94manufacturing (and perhaps re-manufacturing) process, the custom in the trade requires extra pay for extra inspection work necessitated by fault of the manufacturing process. We are not surprised that this is the custom in the trade because it makes such eminent good sense. In the face of the ambiguity of the documents comprising the agreement of the parties, the obligation to pay extra for extra work is of such compelling logic and is of such usual custom in the trade, as to be necessarily implied in the contract. Code Ann. § 20-704 (3).

Moreover, in determining whether Colonial’s purchase orders reciting only Hunt’s “per foot” price constituted a significant variation of Hunt’s quotation based on mill production hours so as to amount to a counter-offer accepted by Hunt, we look to paragraph 5 of Code Ann. § 20-704: “If the construction is doubtful, that which goes most strongly against the party executing the instrument, or undertaking the obligation, is generally to be preferred.” See also Brooke v. Phillips Petroleum Co., supra, where we held pursuant to Code Ann. § 20-704 (5) that “in cases of doubt, the contract will be construed most strongly against the one who prepared the instrument. [Cits.]” Hunt unambiguously quoted a “per foot” rate based on the individual mill’s scheduled production hours. If the inclusion of the mill’s production hours in the rate quoted has any significance, and as a basic rule of interpretation we presume that it does, it means that if the scheduled production hours were exceeded by the mill, the payment for inspection work would suffer some modification per the usual custom in the trade. In placing its quotation on Colonial’s inquiry form, Hunt itself quoted only the cents “per foot” rate, but by integration of its attached letter made it clear that this quotation was inherently based on scheduled production hours.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pottinger v. Cross
317 S.E.2d 850 (Court of Appeals of Georgia, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
296 S.E.2d 633, 164 Ga. App. 91, 1982 Ga. App. LEXIS 2715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/colonial-pipeline-co-v-robert-w-hunt-co-gactapp-1982.