Western Surety Company v. the State of Georgia Department of Transportation

CourtCourt of Appeals of Georgia
DecidedMarch 28, 2014
DocketA13A2157
StatusPublished

This text of Western Surety Company v. the State of Georgia Department of Transportation (Western Surety Company v. the State of Georgia Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Surety Company v. the State of Georgia Department of Transportation, (Ga. Ct. App. 2014).

Opinion

FIRST DIVISION PHIPPS, C. J., ELLINGTON, P. J., and BRANCH, J.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

March 28, 2014

In the Court of Appeals of Georgia A13A2157. WESTERN SURETY COMPANY et al. v. DEPARTMENT OF TRANSPORTATION.

PHIPPS, Chief Judge.

In this construction contract dispute, Western Surety Company and Continental

Casualty Company (the “Sureties”) appeal from the trial court’s grant of partial

summary judgment to defendant State of Georgia Department of Transportation (the

“DOT”) on the Sureties’ claims for breach of contract and violation of the Georgia

Prompt Payment Act (the “PPA”).1 The Sureties contend that the trial court erred in

entering partial summary judgment because there remain genuine issues of material

fact. For the reasons set forth below, we disagree and affirm.

1 OCGA § 13-11-1 et seq. Summary judgment is warranted when the moving party shows that there is “no

genuine issue of material fact and that the movant is entitled to judgment as a matter

of law.”2 A defendant may meet this burden by demonstrating that “the documents,

affidavits, depositions and other evidence in the record reveal that there is no

evidence sufficient to create a jury issue on at least one essential element of the

plaintiff’s case.”3 And when the moving party discharges this burden, “the nonmoving

party cannot rest on its pleadings, but must point to specific evidence giving rise to

a triable issue.”4 We review a grant or denial of summary judgment de novo and

construe the evidence in the light most favorable to the nonmovant.5

So viewed, the record shows that the DOT and Bruce Albea Contracting, Inc.

(“BAC”) entered into a construction contract (the “Contract”) for work on roadway

US 27 (the “Project”). The Sureties issued performance and payment bonds to the

2 Bd. of Commrs. of Putnam County v. Barefoot, 313 Ga. App. 406, 408 (721 SE2d 612) (2011) (punctuation omitted). 3 Id. (punctuation omitted). 4 Id. (punctuation omitted). 5 Home Builders Assn. of Savannah v. Chatham County, 276 Ga. 243, 245 (1) (577 SE2d 564) (2003).

2 DOT, as obligee. The completion date for the Project was originally March 31, 2007,

but was extended to January 18, 2008.

After BAC entered into the Contract, it experienced an increase in material

costs for the Project. As a consequence of the increase in material prices, particularly

for asphalt and other petroleum-related products, BAC suffered financial difficulties.

In December 2006, BAC notified the Sureties of the problem.

Rather than allow the Project to “grind to a halt,” the Sureties provided funds

to BAC between April and July of 2007. In exchange for their help with the Project,

BAC provided the Sureties with a letter from BAC to DOT, dated April 18, 2007,

stating that BAC could not perform the work and was voluntarily abandoning the

Contract. The letter was received by DOT in late June 2007, and DOT placed BAC

in default and directed the Sureties to take over the work on the Project.

On September 11, 2007, the Sureties sent two claim letters to the DOT. After

a meeting, the DOT asked for additional information. The Sureties chose not to

respond to the DOT’s request and subsequently sued the DOT, setting forth three

counts of breach of contract6 and one count of violation of the PPA. The DOT moved

6 Although it does not appear that the Sureties were parties to the Contract, we have found that in a breach of contract action “a subrogee stepping into the shoes of [a government contractor], may rely upon the waiver of sovereign immunity that

3 for partial summary judgment on the Sureties’ claims for: (i) compensation for price

inflation incurred after March 31, 2007 (the “Original Completion Date”) (“Count

II”); (ii) compensation for price inflation incurred before the Original Completion

Date (“Count III”); and (iii) violation of the PPA.7 The trial court granted the DOT’s

motion for partial summary judgment. On appeal, the Sureties contend that the trial

court erred in granting summary judgment on Count II and Count III because they did

not waive their claims against the DOT by failing to strictly comply with the

Contract’s notice and claim provisions.8 The Sureties also contend that the trial court

erred by finding that they are barred from recovering attorney fees under the PPA.

