State Highway Department v. MacDougald Construction Co.

115 S.E.2d 863, 102 Ga. App. 254, 1960 Ga. App. LEXIS 598
CourtCourt of Appeals of Georgia
DecidedJuly 1, 1960
Docket38155
StatusPublished
Cited by15 cases

This text of 115 S.E.2d 863 (State Highway Department v. MacDougald Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Highway Department v. MacDougald Construction Co., 115 S.E.2d 863, 102 Ga. App. 254, 1960 Ga. App. LEXIS 598 (Ga. Ct. App. 1960).

Opinions

[256]*256Townsend, Judge.

Count 1 of the petition, which is the only count on which the plaintiff relies, seeks an ex contractu recovery of two amounts as follows: (1) The,sum of $35,157.76 admittedly retained by the defendant out of the contract price, and sought by the cross-action to be set off, except for the sum of $1,498.95, as liquidated damages incurred by reason of delays in performance; (2) The sum of $33,967.31, which represents the difference between the contract price based on percentages of rock and dirt to be found along the sites to be excavated as indicated by borings made by the defendant, and the actual amounts of rock actually found when the excavations were made. The theory under which the plaintiff proceeded for recovery was that he was entitled to this corrected figure because of a mutual mistake of fact made by the parties in regard to the original contract. As the plaintiff’s counsel succinctly states in his brief: “The plans as bid showed that 31.3% of the total excavation was rock. The rock as finally excavated was 36.2% of total excavation. The difference between these figures based on total excavation was 4.9%, but there was an 11% increase in rock alone. If plaintiff has no information concerning a job, plaintiff drills it. It did not drill this job because of preceding Expressway jobs where plaintiff had found defendant’s drilling figures to be accurate. Plaintiff sees no use in wasting money when it expected to find only what defendant found when it drilled. Plaintiff could not have bid on this job without having something on which to rely as to the amount of rock present, because the cost of removing rock is so much greater than that of removing dirt. The amount of rock is specifically stated in defendant’s plans on which it relied and bid. Plaintiff’s mistake was in accepting defendant’s figure as correct concerning the amount of rock and believing it to be true.”

Accordingly, if the petition shows on its face that the plaintiff is entitled to an alteration of the contract price based on mutual mistake of fact he is entitled, as to (b) supra, to prevail; otherwise not. Whether he is so entitled must depend upon the terms of his contract, as contained in the plans and specifications. The plans and specifications, which are exceed[257]*257ingly bulky, were not attached to the petition in the first instance although they form the basis of the contract sued on. The plaintiff subsequently amended his petition by stating: “Now comes the plaintiff and in this pleading makes profert of Standard Specifications for Construction of Roads and Bridges, Plans for Federal Aid Project No. FI-031-1 (2) CT. 1, the proposal and contract therefor, which are here to the court shown. All of the said documents were prepared by the defendant.” The court’s order reads as follows: “Allowed and ordered filed and to be considered a part of the record for purposes of demurrer.” Both parties, as well as the trial court, thereupon considered the plans and specifications as though the same had been in fact attached to the petition; they are before this court, and this court will also so consider them. Chicago Building & Mfg. Co. v. Talbotton Creamery &c. Co., 106 Ga. 84 (1) (31 S. E. 809).

Code § 20-308 provides: “If the consideration be founded in a mistake of fact or of law, the promise founded thereon cannot be enforced.” Under Code § 96-210, mistake of a material fact may in some cases justify a rescission of the contract; mere ignorance of a fact will not. “In all cases of a mistake of fact material to the contract or other matter affected by it, if the party complaining applies within a reasonable time, equity will relieve.” Code § 37-206. “Equity will not reform a written contract, unless the mistake is shown to be the mistake of both parties; but it may rescind and cancel upon the ground of mistake of fact material to the contract of one party only.” Code § 37-207. “If a party, by reasonable diligence, could have had knowledge of the truth, equity shall not relieve; nor shall the ignorance of a fact, known to the opposite party, justify an interference, if there has been no misplaced confidence, nor misrepresentation, nor other fraudulent act.” Code § 37-211.

