Atlantic & Danville Railway Co. v. Delaware Construction Co.

37 S.E. 13, 98 Va. 503, 1900 Va. LEXIS 70
Supreme Court of Virginia·Decided September 13, 1900·Published·Cited by 20 cases

Opinion

(The opinion was prepared by Judge Biely before his death, and subsequently adopted as the opinion of the court.)

Riely, J.*

An agreement in writing was entered into on August SO, 1894, between the Atlantic and Danville Bailway Company and Butherford & Brown, contractors, whereby the latter agreed and contracted to furnish all materials and labor for, and to construct, according to prepared plans and specifications, certain docks, piers, and warehouse, and to do certain dredging, for the said Bailway Company, at its western terminus at Norfolk, and to remove such old docks and pier work as was shown on the [505] plans by dotted lines. Tbe work was to be completed within four months from the date of the contract—to-wit, on December 30, 1894.

The contractors employed the Delaware Construction Comjrnny, as sub-contractor, to do the work, which it did not complete within the specified time, and does not claim to have done until about five months thereafter, until early in the following June.

This suit was brought by the Railway Company, among: other objects, to recover from the contractors damages for the delay in completing the work, and for the failure to complete the work as required by the contract; and the contractors sought by cross-bill to recover from the complainant the percentage of moneys withheld from them on the monthly estimates of the work as it progressed, compensation for alleged extra work done and materials furnished therefor at the instance and request of the Railway Company, and damages for the failure and refusal of the Railway Company to give them proper facilities for the performance of the work. Upon the hearing of the cause, the court below adjudged that the complainant company was indebted to the contractors in the sum of $7,324.47, with interest from June 7, 1895, and for this sum entered a decree against it in favor of the contractors.

From this decree an appeal was taken to this court by the Railway Company.

The first assignment of error is to the adjudication by the court that the Railway Company was not entitled to any compensation for the failure of the contractors to complete the work within the time prescribed by the contract; and the claim is made that the court should at least have allowed the Railway Company two sjjecific items of damage that will be hereinafter particularly referred to.

It cannot be well questioned, from the nature of the contract and the circumstances from which it arose, that time was an [506] important feature in the completion of the work, and that the Railway Company would be entitled to recover any damages it could satisfactorily prove, was the result of the failure of the contractors to complete the work within the time limit, provided such failure was not caused by the Railway Company.

The evidence in the case is very voluminous, and it is not practicable to go into a critical discussion of it within the limits of an opinion of reasonable length. We can only state the conclusion we have reached upon a careful perusal of it, and that is, that the delay was due to several causes, the many changes required by the Railway Company, through its officers, to be made in the execution of the work, the amount of dredging, which was not fixed by the contract, but merely estimated, and which turned out to be about double the amount of the estimate, but was mainly due, according to the preponderance of the evidence, to the interference by the Railway Company with the execution and progress of the work, by keeping possession of and continuing to use its property, whereon the improvements were being made. It was insisted in behalf of the Railway Company that such possession and use of its property was within the expectation and understanding of the parties, but it could not have been within their contemplation that there could be such retention and use of the property as to interfere with the progress of the work to such extent gs is shown by the evidence.

It is provided in the contract that “no claims for extra work or delay will be allowed, unless such extra work or delay is excessive; in such event, the engineer and contractors shall agree upon the compensation for extra work, and upon the extension of the time necessary to complete it.” It was claimed that no such agreement had taken place as was contemplated by the said provision, and strenuously .argued that therefore the contractors could not escape liability for damages for the failure to complete the work within the time limit. The above provision of the contract could not have been intended, and cannot be [507] construed, to cover a case of delay that resulted from the fault of the Railway Company. It cannot take advantage of its own wrong’. So much in response to the general claim of damages for delay.

The two specific, items for which damages were specially claimed are founded upon the evidence of the general freight agent of the company, who testified that the company had been put to extra expense to the amount of $3,066.18, owing to the non-completion of the work, in handling 11,793 bales of cotton, which reached West Norfolk after December 30, 1894, and that it had been also deprived of the sum of $3,525, which would have been the net revenue on a shipment of 15,000 bales of cotton that it had to decline because the work had not been completed. As to the first item, in addition to what has been said as to the responsibility of the Railway Company for the delay of the contractors in completing the work, the claim, of extra expense in handling the cotton referred to, even if it be admitted to be a proper ground of damage under the circumstances of this case, is not so satisfactorily proved by the evidence adduced in support of it that it can be said that the court below erred in refusing to allow it. As to the other specific item of damages claimed, it comes under the head of remote and speculative damages, and was properly disallowed. Burruss v. Hines, 94 Va. 413. It is altogether uncertain and wholly conjectural whether there would have been any gain or profit from the shipment of the^,000 bales of cotton.

It is also proper to add that the president of the Railway Company testified that he had no intention of claiming any damages for delay until in March or April. He also stated that he was fully acquainted with the affairs of the company, and that it handled all passengers and freight that came to it during the progress of the work, and refused no business offered to it on .account of the non-completion of the work within the time limit.

[508] It is next assigned as error that the court did not allow to the Railway Company damages growing out of the destruction of the warehouse and Pier Ho. 1 and the trestle alongside of the pier, hy fire, without the fault of either party, before the completion of the entire work, and which were not rebuilt by the contractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Atlantic & Danville Railway Co. v. Delaware Construction Co., 37 S.E. 13, 98 Va. 503, 1900 Va. LEXIS 70 (Va. 1900).

37 S.E. 13 (Atlantic & Danville Railway Co. v. Delaware Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

E. J. Miller Construction Co. v. Holt
56 Va. Cir. 153 (Roanoke County Circuit Court, 1998)
Taxson v. Taxson
30 Va. Cir. 134 (Fairfax County Circuit Court, 1993)
Starr Electric Co. v. Federal Insurance
20 Va. Cir. 405 (Richmond County Circuit Court, 1990)
McDevitt & Street Co. v. Marriott Corp.
713 F. Supp. 906 (E.D. Virginia, 1989)
United States v. Centex Const. Co., Inc.
638 F. Supp. 411 (W.D. Virginia, 1985)
Service Steel Erectors Co. v. SCE, INC.
573 F. Supp. 177 (W.D. Virginia, 1983)
"Automatic" Sprinkler Corp. of America v. Coley & Petersen, Inc.
250 S.E.2d 765 (Supreme Court of Virginia, 1979)
Marquette v. Housing Authority of Opelousas
137 So. 2d 374 (Louisiana Court of Appeal, 1962)
Buchanan v. Buchanan
6 S.E.2d 612 (Supreme Court of Virginia, 1940)
Quick v. Southern Churchman Co.
199 S.E. 489 (Supreme Court of Virginia, 1938)
Sinclair Refining Co. v. Hamilton & Dotson
178 S.E. 777 (Supreme Court of Virginia, 1935)
Commonwealth v. Evans
156 A. 139 (Supreme Court of Pennsylvania, 1931)
White v. Reed
135 S.E. 809 (Supreme Court of Virginia, 1926)
Eschner v. Eschner
131 S.E. 800 (Court of Appeals of Virginia, 1926)
Warren v. Goodrich
112 S.E. 687 (Supreme Court of Virginia, 1922)
Whitehead v. Syndicate
68 S.E. 263 (Supreme Court of Virginia, 1910)
Donaldson v. Sutherland Manufacturing Co.
1 Hosea's Rep. 114 (Ohio Superior Court, Cincinnati, 1907)