§ 13-11-7 — Interest on late payments

Georgia·Title 13
(a)Except as provided in Code Section 13-11-5 , if a periodic or final payment to a contractor is delayed by more than 15 days or if a periodic or final payment to a subcontractor is delayed more than ten days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor, as the case may be, shall pay his or her contractor or subcontractor interest, beginning on the day following the due date, at the rate of 1 percent per month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provision of this Code section at the time the request for payment is made. Acceptance of progress payments or final payment shall release all claim

Free access — add to your briefcase to read the full text and ask questions with AI

Georgia § 13-11-7 (Interest on late payments) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Atlanta v. Hogan Construction Group, LLC
801 S.E.2d 606 (Court of Appeals of Georgia, 2017)
2 case citations
Western Surety Co. v. Department of Transportation
757 S.E.2d 272 (Court of Appeals of Georgia, 2014)
2 case citations