Schwartz v. Saunders

46 Ill. 18
CourtIllinois Supreme Court
DecidedSeptember 15, 1867
StatusPublished
Cited by35 cases

This text of 46 Ill. 18 (Schwartz v. Saunders) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schwartz v. Saunders, 46 Ill. 18 (Ill. 1867).

Opinion

Mr. Chief Justice Breese

delivered the opinion of the Court:

This was a petition to enforce a mechanic’s lien, filed in the Superior Court of Chicago, by Joseph Saunders against John J. Schwartz and Wilhelmina, his wife. On a trial by a jury, a verdict was found for the plaintiff, on which judgment was rendered, a new trial having been refused.

To reverse this judgment, the defendants bring the case here by appeal, and assign errors.

The building to be erected was of brick and of large dimensions, tall and narrow and long. The brick work was contracted to be done by another party, with whom it does not appear the plaintiff had any connection; he himself was to do all the carpenter’s and joiner’s work on and about the walls when they should be erected, and furnish the materials for the same, from time to time as the mason work progressed, and as by the progress of the same might be required, and was to receive therefor, wdien his work should be finally completed, five thousand three ^hundred and ninety-nine dollars and thirty-three cents; the Work to be done under the direction of superintendent Bauer* the architect of the building. Plaintiff was entitled to demand! and receive from the architect, from time to time, estimates! of the work done by petitioner on the building, and of V materials furnished, which estimates, on presentation to defen- y dant, were to .be immediately paid by him; the payments to j apply on the contract price, etc., and any balance remaining J when the work was fully completed, was then to be fully paid. The petitioner furnished the materials and did work on the . building, keeping pace with thé brick layers, until the 22d day • of October, 1866, at which time Ms bill amounted,, under the contract,* to about two thousand five hundred dollars, all having been done to the satisfaction of the arcMtect.

The petitioner applied on the 16th of October to the arcMtect for an estimate of the amount due Mm at that time under the contract, and received from Mm a written estimate or certificate, that he was then entitled to a payment of fifteen hmidreíLdüL la.rsmn the contract; fha±-h.e pr.es«BfeMriirrs~T;ertMeate-on and at differeixt-tim§s after its date, to the defendant and demanded payment, which was-i*efused.

On the Mght of the 21st of October, 1866jjM^buiMing,.not then Kavifig received the uppSFjoTsis, and being uncovered, was blown down by a Mgh'wind and destroyed.

The defendant Schwartz does not deny the presentation of tMs certificate and demand of payment on the day it was given by the arcMtect, but denies he refused to pay it, but says he was ready and willing to pay it, but desired the plaintiff to wait a few days to enable Mm to make the payment, and that plaintiff consented to wait until the Monday following, which would be the 22d of October, and he says that he would on that day have paid the amount of the certificate, had it not been that the plaintiff, without fault of the defendant, and "without excuse therefor, abandoned the work and refused to go on and complete his contract. The defendant admits the building wai blown down at the time stated, but through no fault of Ms, and id ' he is not responsible for the consequences. He admits the building became and was of no value, and if ever completed Would have to be almost entirely rebuilt; but he denies that the performance of the plaintiff’s .contract became thereby impossible, but that it was possible notwithstanding for the petitioner to do all the wood work necessary about the building and fully complete it according to the plans and specifications, and of , the dimensions and in the manner specified in the contract and to furnish the materials therefor, and to perform fully every part of his contract, and to complete all the carpenter’s and joiner’s work, including roofing and tinning, in accordance with the contract. And he insists, after the building was blown down, it was the duty of the plaintiff to go on with and complete and perform his contract according to its terms; all which he has refused to do.

This assumption by the defendant is the principal point in • his case. He contends, that when a party by his own contract creates a duty or charge upon himself, he is bound to make it good, if he may, notwithstanding any accident by inevitable necessity, because he might have provided against it in his contract.

We had occasion, in the case of Bacon et al. v. Cobb et al., 45 Ill. 47, to examine this principle, and find it as stated by counsel, and so are the authorities cited by him. The case of Tompkins et al. v. Dudley et al., 25 N. Y. 272, was where one had agreed to build a house on the land of another, and had substantially performed his contract, but had not completely finished the house nor delivered it, when it was destroyed by fire; he was held liable to an action by the owner for money advanced on the contract, and damages for its non-perform anee. Ho property vested in the building in the owner of the land until it was finished and delivered.

