Cook v. McCabe

10 N.W. 507, 53 Wis. 250, 1881 Wisc. LEXIS 258
CourtWisconsin Supreme Court
DecidedOctober 18, 1881
StatusPublished
Cited by29 cases

This text of 10 N.W. 507 (Cook v. McCabe) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cook v. McCabe, 10 N.W. 507, 53 Wis. 250, 1881 Wisc. LEXIS 258 (Wis. 1881).

Opinion

Cassoday, J.

Neither party offered to furnish materials, and rebuild and restore the portions of the building destroyed by the fire. On the contrary, each insisted upon the other suffering the loss. A large nunibér of cases are cited in support of the proposition ' that in case of an entire and indivisible contract for the building of a house for a specified sum, to be paid on its completion, and where the edifice is destroyed by fire during the progress of the work, the builder must bear the loss and be to the expense of repairing the damages. The principle underlying the proposition contended for, to a certain extent, is undoubtedly correct.

In Brecknock Canal Co. v. Pritchard, 6 Durnf. & East., 750, the bridge which the contractor agreed to build was . broken down by an extraordinary flood, and Kenyon, O. J., said: “If the defendants had chosen to except any loss of any kind, it should have been introduced into the contract by way of exception.” So it was held, on the authority of Lord Chief Justice Hale," that “ the lessee of a house, who covenants generally to repair, is bound to rebuild it if it be burned by an accidental fire.” Bullock v. Dommitt, id., 650. See Walton v. Waterhouse, 2 Saunders, 420; S. C., C Keble, 40; 2 Williams’ Notes to Saunders’ R., 826; McKenzie v. McLeod, 10 Bing., 385; Phillyps v. Stevens, 16 Mass., 238; Dermott v. Jones, 2 Wall., 1; Kramer v. Cook, 7 Gray, 550. So it has been held that, “ where a contract is made to build and completé a building and find materials for a certain entire price, payable in installments as the work progresses, the contract is entire; and if the building, either by fault of the *255 builder ol* by inevitable accident, is destroyed before completion, the owner may recover back the installments he has paid.” School Trustees of Trenton v. Bennett, 27 N. J. L., 513. So it has been held that non-performance by a builder, under such an entire contract, was not excused by the destruction of the building by lightning. School District v. Dauchy, 25 Conn., 530. So, where a person contracted to build a house on the land of another, and the house was, before its completion, destroyed by fire, without his fault, it was held that he was not thereby discharged from his obligation to fulfil his contract.” Adams v. Nichols, 19 Pick, 275.

Such cases are distinguishable from one where the contractor agrees to repair another’s house already built, and it burns before completion of the repairs. Lord v. Wheeler, 1 Gray, 282; Wells v. Calnan, 107 Mass., 517.

But the case at bar is not one of an entire contract to complete an entire building. It is more like Brumby v. Smith, 3 Ala., 123, in which it was held that “ where a workman agreed to complete the carpenter’s work on a house, and to receive a certain sum on the completion of the work, his employer furnishing the materials, and the house and materials were destroyed by fire, without the fault of the workman, the house being in the possession of the employer, held, that the workman could not recover a pro rata compensation for the work actually done.”

The opinion in that case is based upon Cutter v. Powell, 6 Durnf. & East, 320, and Menetone v. Athawes, 3 Burr., 1592. In Gutter v. Powell the sailor was to be paid the sum named, “ provided he proceed, continue, and do his duty on board for the voyage;” and that case, in the language of Allen, J., in Wolfe v. Howes, 20 N. Y., 200, “ is distinguishable in this, that by the peculiar wording of the contract it was converted into a wagering agreement, by which the party, in consideration of an unusually high rate of wages, undertook to insure *256 his own life, and to render, at all hazards, his personal services during the voyage, before the completion of which he died.” Lord Kenyon, in deciding Cutter v. Powell, refers to the peculiar terms of the contract, and says it was a kind of insurance.” Page 324. See Taylor v. Laird, 25 L. J. (Exch.), 329. In the other case refered to, Menetone v. Athawes, the shipwright took the ship to his own dock for repairs, the owner agreeing to pay a sum named for the use of the dock, and also for the repairs; and it was held that the value of repairs may be recovered though a ship be burnt in dock.”

