Handex of Florida, Inc. v. Chatham County

602 S.E.2d 660, 268 Ga. 285, 268 Ga. App. 285, 2004 Fulton County D. Rep. 2242, 2004 Ga. App. LEXIS 890
CourtCourt of Appeals of Georgia
DecidedJuly 1, 2004
DocketA04A0727
StatusPublished
Cited by6 cases

This text of 602 S.E.2d 660 (Handex of Florida, Inc. v. Chatham County) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Handex of Florida, Inc. v. Chatham County, 602 S.E.2d 660, 268 Ga. 285, 268 Ga. App. 285, 2004 Fulton County D. Rep. 2242, 2004 Ga. App. LEXIS 890 (Ga. Ct. App. 2004).

Opinion

Adams, Judge.

In late 1999 Chatham County advertised for public bids to relocate portions of the Bacon Park Landfill (the Project). Handex of Florida, Inc. was the successful bidder on the Project, and Handex 1 and the County entered into a Construction Services Contract (the Contract) in February 2000. Under the terms of the Contract, Handex was to excavate and dispose of waste from portions of the landfill and to replace the excavated waste with granular backfill. All work under the Contract was to be done in accordance with the specifications and plans which were provided by the County and which were incorporated into the Contract. Payment for the excavated material was determined under Section 1.07 (B) (3) of the Contract and was based upon the volume of waste removed as determined by comparison topographic/planimetric surveys conducted at the beginning and completion of the Project. Handex was responsible for hiring the surveyor to perform the surveys.

Handex entered into a subcontract with Waste Management of Georgia, Inc. pursuant to which Waste Management was to relocate the nonhazardous material from the landfill and provide granular fill material for the Project. Waste Management’s performance under its agreement with Handex is not at issue in this appeal.

At some point during the project, Handex notified the County that the survey performed by its surveyor may have been inaccurate. *286 The County hired an independent engineering firm to confirm the surveys. On March 27, 2000, Handex and the County met (the Preconstruction conference) and agreed that interim payments made during the Project would be based on the “truck count method.” 2 However, according to the minutes from that meeting, final payment “may be adjusted to reflect actual volumes as determined by land survey.”

Waste Management subsequently brought suit against Handex and The Insurance Company of the State of Pennsylvania (the Surety), contending that Handex had failed to pay it for the work performed on the Project in accordance with the subcontract and the payment bond. Handex answered, relying in part on the defense that the subcontract with Waste Management contained a “pay when paid” clause, which provided that Handex was not obligated to pay Waste Management until it had received payment from the County.

Handex filed a third-party complaint against the County, contending that any failure to pay Waste Management resulted from the failure of the County to pay Handex for all work performed; that the County had breached its contract with Handex; and that payment should be made in accordance with the truck count measure rather than the topographic survey method specified in the Contract.

The County filed a motion for summary judgment against Handex, contending, inter alia, that Handex had been paid in accordance with the terms of the Contract; that there were no genuine issues of material fact regarding the validity of the survey method of measurement that was specified in the Contract and that there was no evidence that the Contract had been amended or altered to provide a different method of calculating the waste removed from the site. Handex then filed a motion for partial summary judgment against the County, contending that the method of measurement set forth in the Contract was unreliable and that, therefore, the measure of the amount of waste excavated should be measured by a reasonably accurate alternative method.

In an extensive order, the trial court granted the County’s motion for summary judgment and denied Handex’s motion for partial summary judgment. Handex appeals. 3

1. Handex argues on appeal that the method of measurement specified in the Contract proved unreliable because the surveys upon which it was based were inaccurate, that using the topographic *287 survey method specified in the Contract results in a windfall to the County because it does not result in payment to Handex for all waste removed from the site and results in a violation of the term of the Contract which provides that Handex is to be paid for all work performed on the Project. In support of this argument Handex points to the evidence that it would be entitled to payment for excavating 130,719 cubic meters of waste using the truck count method, but only 80,181 cubic meters using the survey method. Handex also argues that a question of fact exists as to whether the parties intended that the Contract be modified so that the truck count method replaced the survey method as the measurement to be used in calculating the amount of waste removed from the Project. The County argues that the Contract provided that all modifications be in writing, and further that the evidence does not support Handex’s argument that the parties’ agreement to use the truck count method as an interim method of measurement creates an issue of fact concerning whether the parties agreed to use a different method of measurement to determine final quantities of the amount of waste removed from the site.

We agree with the trial court that the dispositive issue in this case is whether the Contract had been amended to provide for a different method of calculating the total volume of waste removed from the site. The trial court has crafted an extensive and well-reasoned order addressing these issues, and we adopt it as follows:

Handex... contends that the contract provision regarding the method of quantifying the amount of waste disposed was modified by mutual departure and the County has waived its right to enforce the contract provision requiring that all modifications be in writing. In support of this argument, Handex points to evidence that during the course of the project, the County agreed to make interim payments to Handex for waste disposal based upon truck counts although the contract specifically provided that payments for waste excavation would be based upon before and after topographic/planimetric surveys. The County however, asserts that the parties agreed only to utilize the truck count method for monthly progress payments and that final determination of the quantity of waste excavated would be based upon comparison of the topographic surveys as provided in the contract. In further support of their assertion that the terms of the contract regarding payment for waste excavation were not altered, the County points to the provision [of the Contract] requiring that all modifications be written: “No verbal agreement or conversation with any officer, agent, or *288 employee of Chatham County, Georgia, either before, during or after the execution of this contract, shall affect or modify any of the terms or obligations herein contained, nor shall such verbal agreement or conversation entitle the contractor or his subcontractors to any additional payment whatsoever under the terms of this contract. All changes to this shall be in writing and appended hereto. .. .”
Contractual provisions such as the foregoing have been held to be valid and enforceable. Gerdes v. Russell Rowe Communications, Inc., 232 Ga. App. 534, 536 (502 SE2d 352) (1998).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Georgia Department of Labor v. Rtt Associates, Inc.
786 S.E.2d 840 (Supreme Court of Georgia, 2016)
Rtt Associates, Inc. v. Georgia Department of Labor
775 S.E.2d 644 (Court of Appeals of Georgia, 2015)
RHL PROPERTIES, LLC v. Neese
668 S.E.2d 828 (Court of Appeals of Georgia, 2008)
Moore v. Comm'r
2007 T.C. Memo. 134 (U.S. Tax Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
602 S.E.2d 660, 268 Ga. 285, 268 Ga. App. 285, 2004 Fulton County D. Rep. 2242, 2004 Ga. App. LEXIS 890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/handex-of-florida-inc-v-chatham-county-gactapp-2004.