The case in 19 Pick. 275, Adams v. Nicholl, is to the same effect. The court say, after the conflagration the contractor might have proceeded under the contract, and if he had completed a house according to the terms of his agreement, the plaintiff would have been bound to perform his part of the stipulation ; clearly holding that having contracted to erect and finish the building and deliver it as such, he was not excused by its accidental destruction, from performance.

/ The case from 2 Kernan 99, Harmony v. Brigham, sustains / the same view, and so does the case of School District No. 1 v. Dauchy, 25 Conn. 530. That was a case where a party had agreed to build and complete a school house by the first Monday of May, and had nearly completed it on the 27th of April, when the building was destroyed by lightning, whereby, alone, he was prevented from performing his contract, which was absolute in its terms; the court held the non-performance was not excused by such destruction of the building.

The case of School Trustees of Trenton v. Bement et al., 3 Dutcher, (N. J.) 513, was where a contract was made to build and complete a building and find materials, for a certain entire price, payable in instalments as the work progressed. It was held, the contract was entire, and if the building, either by the fault of the builder, or by inevitable accident, was destroyed before completion, the owner could recover back the instalments he had paid, though the falling down and déstruction of the building was, in this case, by reason of a latent defect in the soil.

These, it may be said, are hard cases. Tet such is the stubbornness of the rule of law, when a party undertakes to do a thing, not of itself impossible, he must do it before he can have any advantage from the contract.

But a marked and controlling difference will be observed \ between the case before us and those cited, and that is, the plaintiff had not undertaken to erect and finish this building and deliver it. Nor was it possible, after its prostration, forV him to perform any part of his work until the walls were replaced, with which he had nothing to do—it was no part of his contract to build the walls, but only to put his materials and labor into and upon walls which the defendant was bound to prepare for the reception of the carpenter’s work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Evans
156 A. 139 (Supreme Court of Pennsylvania, 1931)
Smith v. Faust
92 Pa. Super. 267 (Superior Court of Pennsylvania, 1927)
F. M. Gabler, Inc. v. Evans Laboratories, Inc.
129 Misc. 911 (New York Supreme Court, 1927)
Ellis v. Simpson
202 N.W. 554 (Supreme Court of Iowa, 1925)
Cochran v. Hamblen
215 S.W. 374 (Court of Appeals of Texas, 1919)
Prather v. Latshaw
122 N.E. 721 (Indiana Supreme Court, 1919)
Tubbs v. Delillo
127 P. 514 (California Court of Appeal, 1912)
Kinzer Construction Co. v. State
125 N.Y.S. 46 (New York State Court of Claims, 1910)
Bailey v. Fredonia Gas Co.
109 P. 411 (Supreme Court of Kansas, 1910)
Krause v. Brd. of Trustees of the School Crothersville
65 L.R.A. 111 (Indiana Supreme Court, 1904)
Teakle v. Moore
91 N.W. 636 (Michigan Supreme Court, 1902)
Armijo v. Mountain Electric Co.
67 P. 726 (New Mexico Supreme Court, 1902)
Prendergast v. McNally
76 Ill. App. 335 (Appellate Court of Illinois, 1898)
Nonotuck Silk Co. v. Levy
75 Ill. App. 55 (Appellate Court of Illinois, 1898)
Chicago Edison Co. v. Huyett & Smith Manufacturing Co.
66 Ill. App. 222 (Appellate Court of Illinois, 1896)
Dolan v. . Rodgers
44 N.E. 167 (New York Court of Appeals, 1896)
Bratton v. Ralph
42 N.E. 644 (Indiana Court of Appeals, 1896)
Siegel, Cooper & Co. v. Eaton & Prince Co.
60 Ill. App. 639 (Appellate Court of Illinois, 1895)
Porter v. the Arrow Head Reservoir Co.
35 P. 146 (California Supreme Court, 1893)
Campbell v. Jacobson
34 N.E. 39 (Illinois Supreme Court, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
46 Ill. 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schwartz-v-saunders-ill-1867.