In Niblo v. Binsse, 3 Abb. N. Y. Ct. Ap. Dec., 375 (S. C., 1 Keyes, 476), it was held that, “ if the owner of a building contracts for labor upon it, he is under an implied obligation to have the building ready and in a condition to receive the labor contracted for; and if, before the work is completed, the building is destroyed by fire, without the fault of. the contractor, the owner is in default, and the contractor can recover for all that was done up to the time of the fire.” In that case, as well as this, the time of performance had been extended by the mutual assent of the parties to the contract. Schwartz v. Saunders, 46 Ill., 18, was a case where “ the plaintiff entered into a contract with the defendant to do the carpenter work and furnish the materials therefor upon a brick building; the mason work was to be done by another and independent contractor. After the brick work was nearly completed and a part of the carpenter work done, the brick walls were blown down. Held, that the loss as to the carpenter work fell upon the defendant.” The court properly distinguished the case from some of the cases cited above, on the ground that “ the plaintiff had not undertaken to erect and finish this building and deliver it.”

In Rawson v. Clark, 70 Ill., 656, the contractors agreed to manufacture and put into a building then in process of construction, certain iron work, but were prevented from com *257 pleting their contract by the building being destroyed by fire without their fault; and the court held they could recover ,pro tanto, and without performing the balance of their contract.

Hollis v. Chapman, 36 Tex., 1, was a case where the plaintiff, a carpenter, undertook to furnish materials and do the wood work necessary to finish defendant’s brick building, and to turn over the building, complete, by a given day, for a specified gross sum. "When the plaintiff had nearly completed the work, the building was destroyed by fire, without his fault; and the court held that the plaintiff was entitled to recover for the materials furnished and work done by him. Stress was there laid upon the fact that the contract was conditional — that is, dependent upon the execution of another contract; and hence it was held to be apportionable, and the contractor entitled to a pro rata pay for his work.

Taylor v. Caldwell, 3 Best &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Evans
156 A. 139 (Supreme Court of Pennsylvania, 1931)
F. M. Gabler, Inc. v. Evans Laboratories, Inc.
129 Misc. 911 (New York Supreme Court, 1927)
Cochrane v. C. Hennecke Co.
202 N.W. 199 (Wisconsin Supreme Court, 1925)
Klas v. Kuehl
150 N.W. 973 (Wisconsin Supreme Court, 1915)
Taulbee v. McCarty
137 S.W. 1045 (Court of Appeals of Kentucky, 1911)
Kinzer Construction Co. v. State
125 N.Y.S. 46 (New York State Court of Claims, 1910)
De Wolf v. Wisconsin Lakes Ice & Cartage Co.
124 N.W. 297 (Wisconsin Supreme Court, 1910)
Keel v. . Construction Co.
55 S.E. 826 (Supreme Court of North Carolina, 1906)
Ganong v. Brown
40 So. 556 (Mississippi Supreme Court, 1906)
Halsey v. Waukesha Springs Sanitarium Co.
104 N.W. 94 (Wisconsin Supreme Court, 1905)
Krause v. Brd. of Trustees of the School Crothersville
65 L.R.A. 111 (Indiana Supreme Court, 1904)
Vogt v. Hecker
95 N.W. 90 (Wisconsin Supreme Court, 1903)
Comstock v. Fraternal Accident Ass'n
93 N.W. 22 (Wisconsin Supreme Court, 1903)
Teakle v. Moore
91 N.W. 636 (Michigan Supreme Court, 1902)
Atlantic & Danville Railway Co. v. Delaware Construction Co.
37 S.E. 13 (Supreme Court of Virginia, 1900)
Wunderlich v. Palatine Fire Insurance
80 N.W. 471 (Wisconsin Supreme Court, 1899)
Hysell v. Steeling Coal & Manufacturing Co.
33 S.E. 95 (West Virginia Supreme Court, 1899)
Hayes v. Gross
9 A.D. 12 (Appellate Division of the Supreme Court of New York, 1896)
Chicago Edison Co. v. Huyett & Smith Manufacturing Co.
66 Ill. App. 222 (Appellate Court of Illinois, 1896)
Dolan v. . Rodgers
44 N.E. 167 (New York Court of Appeals, 1896)

Cite This Page — Counsel Stack

Bluebook (online)
10 N.W. 507, 53 Wis. 250, 1881 Wisc. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cook-v-mccabe-wis-1881.