In Hargrove v. Bledsoe, 78 Ga. App. 107 (50 S. E. 2d 223) it was held that in an action at law a plea based on the defense of mistake of fact must allege the mistake, and that there was no negligence on the part of the complaining party, as fully as though the petition were one in a court of equity, and the following was quoted from Langston v. Langston, 147 Ga. 318 (93 S. E. 892): “Where the terms of an instrument express [258]*258the intent of the parties at the time the contract is made, as they are then informed, in the absence of any allegation of fraud, misrepresentation, or misplaced confidence, equity will not interfere to relieve on' account of ignorance' of a fact by one of the parties, if by exercise of due diligence he might have ascertained the- truth.”

Testing the petition by the law relative to this subject matter, paragraph 10 recites: “In making its proposal and bid to defendant, petitioner bid for the removal of 241,113 cubic yards of rock, and defendant invited bids on the same basis, and petitioner did not test and could not reasonably have tested the rock that had to be removed, but was authorized to rely and did rely upon the representations of defendant in connection therewith, and there was a mutual mistake of fact between plaintiff and defendant, in the amount of the said excess stated above, with relation in the amount of rock that had to be removed in this construction.”

Section 2.06 of the specifications provided: “The bidder is required tó examiné carefully the site of, and the proposal, plans, specifications and contract form of the work contemplated and it will be assumed that he has judged for and satisfied himself as to the conditions to be encountered, as to the character, quality and quantities ■ of work to be performed and the materials to be furnished, and as to the requirements of these specifications, special provisions, and contract. No adjustments or compensations will be allowed for losses caused by failure to comply with the above requirements.” 'Section 2.05 provides: “The bidder’s attention is directed to the fact that the quantities of work to be performed and materials to be furnished to complete the construction of the project, as'indicated on the plans and contained in the ‘Proposal Form’ are considered as approximate and'are to be'used only for the comparison of bids. The department does not guarantee or assume any responsibility that the quantities indicated on the plans or given in the ‘Proposal Form’ will hold in the construction of the project, and the contractor shall not plead deception or misunderstanding because of the variation of these quantities, or variation from the location, character, or any other conditions pertaining there[259]*259to.” Section 104.05 provided: “The yardage of roadway and drainage excavation measured as provided above shall be paid for at the contract unit price per cubic yard for ‘Common Excavation’ . . . ‘Unclassified Excavation’ ... as the case may be, which price shall be full compensation . . Payment will be made under . . . Item No. 104-E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CRS Sirrine, Inc. v. Dravo Corp.
464 S.E.2d 897 (Court of Appeals of Georgia, 1995)
J. Mervin Harden v. Trw, Inc., a Corporation
959 F.2d 201 (Eleventh Circuit, 1992)
Medical Oncology Hematology Group, P. C. v. Goldklang
360 S.E.2d 41 (Court of Appeals of Georgia, 1987)
Hiers-Wright Associates, Inc. v. Manufacturers Hanover Mortgage Corp.
356 S.E.2d 903 (Court of Appeals of Georgia, 1987)
Jahncke Service, Inc. v. Department of Transportation
322 S.E.2d 505 (Court of Appeals of Georgia, 1984)
Codell Construction Co. v. Commonwealth
566 S.W.2d 161 (Court of Appeals of Kentucky, 1977)
Kingsbury v. Exxon Co., U. S. A.
220 S.E.2d 481 (Court of Appeals of Georgia, 1975)
Gilreath v. Argo
219 S.E.2d 461 (Court of Appeals of Georgia, 1975)
Knight Bros., Inc. v. State
199 N.W.2d 720 (Nebraska Supreme Court, 1972)
Peter Kiewit Sons' Co. v. Summit Construction Co.
422 F.2d 242 (Eighth Circuit, 1969)
St. Paul Fire & Marine Insurance v. Fleet Transport Co.
158 S.E.2d 476 (Court of Appeals of Georgia, 1967)
State Highway Department v. W. L. Cobb Construction Co.
143 S.E.2d 500 (Court of Appeals of Georgia, 1965)
State Highway Dept. v. Cobb &C. Co.
143 S.E.2d 509 (Court of Appeals of Georgia, 1965)
State Highway Department v. MacDougald Construction Co.
115 S.E.2d 863 (Court of Appeals of Georgia, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
115 S.E.2d 863, 102 Ga. App. 254, 1960 Ga. App. LEXIS 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-highway-department-v-macdougald-construction-co-gactapp-1960.