applied to the government contractor.” State Dept. of Corrections v. Developers Sur. & Indem. Co., 324 Ga. App. 371, 376 (1) (750 SE2d 697) (2013) (Cert. granted State Dept. of Corrections v. Developers Sur. & Indem. Co., 2014 Ga. LEXIS 207 (Mar. 3, 2014)). 7 The DOT’s motion for summary judgment did not encompass Count I of the Sureties’ complaint, which set forth a claim for the alleged outstanding balance for work performed. 8 Although we do not reach these issues, the Sureties also contend that the trial court erred to the extent it determined that supplementary agreements to the Contract acted as accords and satisfactions, to the extent it found utility-related delays were not compensable, and to the extent it found that the breach of contract claims were disguised equity claims. They acknowledge, however, that “the argument relative to notice would theoretically apply to all of the Sureties’ claims.”

4 1. The Sureties acknowledge that neither BAC nor the Sureties strictly

followed the claim notice requirements set forth under the Contract, particularly

Specification 105.13. Specification 105.13.B.9 provides:

NOTICE OF POTENTIAL CLAIM: In any case in which the Contractor believes that it will be entitled to additional compensation, the Contractor shall notify the Engineer in writing of its intent to claim such additional compensation. Such notice shall be given in order that the Department can assess the situation, make an initial determination as to who is responsible, and institute appropriate changes or procedures to resolve the matter.

a. Claims for Delay– The Department shall have no liability for any delay which occurred more than one week prior to the filing of such written notice. Failure of the Contractor to give such written notice in a timely fashion will be grounds for denial of the claim.

b. All Other Claims Except Acceleration and Delay– If the Contractor does not file such written notice before beginning the work out of which such claim arises, then the Contractor hereby agrees that it shall have waived any additional compensation for that work and the Contractor shall have no claim thereto.9

9 The damages which the Sureties claim appear to be primarily associated with delay. However, the Sureties’ representative acknowledged that it was not clear whether claims for material price increases before the Original Completion Date were a “delay” or “other” claim for purposes of the Contract, although it “seemed more like

5 In submitting a claim, the Contractor is also required to provide certain information,

as set forth in Specification 105.13.C, and to certify the claim, as required by

Specification 105.13.D.

Further, under Specification 105.13.B.6.b, recoverable damages under the

Contract include “[d]ocumented additional costs for materials.” The parties also

agreed under Specification 105.13.B.5, however, that “[c]ompliance with the

provisions of this Subsection will be an essential condition precedent to any recovery

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rice v. Lost Mountain Homeowners Assoc.
604 S.E.2d 215 (Court of Appeals of Georgia, 2004)
Ramsey v. Langley
71 S.E.2d 863 (Court of Appeals of Georgia, 1952)
Home Builders Ass'n of Savannah, Inc. v. Chatham County
577 S.E.2d 564 (Supreme Court of Georgia, 2003)
Department of Transportation v. Fru-Con Construction Corp.
426 S.E.2d 905 (Court of Appeals of Georgia, 1992)
State Highway Department v. Hewitt Contracting Co.
149 S.E.2d 499 (Court of Appeals of Georgia, 1966)
State Highway Department v. Hall Paving Co.
194 S.E.2d 493 (Court of Appeals of Georgia, 1972)
State Highway Department v. Wright Contracting Co.
131 S.E.2d 808 (Court of Appeals of Georgia, 1963)
Apac-Georgia, Inc. v. Department of Transportation
472 S.E.2d 97 (Court of Appeals of Georgia, 1996)
Department of Transportation v. Dalton Paving & Construction, Inc.
489 S.E.2d 329 (Court of Appeals of Georgia, 1997)
AAF-McQuay, Inc. v. Willis
707 S.E.2d 508 (Court of Appeals of Georgia, 2011)
Allgood Electric Co. v. Martin K. Eby Construction Co.
959 F. Supp. 1573 (M.D. Georgia, 1997)
BD. OF COM'RS OF PUTNAM COUNTY v. Barefoot
721 S.E.2d 612 (Court of Appeals of Georgia, 2011)
State v. Developers Surety & Indemnity Co.
750 S.E.2d 697 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Western Surety Company v. the State of Georgia Department of Transportation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-surety-company-v-the-state-of-georgia-department-of-transportation-gactapp-2014.