Heman Construction Co. v. Mason

212 P. 1089, 112 Kan. 648, 1923 Kan. LEXIS 454
CourtSupreme Court of Kansas
DecidedFebruary 10, 1923
DocketNo. 23,452
StatusPublished
Cited by1 cases

This text of 212 P. 1089 (Heman Construction Co. v. Mason) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Heman Construction Co. v. Mason, 212 P. 1089, 112 Kan. 648, 1923 Kan. LEXIS 454 (kan 1923).

Opinion

The opinion of the court was delivered by

BuRCH, J.:

The action is one of mandamus, to compel delivery to the plaintiff of two executed, registered, and numbered warrants, based on approved and audited vouchers, for the final portion of the contract price for the erection of a public' building at Emporia.

Originally the construction company sued the board of administration for the money now sought to be obtained through medium of the warrants. It was held the suit was against the state without its authority. (Construction Co. v. Board of Administration, 105 Kan. 291, 182 Pac. 386.) The construction company then brought this action, and the board of administration answered'the alternative writ. A statement of the issues thus made may be found in Construction Co. v. Mason, 109 Kan. 373, 374, 198 Pac. 966. A demurrer to the answer made the point that the answer must be established, if at all, by parole evidence, which would contradict the records made by the board of administration, the state auditor, and the state treasurer. In response to the demurrer, the court said:

“While these officers probably cannot dispute any statement contained in the record made by them, the state is not concluded by that record if it does not recite the facts. The state, on the relation of the attorney-general, in this or in an action commenced for that purpose, may question the correctness of - the record, and may procure a judgment preventing the delivery of the warrants if the facts alleged in the answer are true. The court therefore suggests that the state on the relation of the attorney-general intervene in this action and file such pleadings as may be necessary to enable the court to determine the truth of the matters alleged in the answer filed by the defendants.” (Construction Co. v. Mason, 109 Kan. 373, 375, 198 Pac., 966.)

The state on the relation of the attorney-general intervened. The intervening petition set up substantially the facts contained in [650]*650■the answer of the board of administration, and prayed for cancellation of the warrants. The Honorable Oscar Raines was appointed commissioner to take the evidence and report findings of fact and conclusions of law. Findings of fact favorable to the state were returned, together with a conclusion of law that the warrants should be canceled. The plaintiff excepted to the findings and the conclusion, and the case is now before the court for determination on the pleadings, the evidence, the commissioner’s report and the exceptions.

The plaintiff renews the contention made in support of the demurrer to the answer of the board of administration, and asserts the state is in no better position to resist delivery of the warrants than the board itself. The court decided the matter when it suggested intervention by the state, and does not propose to debate it further. The plaintiff can get an order from this court for payment to it, out of the state treasury, of $5,472.28, in just one way, and that is by proof of performance of contract entitling it to the money. A rule of evidence will not be accepted as a substitute for a cement floor in the building the plaintiff undertook to erect.

The specifications on which the plaintiff made its bid, and which became a part of the contract, contained the following provisions:

“Floor Finish.
“The floors of the front entrance corridor, first floor rotunda, platform at entrance to auditorium on first floor, side corridors on first floor back to east and west sides of pilasters at main stairways, and the first stair landing, are to be of tile. In these parts the top of the concrete slab is to be leveled off to lVi" below the finished floor level.
“The floors of all other corridors, stair halls, loggia, toilet and wash rooms, and wherever else cement floors are shown or marked on the plans, are to be' of cement put down by the Master Builders’ process as hereinafter specified; and in these parts the concrete is to be floated down to a level %" below the finished floor level.
“Cement Floors.
“This includes all parts before specified to have cement floors, also the balcony and stair treads. This cement finish is to be made and put on as follows:
“Application of Topping. — The topping, which shall consist of one part fresh cement to two parts coarse, gritty, clean sand, mix (1:1%), shall at no time be made sloppy. Lay and straight-edge the topping to a true and even surface. The topping shall then be well floated with wooden floats to close all voids and hollows.
[651]*651“The finish. — Then a dry mixture of one (1) part Master Builders’ Concrete Hardener and one (1) part of tested Portland cement (by weight), mixed to an even color, shall be sprinkled evenly over the surface. This shall be floated in thoroughly and troweled. A second troweling shall be given surface when it has set sufficiently to take a hard, smooth , finish. Under no circumstances shall the finish be applied when there is any sign of surplus water on the floated surface.
“The finish consumes approximately 15 pounds Master Builders’ Concrete Hardener and 15 pounds cement per 100 square feet.
“Coloring.
“The finish shall be colored to a dark red by troweling the coloring material into the finish before it is set up, applying as many coats as may be necessary to produce a thoroughly even, dark color.
“Workmen.
“This topping and finish are to be applied by workmen skilled in this kind of work, furnished by the Builders’ Material Supply Co., of Kansas City, Mo., or by some other company recommended by and under the directions of the manufacturers of this concrete hardener.
“Safeguarding the Floor. — After the topping has set up, the contractor shall cover it with a uniform layer of soft wood sawdust, shavings, or other suitable covering. This covering must not be applied until experiment shows surface hard enough to prevent covering from scratching or injuring the finish. Surface shall be kept wet for at least five days. Floors, if protected as above, will be ready for light traffic in a week, and for heavy traffic in three weeks, under favorable weather conditions.”

Workmen furnished by the Builders’ Material Supply Company applied topping and finish to the floors indicated. While the work was in progress, Lewis, superintendent of construction for the state, objected to Tate, superintendent of construction for the plaintiff, that the topping and finish were not being applied according to specifications. Lewis’ recollection is that both Tate and Heman were present when objection was made to the workmen who were doing the work. The workmen persisted. Lewis, doubtful of his authority to stop the work, notified Tate, Heman, and the workmen, that it would be a question whether they would get the floor off their hands.

The departure from the specifications consisted in this: The specifications required topping and finish -to be one-half inch thick, in order to bring the floor up to the floor level from the top of the cement slab. Instead of this, the topping was merely a “skim,” in some places thicker than others, but generally of eggshell thickness.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fulton v. Farmers National Bank
253 P. 561 (Supreme Court of Kansas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
212 P. 1089, 112 Kan. 648, 1923 Kan. LEXIS 454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/heman-construction-co-v-mason-kan-1923.