State v. Developers Surety & Indemnity Co.

750 S.E.2d 697, 324 Ga. App. 371, 2013 Fulton County D. Rep. 3366, 2013 WL 5779779, 2013 Ga. App. LEXIS 847
CourtCourt of Appeals of Georgia
DecidedOctober 28, 2013
DocketA13A0969
StatusPublished
Cited by13 cases

This text of 750 S.E.2d 697 (State v. Developers Surety & Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State v. Developers Surety & Indemnity Co., 750 S.E.2d 697, 324 Ga. App. 371, 2013 Fulton County D. Rep. 3366, 2013 WL 5779779, 2013 Ga. App. LEXIS 847 (Ga. Ct. App. 2013).

Opinion

Ray, Judge.

This case stems from a construction contract entered between the Georgia Department of Corrections (“GDOC”) and Lewis Walker Roofing (‘Walker Roofing”) for the purpose of re-roofing certain buildings at the Valdosta State Prison. After a nearly two-year-long delay in completing the project, GDOC declared the contract in default, and the payment and performance bonds issued by Developers Surety and Indemnity Company (“Developers Surety”) for the benefit of GDOC as obligee were invoked. Developers Surety then filed the present suit against GDOC, alleging that GDOC breached [372]*372the construction contract it entered into with Walker Roofing. Developers Surety also sought a declaratory judgment that, as a result of GDOC’s breach of the construction contract, it had no obligation to perform its obligations under the payment and performance bond it issued to Walker Roofing on behalf of GDOC. GDOC filed a counterclaim for breach of contract. Both parties filed cross-motions for summary judgment. In its motion for summary judgment, GDOC argued that the doctrine of sovereign immunity barred Developers Surety’s claims against it. GDOC appeals from the trial court’s order granting Developers Surety’s summary judgment motion and denying GDOC’s summary judgment motion. Finding no error, we affirm .

On appeal from the grant or denial of a motion for summary judgment, “this Court conducts a de novo review of the evidence to determine whether there is a genuine issue of material fact and whether the undisputed facts, viewed in the light most favorable to the nonmoving party, warrant judgment as a matter of law.” (Citation omitted.) Shekhawat v. Jones, 293 Ga. 468 (746 SE2d 89) (2013).

So viewed, the relevant evidence shows as follows. On April 25, 2008, GDOC posted an “Invitation to Bid” for a construction project that involved replacing the roofs on several buildings located at the Valdosta State Prison. On June 12, 2008, GDOC awarded the project to Walker Roofing. The construction contract between GDOC and Walker Roofing included two “no assignment” clauses prohibiting Walker Roofing from assigning its performance or right to payment under the contract.

As a prerequisite to contracting with GDOC, Walker Roofing was required to obtain payment and performance bonds that would assure its performance under the contract. Developers Surety issued payment and performance bonds to Walker Roofing. Walker Roofing and Developers Surety had previously signed a general agreement of indemnity in favor of Developers Surety that included a provision in which Walker Roofing assigned to Developers Surety the company’s right to payment under bonded contracts as security against any losses that Developers Surety might suffer under a bond. GDOC is not a party to the indemnity agreement. The bonds required Developers Surety, upon default of Walker Roofing, to “promptly remedy the default or defaults or to promptly perform the [cjontract in accordance with its terms and conditions.” It also required Developers Surety to give GDOC notice “within twenty-five (25) days after receipt of a declaration of default of the surety’s election either to remedy the default or defaults promptly or to perform the contract promptly.”

Walker Roofing began work at the Valdosta State Prison on December 1, 2008. Pursuant to its construction contract, Walker [373]*373Roofing was required to complete its work within 150 consecutive calendar days; however, the work was not completed as of September 23, 2010, when GDOC declared Walker Roofing in default. The contract between Walker Roofing and GDOC states that Walker Roofing shall have access to work areas on weekdays between 7:30 a.m. and 5:00 p.m. However, Walker Roofing’s daily start time was delayed by at least thirty minutes and up to two-and-a-half hours because the workers experienced difficulties gaining access to the prison grounds. GDOC additionally required Walker Roofing to have their equipment properly secured and the roofers off the project site by 4:30 p.m., not 5:00 p.m. as per the contract. To exit the project site and secure their equipment by 4:30 p.m., however, the roofing crew had to stop work at 3:30 p.m. Work was further delayed because Walker Roofing was prohibited from accessing more than one roof at a time, GDOC assigned only one prison guard to monitor the roofing crew, and work was not permitted when the assigned guard was unavailable due to sickness or vacation time.

