Dolan v. . Rodgers

44 N.E. 167, 149 N.Y. 489, 3 E.H. Smith 489, 1896 N.Y. LEXIS 730
CourtNew York Court of Appeals
DecidedMay 26, 1896
StatusPublished
Cited by68 cases

This text of 44 N.E. 167 (Dolan v. . Rodgers) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dolan v. . Rodgers, 44 N.E. 167, 149 N.Y. 489, 3 E.H. Smith 489, 1896 N.Y. LEXIS 730 (N.Y. 1896).

Opinion

Vann, J.

The referee found, upon evidence placing the facts beyond review in this court, that on the nineteenth of May, 1890, the defendant and a corporation known as the Buffalo & Geneva Railway Company entered into a written agreement whereby the former agreed to build ten sections of a railroad then in process of construction by the latter. The contract contained the following clause : “ Svh-contracts.— Contractors shall be required to give their personal attention and supervision to the work, and will not be allowed to subcontract the whole or any part of same without consent of the railway company having been given in writing thereto.”

In June, 1890, the plaintiff’s firm agreed verbally with the defendant to construct four of said sections at a stipulated price per cubic yard or other measure of quantity, and at the time both parties knew of said clause in the contract with the railroad company and that no consent to sub-let had been given. The plaintiff’s firm completed sections seven and eight, but did nothing upon sections nine and ten, because *491 they were prevented by the railroad company by virtue of said clause in its contract with the defendant. The value of the work done at this.time, at the rate of compensation fixed by the parties, was the sum of $4,135.14, of which the defendant paid to the plaintiff, prior to the stoppage of work, $2,650, and, after that, the further sum of $300. The defendant claims that the plaintiff should not recover the balance alleged to be due, but should pay damages for not completing the work, because the contract, although entire, was not performed. except in part, while the plaintiff claims that there was a valid excuse for non-performance of the part not done, because both parties contracted with reference to the possibility of interference by the railroad company.

Impossibility of performance is, in general, no answer to an action for damages for non-performance of a contract, provided the contingency was such as the promissor should have foreseen and provided against when he made the promise, nor will it permit a recovery for part performance of an entire contract. (3 Addison on Contracts, 1196, 8th ed.; 2 Parsons on Contracts, 672, 8th ed.) If, however, the impossibility arises, even indirectly, from the acts of the promisee, as, for instance, where one of the contracting parties so conducts himself as to subject the other to an action by some third person, if he duly performs the contract, it is a sufficient excuse for non-performance. (United States v. Peck, 102 U. S. 64; Gallagher v. Nichols, 60 N. Y. 438; European, etc., Mail Co. v. Royal Mail Steam Packet Co., 30 L. J. C. P. 247 ; 3 Addison on Contracts, 1194; Story on Contracts, sec. 976.) This is upon the principle that he who prevents a thing from being done may not avail himself of the non-performance, which he has, himself, occasioned, for the law says to him, in effect: “ This is your own act, and, therefore, you are not damnified.” ( West v. Blakeway, 2 M. & Gr. 751.)

