Fatt Katt Enterprises, Inc. v. Rigsby Construction, Inc.

Court of Appeals for the Eleventh Circuit·Decided February 27, 2019·No. 18-11182·Unpublished

Opinion

[DO NOT PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT

No. 18-11182

Non-Argument Calendar

D.C. Docket No. 1:16-cv-00952-LMM

FATT KATT ENTERPRISES, INC., d.b.a. Granite Transformations of Atlanta,

Plaintiff - Counter

Defendant - Appellant,

versus

RIGSBY CONSTRUCTION, INC., d.b.a. Artisan Design & Construction Group,

Defendant - Counter

Claimant - Appellee.

Appeal from the United States District Court for the Northern District of Georgia

(February 27, 2019)

Before WILSON, WILLIAM PRYOR, and ANDERSON, Circuit Judges.

PER CURIAM:

Fatt Katt Enterprises d/b/a/ Granite Transformations of Atlanta (Fatt Katt)

sued Rigsby Construction, Inc. d/b/a Artisan Design and Construction Group (Rigsby), asserting claims including (1) breach of contract and (2) violation of Georgia’s Prompt Pay Act, O.C.G.A. § 13-11-1, et. seq., and seeking damages for work that Fatt Katt allegedly performed. Rigsby answered and filed counterclaims against Fatt Katt for breach of contract. The district court granted Rigsby’s motion for a directed verdict on Fatt Katt’s Prompt Pay Act claim based on O.C.G.A. § 13- 11-4(b), a default statutory rule governing the timing of payments between contractors and subcontractors. Rigsby sought and obtained attorney’s fees as the “prevailing party” in the action under O.C.G.A. § 13-11-8. Fatt Katt now appeals the directed verdict and award of attorney’s fees.

Fatt Katt first contends that the district court misinterpreted the Georgia Prompt Pay Act in granting a directed verdict to Rigsby by ignoring a provision in the Act that allowed the parties to negotiate payment terms that would control in lieu of O.C.G.A. § 13-11-4(b). Fatt Katt also argues that the district court erred in awarding attorney’s fees to Rigsby under the Prompt Pay Act because Rigsby was not a “prevailing party” insofar as it did not obtain any relief at trial. We affirm.

I. Factual and Procedural Background This case arises from a construction dispute between a general contractor,

Rigsby, and one of its subcontractors, Fatt Katt. Seeking damages for work it allegedly performed in constructing a hotel, Fatt Katt sued Rigsby for breach of contract, unjust enrichment, quantum meruit, and violation of Georgia’s Prompt Pay Act, O.C.G.A. § 13-11-1, et. seq. (Prompt Pay Act). Rigsby answered and filed counterclaims for breach of contract and a declaratory judgment related to a mechanics’ lien that Fatt Katt recorded against the property.

Before the jury considered any issues, the district court granted Rigsby’s motion for a directed verdict on Fatt Katt’s Prompt Pay Act claim. The court reasoned that O.C.G.A. § 13-11-4(b), a default statutory rule governing the timing of payment in construction contracts, only required a contractor to pay its subcontractors after receiving payment from the property owner in a contract. Because there was no evidence that the hotel owner had ever paid Rigsby for Fatt Katt’s alleged work, O.C.G.A. § 13-11-4(b) barred Fatt Katt’s claims. Fatt Katt argued that it had an oral agreement with Rigsby that, under O.C.G.A. § 13-11- 7(b), superseded the language of O.C.G.A. § 13-11-4(b). The district court rejected this argument.

A jury considered the remaining issues, finding for Rigsby on Fatt Katt’s breach of contract claim. On Rigsby’s counterclaim, the jury found that Fatt Katt had breached the contract, but did not award any monetary damages. Rigsby filed a Bill of Costs and Motion for Attorney’s Fees as the “prevailing party” under Rule

54(d) of the Federal Rules of Civil Procedure and O.C.G.A. § 13-11-8. Fatt Katt opposed the Motion for Attorney’s Fees and filed a Motion to Amend Final Judgment, arguing that Rigsby was not the “prevailing party” in the action. The district court denied this Motion to Amend and granted, in part, Rigsby’s Motion for Attorney’s Fees. Fatt Katt now appeals the directed verdict and the order granting attorney’s fees to Rigsby under the Prompt Pay Act.

II. Directed Verdict

We review a district court’s grant of a directed verdict de novo. Wilcox v.

