Georgia Statutes

§ 13-11-4 — Time limits for payments to contractors and subcontractors

Georgia § 13-11-4

This text of Georgia § 13-11-4 (Time limits for payments to contractors and subcontractors) is published on Counsel Stack Legal Research, covering Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O.C.G.A. § 13-11-4 (2026).

Text

(a)When a contractor has performed in accordance with the provisions of a contract, the owner shall pay the contractor within 15 days of receipt by the owner or the owner's representative of any payment request based upon work completed or service provided under the contract.
(b)When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor and each subcontractor shall pay to its subcontractor, within ten days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor's work and materials based on work completed or service provided under the subcontract, provided that the subc

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Atlanta v. Hogan Construction Group, LLC
801 S.E.2d 606 (Court of Appeals of Georgia, 2017)
2 case citations
Western Surety Co. v. Department of Transportation
757 S.E.2d 272 (Court of Appeals of Georgia, 2014)
2 case citations

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Georgia § 13-11-4, Counsel Stack Legal Research, https://law.counselstack.com/statute/ga/13-11-4.