In this case the defendant, by his contract with the railroad company, had given it the power to treat any sub-contractor, who entered upon its premises to build the road, as a trespasser, and to prosecute him accordingly. It is insisted that *492 the defendant thus, indirectly, stopped the work, himself, and created the impossibility that he now, in effect, invokes as an excuse for refusing further payment, although he has been paid by the company for all that was done by the plaintiff. This may be true, but we prefer to base our affirmance of the judgment upon another ground. We think that 'as both parties had in view the contingency that performance might not be permitted by the railroad company, it was an implied part of their contract that if such were. the result, both were to be released as to the future, but bound as to the past. Thus, where a contract provided that the defendant was to give to the plaintiff the use of a music hall upon a certain day, but before the day arrived the hall was destroyed by fire, it was said : “ There seems no doubt that where there is a positive contract to do a thing, not in itself unlawful, the contractor must perform it or pay damages for not doing it, although, in consequence of unforeseen accidents, the performance of his contract has become unexpectedly burdensome or even impossible. * * * But this rule is only applicable when the contract is positive and absolute, and not subject to any condition, either express or implied; and there are authorities which, as we think, establish the principle that where, from the nature of the contract, it appears that the parties must from the beginning have known that it could not be fulfilled unless, when the time for the fulfillment of the contract- arrived, some particular specified thing continued to exist-, so that when entering into the contract they must have contemplated such continued existence as the foundation of what was to be done, there, in the absence of any express or implied warranty that the thing shall exist, the contract is not to be construed as a positive contract, but as subject to an implied condition that the parties shall be excused in case, before breach, performance becomes impossible from the perishing of the thing, without default of the contractor.” (Taylor v. Caldwell, 32 L. J. Q. B. 164.) That case was made the basis of a judgment rendered by this court in an action involving the sale and delivery of *493 specified articles of personal property, under such circumstances that the title did not vest in the vendee, and it was held that, as the property was destroyed by an accident, without the fault of the vendor, so that delivery became impossible, the latter was not liable to the vendee in damages for the non-delivery, because the law implied a condition that the property should continue to exist. (Dexter v. Norton, 47 N. Y. 62.) So contracts for personal services requiring skill, which can only be performed by the person named, are held not of absolute obligation, under all circumstances, but subject to the implied condition that the person designated shall be able to perform at the time specified. (Spalding v. Rosa, 71 N. Y. 40.) Judge Allen, in delivering the opinion of the court in the case last cited, said: “ Both parties must be supposed to contemplate the continuance of the ability of the person whose skilled services are the subject of the contract, as one of the conditions of the contract.” (Id. p. 44.) Where a person guaranteed the payment of dividends by a corporation at a fixed rate for seven years, and before the expiration of that period the corporation was dissolved on the application of the attorney-general, it was held that the parties contracted upon the assumption of corporate existence during the time covered by the guaranty, and that the dissolution, by taking away for the future the whole consideration upon which the guaranty was based, relieved the guarantor from liability thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. McDonough
71 F.4th 909 (Federal Circuit, 2023)
Costantino v. City of Atlantic City
152 F. Supp. 3d 311 (D. New Jersey, 2015)
In Re Penn Traffic Co.
322 B.R. 63 (S.D. New York, 2005)
Keller v. California Liquid Gas Corporation
363 F. Supp. 123 (D. Wyoming, 1973)
Robel v. Highline Public Schools, District No. 401
398 P.2d 1 (Washington Supreme Court, 1965)
Robel v. HIGHLINE PUBLIC SCH. DIST.
398 P.2d 1 (Washington Supreme Court, 1965)
W. K. Ewing Co. v. New York State Teachers' Retirement System
14 A.D.2d 113 (Appellate Division of the Supreme Court of New York, 1961)
Minevitch v. Puleo
9 A.D.2d 285 (Appellate Division of the Supreme Court of New York, 1959)
Meyer v. Custom Manor Homes, Inc.
4 A.D.2d 488 (Appellate Division of the Supreme Court of New York, 1957)
Foutz v. Commissioner
24 T.C. 1109 (U.S. Tax Court, 1955)
Sly v. United States
125 F. Supp. 89 (E.D. Illinois, 1954)
Stockstrom v. Commissioner of Internal Revenue
190 F.2d 283 (D.C. Circuit, 1951)
Keifhaber v. Yannelli
75 A.2d 478 (New Jersey Superior Court App Division, 1950)
Parrish v. Wightman
34 S.E.2d 229 (Supreme Court of Virginia, 1945)
Mohrmann v. Kob
182 Misc. 571 (New York Supreme Court, 1944)
Chisholm v. Chisholm Construction Co.
298 N.W. 390 (Michigan Supreme Court, 1941)
Becker v. Bemis
104 F.2d 871 (Eighth Circuit, 1939)
Alamo Nat'l Bank v. Commissioner
36 B.T.A. 402 (Board of Tax Appeals, 1937)
In re Boardwalk Amusement Co.
247 A.D. 313 (Appellate Division of the Supreme Court of New York, 1936)
Larkin v. United States
78 F.2d 951 (Eighth Circuit, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
44 N.E. 167, 149 N.Y. 489, 3 E.H. Smith 489, 1896 N.Y. LEXIS 730, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dolan-v-rodgers-ny-1896.