Chicago Building & Manufacturing Co. v. Talbotton Creamery & Manufacturing Co.

31 S.E. 809, 106 Ga. 84, 1898 Ga. LEXIS 24
CourtSupreme Court of Georgia
DecidedNovember 26, 1898
StatusPublished
Cited by21 cases

This text of 31 S.E. 809 (Chicago Building & Manufacturing Co. v. Talbotton Creamery & Manufacturing Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Building & Manufacturing Co. v. Talbotton Creamery & Manufacturing Co., 31 S.E. 809, 106 Ga. 84, 1898 Ga. LEXIS 24 (Ga. 1898).

Opinion

Cobb, J.

The petition of the Chicago Building and Manufacturing Company in substance alleged : It is a corporation, incorporated under the laws of the State of Illinois, and is a manufacturer, machinist, builder and contractor, and furnisher of materials. In 1895 it contracted with certain persons named, and the Talbotton Creamery and Manufacturing Company, all of said county. After the contract was made, the parties named were incorporated under the laws of Georgia as tire Talbotton Creamery and Manufacturing Company. The contract was made with the persons named and the company, for the purpose of building a creamery on a described lot in the town of Talbot-ton. The building was erected and fully equipped for a cream[85]*85ery at and for the sum of $3,950, all of which has been paid except $1,359.35; and for this sum the petitioner has taken no personal security. In June, 1895, petitioner completed the building • and creamery equipment and machinery, in compliance with its contract, and thereupon the defendant became indebted to it in the sum last above mentioned, besides interest. On September 25, 1895, and within three months of the completion of the work required under the contract, petitioner filed its claim of lien against the individual subscribers and the corporation, on the building and machinery furnished by it and upon the lot upon which the building was situated, and the same was recorded in the office of the clerk of the superior court as required by law. The action is commenced within twelve months from the time the debt .which is the foundation of the lien became due. The prayers are, that a lien on the building, machinery and lot be set up and established, and that process issue against the Talbotton Creamery and Manufacturing Company. The defendant demurred to the petition, on the ground that the allegations were insufficient in law to authorize the foreclosure of the lien as claimed, or to authorize a' recovery in the suit. The court sustained the demurrer and disfnissed the petition. The bill of exceptions sets out a copy of the contract between the parties, and states that in the argument upon the demurrer the defendant’s counsel used the contract “as a proferí.” The order of the judge sustaining the demurrer contains this clause: “Plaintiff’s counsel made profert of the written contract which was the foundation of the suit”; and it appears from the order that the judge treated the contract as a part of the petition. The contract referred‘to was, in substance, as follows: The plaintiff is referred to in the contract as the party of the first part, and the persons named in the petition as defendants are referred to as the party of the second part. The purpose of the contract is to provide for building, erecting, completing, and equipping for the party of second part a butter and cheese factory at or near Talbotton, Georgia. The character of the building and equipment of the factory is fully set forth. The party of the second part “agrees to select, describe, and furnish at its own expense, within ten days from [86]*86the date of this contract, suitable and reasonably level land with good title, and water ready to connect pump to for the use of said factory, and agrees within the same time to appoint an executive committee with full authority to represent second party’s interest while first is discharging said contract.” The party of the first part agrees to erect a butter and cheese factory as set forth in the specifications, for $3,950, payable in cash when the factory is completed. The party of the second part agrees to pay that amount when the factory is erected, and the building is to be completed within ninety days after the amount above mentioned is subscribed. As soon as that amount is subscribed, and within a reasonable time thereafter, the party of the second part agrees “to incorporate under the laws of the State, as therein provided, fixing the aggregate amount, of stock at not less than the amount subscribed, to be divided into shares of $100 each. Said share or shares, as above stated, to be issued to the subscribers hereto in proportion to their paid-up interest herein, and it is herein agreed that each stockholder shall be liable to the corporation only for the amount subscribed by him and no more.” Subscriptions to any amount in excess of the amount above uamed are authorized by the contract, but all such subscriptions “shall belong to the first party until the full contract price has been fully collected therefor. The remainder of the subscriptions, after the first party has been fully paid, is the property of the second party, and may then be by the second party also collected and used as working capital.” The contract is signed by the plaintiff company, and also by the persons named in the petition, in the following way:

Names of subscribers. ' . No. of shares. Amount of stock

after incorporation.