Corr. Corp. of Am., 892 F.3d 1283, 1286 (11th Cir. 2018). We apply the same standard of review as the district court. Miles v. Tenn. River Pulp & Paper Co., 862 F.2d 1525, 1527–28 (11th Cir. 1989). We view the evidence and draw all reasonable inferences in the light most favorable to the nonmoving party, Moore v. Appliance Direct, Inc., 708 F.3d 1233, 1237 (11th Cir. 2013), and affirm only if “a reasonable jury would not have a legally sufficient evidentiary basis to find” for the nonmoving party, Wilcox, 892 F.3d at 1286 (internal quotation marks omitted).

We will not reverse a district court decision if the court’s error is harmless.

To determine whether an error is harmless, we ask “whether the complaining party’s substantive rights were affected.” Goldsmith v. Bagby Elevator Co., 513 F.3d 1261, 1276 (11th Cir. 2008).

Section 4(b) of the Georgia Prompt Pay Act states:

When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor . . . within ten days of receipt by the contractor . . . of each periodic or final payment, the full amount received for such subcontractor’s work and materials based on work completed or service provided under the subcontract . . . .

GA. CODE ANN. § 13-11-4(b) (West). This section suggests that a contractor must receive payment from the property owner before paying a subcontractor for work performed “in accordance with the provisions of its subcontract.” That is, payment to the contractor is a condition precedent to the contractor’s duty to pay the subcontractor. The district court determined that the property owner did not pay Rigsby for the amount Fatt Katt demanded under the Act, and thus Fatt Katt’s claim did not satisfy the requirements of O.C.G.A. § 13-11-4(b).

Section 13-11-7(b) of the Prompt Pay Act provides that “[n]othing in this chapter shall prohibit owners, contractors, and subcontractors from agreeing by contract to rates of interest, payment periods, and contract and subcontract terms different from those stipulated in this Code section, and in this event, these contractual provisions shall control.” GA. CODE ANN. § 13-11-7(b) (West). Where the Prompt Pay Act clearly states that it does not apply to certain claims, Georgia courts have followed the plain language of the statute. See, e.g., City of Atlanta v. Hogan Constr. Grp., LLC, 801 S.E.2d 606, 610–11 (Ga. Ct. App. 2017) (citing Pipe Sols., Inc. v. Inglis, 661 S.E.2d 683, 686 (Ga. Ct. App. 2008)).

Fatt Katt alleges that it entered into an oral agreement with Rigsby regarding the timing of progress payments, and the terms of its agreement should control under O.C.G.A § 13-11-7(b) and City of Atlanta. Fatt Katt asserts that Rigsby “agreed to pay all invoices received upon receipt,” and since this agreement controls, O.C.G.A. § 13-11-4(b) does not apply and Fatt Katt’s Prompt Pay Act claim is not be barred.

The district court determined that O.C.G.A. § 13-11-7(b) did not apply to Fatt Katt’s claim; instead, the court focused on O.C.G.A. § 13-11-4(b). Basing its conclusions on the requirements in § 13-11-4(b), the court stated that it did not “find anything in the record” to support Fatt Katt’s Prompt Pay Act claim, because Rigsby did not receive payment from the hotel owner prior to Fatt Katt’s demand for payment.

The district court properly applied the Georgia Prompt Pay Act. Section 13-

Free access — add to your briefcase to read the full text and ask questions with AI

Fatt Katt Enterprises, Inc. v. Rigsby Construction, Inc., (11th Cir. 2019).

Fatt Katt Enterprises, Inc. v. Rigsby Construction, Inc. (Fatt Katt Enterprises, Inc. v. Rigsby Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Loggerhead Turtle v. County Council of Volusia County
307 F.3d 1318 (Eleventh Circuit, 2002)
Goldsmith v. Bagby Elevator Co., Inc.
513 F.3d 1261 (Eleventh Circuit, 2008)
Clark v. Riley
595 F.3d 1258 (Eleventh Circuit, 2010)
Leonard Moore v. Appliance Direct,Inc.
708 F.3d 1233 (Eleventh Circuit, 2013)
Magnetic Resonance Plus, Inc. v. Imaging Systems International
543 S.E.2d 32 (Supreme Court of Georgia, 2001)
Smith v. Baptiste
694 S.E.2d 83 (Supreme Court of Georgia, 2010)
Pipe Solutions, Inc. v. Inglis
661 S.E.2d 683 (Court of Appeals of Georgia, 2008)
City of Atlanta v. Hogan Construction Group, LLC
801 S.E.2d 606 (Court of Appeals of Georgia, 2017)
Felicia A. Wilcox v. Corrections Corporation of America
892 F.3d 1283 (Eleventh Circuit, 2018)
Benchmark Builders, Inc. v. Schultz
751 S.E.2d 45 (Supreme Court of Georgia, 2013)