Jahncke Service, Inc. v. Department of Transportation

322 S.E.2d 505, 172 Ga. App. 215, 1984 Ga. App. LEXIS 2464
CourtCourt of Appeals of Georgia
DecidedSeptember 10, 1984
Docket68959
StatusPublished
Cited by8 cases

This text of 322 S.E.2d 505 (Jahncke Service, Inc. v. Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jahncke Service, Inc. v. Department of Transportation, 322 S.E.2d 505, 172 Ga. App. 215, 1984 Ga. App. LEXIS 2464 (Ga. Ct. App. 1984).

Opinion

Deen, Presiding Judge.

Appellants Jahncke Service, Inc., and T. L. James & Co. (hereinafter collectively referred to as “contractor” or “contractors”) entered into a contract in August 1971 with the State Highway Department (now known as the Department of Transportation and hereinafter referred to as DOT) for construction of 6.61 miles of highway embankment on Interstate 95 in Camden County, Georgia. Prior to bidding on the contract the appellants, along with other potential bidders, had been supplied with, inter alia, a report (“boring report” or “borrow pit report”) on DOT’s investigation of possible borrow pits from which materials for use in building the embankment could be obtained. DOT also obtained permission of the pits’ owners for them to be used for that purpose and, additionally, obtained dredging permits from the U. S. Corps of Engineers. The boring report, which listed results of tests of the three pits, contained a clear and conspicuous statement that the results of the tests were not guaranteed, and an admonition to potential bidders that they needed to make their own tests before submitting a bid, or “proposal.”

The contract between the two parties, DOT and the successful bidders (appellants here), consisted of the following documents: (1) Notice to Contractors; (2) the contractor’s proposal, Special Provisions, Supplemental Specifications, Performance and Payment Bonds, the formal contract between DOT and appellants executed August 31, 1971, and documents contained in a bound volume entitled “State Highway Department of Georgia — Proposal”; (3) Standard Specifications of the State Highway Department of Georgia for the Construction of Roads and Bridges, January 1966, vols. 1 and 2; and (4) highway construction engineering plans, entitled “Plan and Profile of Proposed Jacksonville, Florida-Brunswick, Georgia, Interstate Road Construction Contract.” The boring report bore on its face a statement that it was not part of the contract. As is customary in highway, construction work, payment was to be made on a “unit/price” basis; that is, for a specified price per cubic yard, the contractors were to do all work necessary or incidental to performance of each unit of work.

Appellants assert that after work had gotten under way, the largest of the three borrow pits, which according to the boring report seemed capable of providing the major portion if not all of the required fill, did not produce adequate material of a quality acceptable *216 to DOT. Appellants further allege that DOT arbitrarily classified as unacceptable material which its boring report had indicated would meet the applicable standards. Consequently, appellants allege, they were forced to dig the pits to greater depths than they had anticipated, thereby allegedly incurring additional expense. Moreover, instead of the largest pit supplying all the materials needed (as the contractors apparently expected), appellants had to use material from both the remaining pits in order to obtain an adequate supply for the embankment. This process allegedly began in April of 1971; appellants did not bring it to DOT’s attention, however, until late July of that year, when a letter to the State Highway Engineer from appellants set forth their claim for additional compensation. Other letters in the same vein were written the following August and October. DOT refused to consider this as “extra work” or as an alteration in the character of the work involving “a substantial change in the nature of the design or in the type of construction” which “materially increase [d] the cost of the performance,” as defined in the Standard Specifications, §§ 4.03, 4.04. Therefore, under the contractual documents, DOT declined to authorize additional payment for this work.

Upon completion of the work contracted for, appellants filed a written claim for additional compensation for expenses incurred as a result of encountering unforeseen conditions during the construction process. DOT sought a declaratory judgment in. the Fulton Superior Court as to the validity of the claim for additional compensation and subsequently moved for summary judgment. 1 See Jahncke Service v. Dept. of Transp., 137 Ga. App. 179 (223 SE2d 228) (1976); Jahncke Service v. Dept. of Transp., 134 Ga. App. 106 (213 SE2d 150) (1975). In November 1983 the court granted summary judgment to DOT. Jahncke and James appeal, enumerating as error this award of judgment, on the basis that there exist genuine issues of material fact which preclude summary adjudication. Held:

1. Provisions of the contract and related documents which are of particular significance to our review of the case at bar can be summarized in the following excerpts:

“Whenever an alteration in character of work involves a substantial change in the nature of the design or in the type of construction, a Change Order covering such alteration will be issued ... If the alteration materially increases or decreases the cost of the performance, a Supplemental Agreement acceptable to both parties shall be executed before work is started on such alteration ... In all other cases the work involved in all changes shall be performed on the basis of *217 the Contract unit price and no Supplemental Agreement will be necessary.” (Standard Specifications § 4.03A.)

“Extra work as defined in Section 1 herein shall be done by the Contractor in accordance with the Specifications and as directed, provided that, before any extra work is begun, a Supplemental Agreement or an Extension Agreement shall be signed by both contracting parties . . . No work performed by the Contractor shall be determined to be Extra work until it has been approved in writing by the State Highway Engineer . . . The Contractor shall waste or avoid any plastic clay strata or pockets, or other material not meeting the requirements for In Place Embankment. There shall be no payment for excavation and wasting of such material, either from sources shown on the plans or from those submitted by the Contractor.” (Standard Specifications § 4.04.)

“A. Engineer’s Decision and Estimates Final: The Engineer will decide promptly all questions related to the interpretation of the Specifications and the Plans and as to the acceptable fulfillment of the Contract by the Contractor . . . B. Engineer to Interpret Documents: Any doubt as to the meaning of the Contract, Plans or Specifications and any obscurity as to the work required under the Contract, Plans and Specifications will be explained by the Engineer.” (Standard Specifications § 5.01A.)

“Contract Plans, furnished by the Department, consisting of general drawings and showing such details as are necessary to give a comprehensive idea of the construction contemplated, will be prepared by or under the direction of the Department . . . Data shown on such plans are not guaranteed to be correct; and the obligation is upon the Contractor, before making his Bid or Proposal, to make his own investigation. B. . . . [T]he Department does not guarantee that the information shown on the plans is correct, and the Department will not be bound thereby; therefore, before making his bid and submitting his proposal, the Contractor shall satisfy himself as to such conditions, materials, and structures existing on the project as is specified in Articles 2.05 and 2.06.” (Standard Specifications § 5.03A.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan v. City of Cotter
2009 Ark. 457 (Supreme Court of Arkansas, 2009)
Handex of Florida, Inc. v. Chatham County
602 S.E.2d 660 (Court of Appeals of Georgia, 2004)
Atlantic Wood Industries, Inc. v. Lumbermen's Underwriting Alliance
396 S.E.2d 541 (Court of Appeals of Georgia, 1990)
Pinkerton and Laws Co., Inc. v. Roadway Exp., Inc.
650 F. Supp. 1138 (N.D. Georgia, 1986)
Roberts v. Grigsby
339 S.E.2d 633 (Court of Appeals of Georgia, 1985)
Butler v. Terminix International, Inc.
334 S.E.2d 865 (Court of Appeals of Georgia, 1985)
Anderberg v. Georgia Electric Membership Corp.
332 S.E.2d 326 (Court of Appeals of Georgia, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
322 S.E.2d 505, 172 Ga. App. 215, 1984 Ga. App. LEXIS 2464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jahncke-service-inc-v-department-of-transportation-gactapp-1984.