E. IT. Spivey 1 $100.00.

W. T. Cosby '. 2 $200.00.

W. C. Turner 1/2 $50.00.

Attached to the contract is a communication addressed to the plaintiff, signed by four persons styling themselves the “regularly appointed executive committee” of the party of the. second part, in which it is stated that a described tract of land has been selected by them upon which to erect the butter and [87]*87uheese factory, and that they have accepted the same as suitable for the purpose, and agree to indemnify plaintiff against all adverse claimants, and. authorize the plaintiff to proceed to erect the factory thereom according to the contract.

1. The first question to be determined is: Did the court have a right to consider this contract in. passing upon the demurrer filed to the petition? The contract is the foundation of the action. It is neither embodied in the petition, nor exhibited thereto, nor is a technical profert of the same made in the pleadings. It appears, however, distinctly from the record, that on the hearing an oral profert of the contract was made ; that it was produced; that it was read; that counsel for both parties argued the case upon the theory that the contract was a part of the pleadings, and that the ruling by the court was also based 'upon this assumption. While the contract did not come before the court and become a part of the record, in compliance with the technical rules of profert and oyer as they existed at common law, since the day of written pleading, still we are of the opinion that under the liberal, and we might say loose, practice which is allowable in this State, the contract was properly before the court, became a part of the petition, and was therefore properly considered by the court in passing upon the demurrer. While at common law profert was required only in cases where the party claimed or justified under a deed, and was npt necessary where the suit or defense .was founded upon an instrument not under seal, still the rule in this State requires that profert should be made of any note or other instrument which is the foundation of the action, whether the same be .under .seal or not. Steph. Plead. 67, 437; Smith v. Simms, 9 Ga. 418.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jackson v. Southern Pan & Shoring Co.
369 S.E.2d 239 (Supreme Court of Georgia, 1988)
Henderson v. Mitchell Engineering Co.
279 S.E.2d 750 (Court of Appeals of Georgia, 1981)
Rembrant, Inc. v. Phillips Const. Co., Inc.
500 F. Supp. 766 (S.D. Georgia, 1980)
Southwire Co. v. Metal Equipment Co.
198 S.E.2d 687 (Court of Appeals of Georgia, 1973)
St. Paul Fire & Marine Insurance v. Fleet Transport Co.
158 S.E.2d 476 (Court of Appeals of Georgia, 1967)
Woodside v. Fulton County
155 S.E.2d 404 (Supreme Court of Georgia, 1967)
Allen v. Arrow Contracting Co.
138 S.E.2d 600 (Court of Appeals of Georgia, 1964)
J. M. Wells Supply Co. v. Shiels
121 S.E.2d 36 (Court of Appeals of Georgia, 1961)
State Highway Department v. MacDougald Construction Co.
115 S.E.2d 863 (Court of Appeals of Georgia, 1960)
Ernest G. Beaudry Inc. v. Freeman
38 S.E.2d 40 (Court of Appeals of Georgia, 1946)
Rembert v. Ellis
17 S.E.2d 165 (Supreme Court of Georgia, 1941)
McEachin v. Kingman
12 S.E.2d 212 (Court of Appeals of Georgia, 1940)
Fidelity & Deposit Co. v. Fine
194 S.E. 58 (Court of Appeals of Georgia, 1937)
Cann v. Macon Academy Music Co.
142 S.E. 203 (Court of Appeals of Georgia, 1928)
Odum v. South Atlantic Casket Co.
117 S.E. 275 (Court of Appeals of Georgia, 1923)
Mann v. Showalter
88 S.E. 968 (Supreme Court of Georgia, 1916)
Florida Coca Cola Bottling Co. v. Ricker
71 S.E. 734 (Supreme Court of Georgia, 1911)
Mitchell v. Southern Railway Co.
45 S.E. 703 (Supreme Court of Georgia, 1903)
Norcross Butter & Cheese Manufacturing Co. v. Summerour
39 S.E. 870 (Supreme Court of Georgia, 1901)
Candler v. Kirkland
37 S.E. 715 (Supreme Court of Georgia, 1900)

Cite This Page — Counsel Stack

Bluebook (online)
31 S.E. 809, 106 Ga. 84, 1898 Ga. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-building-manufacturing-co-v-talbotton-creamery-manufacturing-ga-1898.