On September 23, 2010, GDOC issued a formal notice of default with respect to the performance of Walker Roofing, thus triggering Developers Surety’s obligations under the performance bond. Developers Surety did not notify GDOC within 25 days of receipt of GDOC’s notice of default regarding whether it would remedy the default or perform the contract. However, on January 12, 2011, approximately three months after the declaration of default, Developers Surety offered to GDOC that it “could enter into a contract with Skyline for the completion of the work on the Project (this process being sometime known as a ‘tender of completion contractors’).” GDOC then contracted with Skyline to complete the project. Prior to Walker Roofing’s default, Developers Surety had provided financial assistance to Walker Roofing under the payment and performance bonds in the amount of $577,118.60, and it additionally incurred $160,161.39 in costs and attorney fees arising from its investigation of its liability, if any, under the default.

On July 12, 2011, Developers Surety filed the present complaint against GDOC for breach of contract and for a declaratory judgment that it had no obligation under the payment and performance bond it issued to Walker Roofing on behalf of GDOC. The parties filed cross-motions for summary judgment. After a hearing, the trial court found that Developers Surety’s claims were not barred by sovereign immunity and that GDOC had breached the construction contract as a matter of law. Thus, it granted Developers Surety’s motion for summary judgment and denied GDOC’s motion for summary judg[374]*374ment. In the same order, the trial court entered a judgment in favor of Developers Surety in the amount of $577,118.60.1 GDOC appeals from that order.

1. GDOC contends that the trial court’s denial of its summary judgment motion was in error because Developers Surety was not a party to the construction contract between GDOC and Walker Roofing and, thus, that the State’s waiver of sovereign immunity for breach of contract did not apply to Developers Surety. We disagree.

“ [Sovereign immunity is a threshold issue that the trial court [is] required to address before reaching the merits of any other argument.” (Footnote omitted.) Albertson v. City of Jesup, 312 Ga. App. 246, 248 (1) (718 SE2d 4) (2011). It is axiomatic that “[t]he party seeking to benefit from the waiver of sovereign immunity bears the burden of proving such waiver.” (Citations omitted.) Bd. of Regents of the Univ. System of Ga. v. Doe, 278 Ga. App. 878, 881 (1) (630 SE2d 85) (2006). It is also well settled that “the sovereign cannot be sued in its own courts, or in any other court, without its consent and permission; but it may, if it thinks proper, waive this privilege, and permit itself to be made a defendant in a suit by individuals.” (Punctuation and footnotes omitted.) DeKalb County School Dist. v. Gold, 318 Ga. App. 633, 636 (1) (734 SE2d 466) (2012).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fulton County, Georgia v. Soco Contracting Company, Inc.
808 S.E.2d 891 (Court of Appeals of Georgia, 2017)
Marketta Howard v. Ronald Leonard
Court of Appeals of Georgia, 2014
Michael Houston v. Rebecka S. Flory
Court of Appeals of Georgia, 2014
Howard v. Leonard
765 S.E.2d 466 (Court of Appeals of Georgia, 2014)
Houston v. Flory
766 S.E.2d 227 (Court of Appeals of Georgia, 2014)
Gonzalez v. Georgia Department of Transportation
764 S.E.2d 462 (Court of Appeals of Georgia, 2014)
Western Surety Co. v. Department of Transportation
757 S.E.2d 272 (Court of Appeals of Georgia, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
750 S.E.2d 697, 324 Ga. App. 371, 2013 Fulton County D. Rep. 3366, 2013 WL 5779779, 2013 Ga. App. LEXIS 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-v-developers-surety-indemnity-co-gactapp-2013.